Cooper Bussmann CT02MAN manual Temperature Rise Test

Page 31
(also see Sections

Temperature Rise Test

Material Thickness: 0.125" Aluminum or 14 Gauge Steel

 

Cross Section Area,

 

 

 

 

 

13/16"

2 Rails:

 

 

 

 

 

 

4"

 

91/2"

 

Aluminum - 1.00 sq. in.

 

 

 

 

Steel - 0.76 sq. in.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3/8"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

41/2"

 

 

 

4"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

0.080" Aluminum or

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

14 Gauge Steel

Rigid

 

 

 

 

Adjustable Vertical

 

 

 

 

 

 

 

 

 

3/8" Bolting Hardware

 

Cable Tray Connectors

 

 

 

Cross Section Cable

 

 

 

 

 

 

 

 

Tray Side Rail

 

Insulated Joints

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fuse (if used)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

500 kcmil copper, Type RH Insulation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Current Source

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Cable Lug

 

 

 

T

 

 

 

 

 

T

 

 

 

T

 

 

 

Cable Lug

 

 

 

C1

 

 

 

C2

 

 

C3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

T - Temperature Measurement at each Tray Connection C1,

C2, & C3 - Cable Tray Connectors or Bonding Jumpers

Figure 1

(See Page 45 Appendix Sheet 1)

392.7.Grounding. (B) Steel or Aluminum Cable Tray Systems. (3) & (4)

For a cable tray to be used as an EGC the manufacturer must provide a label showing the cross-sectional area available. This also holds true for some mechanically constructed cable tray systems such as Redi-Rail®. Redi-Rail has been tested and UL Classified as an EGC. B-Line's label is shown at the top of page 30.

The cable tray system must be electrically continuous whether or not it is going to serve as the EGC. At certain locations (expansion joints, discontinuities, most horizontal adjustable splice plates, etc.), bonding jumpers will be required. Section 250.96. Bonding Other Enclosures states that cable tray shall be effectively bonded where necessary to assure electrical continuity and to provide the capacity to conduct safely any fault current likely to be imposed on them

99-40

1600 amps max.

99-N1

600 amps max.

99-1620

2000 amps max.

250.92(A)(1) & 250.118(12)).

It is not necessary to install bonding jumpers at standard splice plate connections. The splice connection is UL classified as an EGC component of the cable tray system.

NOTE: The NEC® only recognizes aluminum and steel cable trays as EGC’s. As with all metallic cable trays, stainless steel cable trays must be bonded according to NEC® guidelines. Fiberglass cable trays do not require bonding jumpers since fiberglass is non-conductive.

Cable Tray Manual

Cooper B-Line, Inc

29

Image 31
Contents Cable Tray Manual Page Table of Contents Introduction Cable Tray Safety Features WHY Cable TRAY?Cable Tray Space Savings Cable Tray DependabilityDesign Cost Savings Cable Tray Wiring System Cost SavingsMaterial Cost Savings Cost Cable Tray vs. Conduit Installation Cost Time SavingsMaintenance Savings Cooper B-Line, Inc Scope AN IN-DEPTH Look AT 2002 NEC Article 392 Cable TraySteel Ventilated Trough Center Supported Cable Tray Cable Tray Materials Uses Permitted. a Wiring MethodsDefinition. Cable Tray System Cable Tray Manual Uses Permitted. B In Industrial Establishments Uses Permitted. C Equipment Grounding Conductors 392.3B1a392.3B1b 392.3B1cSealing and Drainage. E Cable Seals, Class 1, Division 2 Uses Permitted. E Nonmetallic Cable Tray 502.4B3. Nonincendive Field WiringUses Not Permitted Construction Specifications. a Strength and RigidityCable Tray Manual Construction Specifications. E Fittings Construction Specifications. B Smooth EdgesConstruction Specifications. C Corrosion Protection Construction Specifications. D Side RailsInstallation. a Complete System Construction Specifications. F Nonmetallic Cable TrayNomenclature Installation. B Completed Before Installation Installation. D Covers Installation. C SupportsInstallation. F Cables Over Volts Installation. G Through Partitions and WallsInstallation. H Exposed and Accessible Installation. I Adequate Access Grounding. a Metallic Cable Trays EGC Grounding. B Steel or Aluminum Cable Tray Systems Temperature Rise Test Cable Installation. B Fastened Securely Cable Installation. a Cable SplicesCable Installation. D Connected in Parallel Cable installation. C Bushed Conduit and TubingSheet 3, Example 392.9A1 392.9A2 392.9E2 392.9F2 Single Diameter Inch Conductor Inches Channel Size AWG Technically Undesirable Installation Interpretation #1 Cable Tray Wiring System Design and Installation Hints Cable Tray Manual Cooper B-Line, Inc Cable Tray Maintenance and Repair Cable Tray AccessoriesFireproofing Cable Tray FRP Cable TRAY. Thermal Contraction and Expansion13B is 128 F. The 125 F line in Table Cable Tray Manual Cooper B-Line, Inc Appendix Pages See Page 29 for Temperature Rise Test illustration Circuit Arrangement for Rigid Conduit Temperature Rise Tests Example NEC .9A1 Example NEC .9A2 Example NEC .9A3 Example NEC .9B Appendix Sheet Start Sizing Cable Tray Per NEC Here Cable Tray Sizing FlowchartYes Ladder Or Vented Trough Fiberglass-Vinyl Ester Resin Project InformationLine Series Cable Channel Wire Basket TrayVentilated Non-Ventilated Cent-R-Rail Cooper B-Line, Inc Cable Tray Manual Line Wire Management Resources Ask the Experts