American Power Conversion PDRPPH1000, PD60H5HK1 manual Customizing and Updating the PDU

Page 54

Customizing and Updating the PDU

4.At the front of the PDU, connect the power cord’s individual wires:

a.If you have branch current monitoring installed, route the phase conductor through a current sensor.

b.Connect the line wire to the circuit breaker.

c.Connect the neutral wire to the closest open termination point on the Neutral Bar (N).

d.Connect the PE wire to the closest open termination point on the PE Bar (PE).

N

PE

46

60kW InfraStruXure PDU—Operation and Configuration

Image 54
Contents 60kW InfraStruXure PDU Page Audience How to find updates to this manualAbout This Manual Companion manualsPage Contents Overview Communication Configuration Product Information Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewInstallation/maintenance Total Power OffUnpacking/moving Emergency Power Off EPO Page PDU Display Interface       Top-level status screens Top-level menu screenNavigating through screens Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Input Contacts Contacts ScreenOverview Open or ClosedPDU Display Interface How to connect contacts to the PDU monitoring unit Breakers Screen Main InputEntire Log Alarms ScreenNew Logged Items Clear LogLoading Limits Global AlarmConfig Voltage LimitsPDU Alarms Alarm Condition ExplanationPanel Screen Branch Ckt LoadingBranch Ckt Limits Panel Configuration Associated circuit breakers occupying positions 08, 10,On the top right distribution panel Global Panel Config System/Network Config ScreenSystem Password Date/TimeOutput Config Electrical ConfigInput Config Manufacturer DataFactory Defaults Firmware UpdatesSystem ID Overview InfraStruXure PDUFront view Front view interior Rear view of PDU with transformer interior Rear view of PDU without transformer interior Arm/Test rocker switch PDU monitoring unitUser connection plate How to Apply Power to the System Power the PDU distribution circuit breakersSystem Operation How to Ensure Total Power Off For PDU with transformer Open turnInfraStruXure Manager Communication ConfigurationInfraStruXure PDU Management Options Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConfiguring the Network Management Interface Configuration OverviewConnect the InfraStruXure PDU to your network TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Local access to the control console Use apc for the User Name and PasswordRemote access to the control console Use apc for both User Name and Password Control consoleChoose Network from the Control Console menu Web interface Snmp FTP and SCP 60kW InfraStruXure PDU-Operation and Configuration Important Safety Instructions Customizing and Updating the PDUPower Cables PDU Orderable Part ListBreakers How to Add Circuit Breakers and Power Cables Add a power cable to the PDUAdd a circuit breaker on the PDU Customizing and Updating the PDU Overview How to connect contacts to the PDU monitoring unit How to Test the Emergency Power Off Switch Contact closure 24VAC 24VDC Contact closure is recommendedTesting the switch On the previous page for proper How to Download Firmware Upgrades Downloading firmware upgrades from a local computerUpgrading the PDU monitor processor Xmodem Page Specifications Electrical With Transformer Without TransformerCompliance InfraStruXure Standard Warranty Product InformationProduct Information APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to Contact APCAppendix a Changes in This Manual General changesChanges by page number Page Index SSH Page Page Page APC Worldwide Customer Support