Linear SLC Mounting Pad Installation, Gate Preparation, Mounting Pad Specifications, Gate Post

Page 5

Mounting Pad Installation

The gate operator mounts bolted to a custom poured concrete mounting pad.. The pad supports the operator and prevents it from moving during operation..

An optional post mount kit is also available (P/N 2120-483) which allows installation without a concrete mounting pad..

Gate Preparation

Before installing the pad, make sure the gate rolls or slides freely, and that all exposed rollers are properly covered.. The gate must be covered with fabric with openings no larger than 2-1/4” in size, to a minimum height of 48” above ground level.. On picket-style gates, if pickets are spaced less than 2-1/4” apart, mesh is optional..

  WARNING 

The operator is intended for installation only on gates used for vehicles. Pedestrians must be supplied with a separate access opening. The pedestrian access opening shall be designed to promote pedestrian usage. Locate the gate such that persons will not come into contact with the vehicular gate during the entire path of travel of the vehicular gate.

  WARNING 

The gate must be installed in a location so that enough clearance is supplied between the gate and adjacent structures when opening and closing to reduce the risk of entrapment. Swing gates shall not open into public areas.

Mounting Pad Specifications

Recommended pad size is 21” x 21” minimum.. Pad depth should be set according to local codes and at least as deep as frost line.. 5/8” J-bolts may be set into the concrete before it sets following the dimensions shown, or drilled after the concrete sets..

GATE POST

 

10"

 

 

CHAIN LINE MUST BE IN

STRAIGHT LINE WITH OUTPUT

SPROCKET OF OPERATOR!

MAX GATE

OPENING

PAD MOUNT DETAIL

12"

FENCE LINE

11"5"

OPERATOR SHOWN WITH COVER REMOVED

COVER GATE WITH FABRIC WITH OPENINGS SMALLER THAN 2 1/4"

TO A MINIMUM HEIGHT OF 48" ABOVE GROUND, ON PICKET STYLE GATES, IF PICKETS ARE SPACED LESS THAN 2 1/4"

APART MESH IS OPTIONAL.

10"

12" 8"

GATE

5"

11" 2"

2-1/4"

3/4" DIA

OPENING

FOR

CONDUIT

MINIMUM PAD SIZE 21" WIDE X 21" DEEP PAD DEPTH PER LOCAL CODES AND FROSTLINE REQUIREMENTS

USE ROLLER COVERS

ON TOP AND BOTTOM

ROLLERS

PAD & CHAIN BRACKET

 

 

 

 

PLACEMENT

 

 

 

 

GATE

"A"

"B"

 

 

 

LENGTH

 

 

 

 

 

 

 

 

45 FT.

19"

12"

 

 

 

40 FT.

17"

10"

 

 

 

35 FT.

15"

8"

 

 

 

30 FT.

13"

6"

 

 

 

RECOMMENDED PAD AND

 

 

 

CHAIN BRACKET PLACEMENT

 

 

 

FOR PAD MOUNTING.

 

 

 

 

OPTIONAL POST MOUNT KIT

"A"

 

 

 

 

 

AVAILABLE: 2120-483

 

 

 

"B"

 

 

 

 

 

 

 

 

 

CHAIN SAG ALLOWABLE

 

 

 

 

 

1/4-3/8" PER FOOT OF CHAIN

 

 

 

 

Figure 1. Mounting Pad Specifications

 

SLR SLC SLD  Slide Gate Operator Installation Guide

- 3 -

227968 Revision X13 2-3-09

Image 5
Contents SLR SLC SLD Table of Contents Always Check the Gate’s Action Before You BeginRegulatory Warnings Gate Operator ClassificationsDC Control and Accessory Wiring Wiring SpecificationsAC Power Wiring Mounting Pad Specifications Mounting Pad InstallationGate Preparation Gate PostEND of Gate Pipe Shown Reference only Gate Bracket and Chain AssemblyOperator Preparation Operator SetupRIGHT-HAND Installation Limit Nuts Rough AdjustmentLimit Nuts Fine Adjustment Connectors Controller FeaturesBlinks if Connection has Failed Maint Alert SET Indicator DescriptionsTerminal Group Function Terminal DescriptionsOperator Accessory Connections Operator Accessory ConnectionsBasic Controller Programming Maximum Close Direction Current Setting Run Alarm and Pre-start AlarmMaximum Open Direction Current Setting Single Button Input Setup Entering Advanced Programming ModeAdvanced Controller Programming Maximum Run TimeReverse Delay Time Auxiliary Relay ModeLow Power Mode Power Failure ModeMaintenance Alert Trigger Reset Cycle CountSoft Start/Stop Duration Mid-travel Stop PositionAntenna Installation Radio EnableReset Controller to Factory Defaults Radio Transmitter LearnLoop Sealant Loop Layout IllustrationUSE Relief Cuts AT Corners SLR SLC SLD Safety Edge Layout Illustration Safety Edge Layout Illustration #2 Photoeye Installation Illustration Entrapment Zone #1 Pickets Space Smaller than 2 1/4Entrapment Zone #3 Gate Bracket Bolted to Channel Track Gate InstallationOpen and Close Limit settings Dual Gate InstallationsOperator #1 ShieldOperation Indications Gate OperationEntrapment Error IndicationsComm Link Connection Failure MGT Obstacle Transmitter TroubleTroubleshooting Optional Parts Model SLR Exploded ViewOptional Torque Limiter Model SLC Exploded ViewCapacitors For drives 34 to 47 feet wideLimiter Model SLD Exploded ViewModel SLD Mechanical Parts List Battery Maintenance Model SLD MaintenanceDC Motor Brush Replacement When NEWMonth Preventative Maintenance Preventative MaintenanceFCC Notice GeneralInstaller Customer Gate Operator Installation Checklist