Setup
Setup
Locate Reactor | Electrical Requirements |
1.Locate Reactor
•Two bolts through the 2 in. (50 mm) deep caster bushings in the rear.
•Two bolts through the
2.Do not expose Reactor
3.If you need to move the machine, add provided casters.
4.Lift with hoist only from bar spanning across top of cart.
Determine Power Source
Reactor
•230 Volt / 1 Phase
•230 Volt / 3 Phase Delta
•380 Volt / 3 Phase WYE
(220 Volts to Neutral)
Improper wiring may cause electric shock or other serious injury if work is not performed properly. Have a qualified electrician connect power and ground to main power switch terminals. Ensure your installation complies with all National, State, and Local safety and fire codes.
Also ensure that incoming power is disconnected and locked out at the source.
NOTICE
Ensure main power source meets all electrical requirements specified on nameplate of proportioning unit. Also ensure main power source has a dedicated fuse disconnect. Power cord is not supplied.
14 | 311511G |