American Power Conversion PD60H5HK1 manual System Operation, How to Apply Power to the System

Page 37

System Operation

How to Apply Power to the System

1. Close (turn ON) the main circuit breaker of the power source supplying power to the PDU.

2. Close (turn ON) the Main Input on the PDU.

3.Power the PDU distribution circuit breakers.

For PDUs with transformer:

a. Close (turn ON) the Main Output circuit breaker on the PDU.

Note: After the Main Output circuit breaker has been closed, both PDU distribution panels will be energized.

For PDUs with and without a transformer:

b. Close (turn ON) the PDU distribution panel circuit breakers.

When the distribution panel circuit breakers are closed, the PDU power cables and connected equipment are energized.

Note

60kW InfraStruXure PDU—Operation and Configuration

29

Image 37
Contents 60kW InfraStruXure PDU Page About This Manual How to find updates to this manualAudience Companion manualsPage Contents Overview Communication Configuration Product Information Safety symbols used in this manual SafetyCross-reference symbols used in this manual OverviewTotal Power Off Installation/maintenanceUnpacking/moving Emergency Power Off EPO Page        PDU Display InterfaceTop-level menu screen Top-level status screensNavigating through screens Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Overview Contacts ScreenInput Contacts Open or ClosedPDU Display Interface How to connect contacts to the PDU monitoring unit Main Input Breakers ScreenNew Logged Items Alarms ScreenEntire Log Clear LogConfig Global AlarmLoading Limits Voltage LimitsAlarm Condition Explanation PDU AlarmsBranch Ckt Loading Panel ScreenBranch Ckt Limits Associated circuit breakers occupying positions 08, 10, Panel ConfigurationOn the top right distribution panel Global Panel Config System Password Config ScreenSystem/Network Date/TimeInput Config Electrical ConfigOutput Config Manufacturer DataFirmware Updates Factory DefaultsSystem ID InfraStruXure PDU OverviewFront view Front view interior Rear view of PDU with transformer interior Rear view of PDU without transformer interior PDU monitoring unit Arm/Test rocker switchUser connection plate Power the PDU distribution circuit breakers How to Apply Power to the SystemSystem Operation For PDU with transformer Open turn How to Ensure Total Power OffInfraStruXure PDU Management Options Communication ConfigurationInfraStruXure Manager Network management interfacesConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConfiguration Overview Configuring the Network Management InterfaceConnect the InfraStruXure PDU to your network Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Use apc for the User Name and Password Local access to the control consoleRemote access to the control console Control console Use apc for both User Name and PasswordChoose Network from the Control Console menu Web interface Snmp FTP and SCP 60kW InfraStruXure PDU-Operation and Configuration Customizing and Updating the PDU Important Safety InstructionsPDU Orderable Part List Power CablesBreakers Add a power cable to the PDU How to Add Circuit Breakers and Power CablesAdd a circuit breaker on the PDU Customizing and Updating the PDU Overview How to connect contacts to the PDU monitoring unit Contact closure 24VAC 24VDC Contact closure is recommended How to Test the Emergency Power Off SwitchTesting the switch On the previous page for proper Downloading firmware upgrades from a local computer How to Download Firmware UpgradesUpgrading the PDU monitor processor Xmodem Page Electrical With Transformer Without Transformer SpecificationsCompliance Product Information InfraStruXure Standard WarrantyProduct Information Life-Support Policy APC Three-Phase SystemsHow to Contact APC How to Obtain ServiceGeneral changes Appendix a Changes in This ManualChanges by page number Page Index SSH Page Page Page APC Worldwide Customer Support