Graco 311511G Initial Startup, Fluid Temperature Sensor FTS Calibration

Page 21

Initial Startup

Do not operate Reactor without all covers and shrouds in place.

Fluid Temperature Sensor (FTS) Calibration

Calibrate the FTS ONLY at initial startup (the first time the unit is operated) and any time the hose length changes.

1.Before turning on the unit, ensure all hoses and cables are properly connected. To ensure that the FTS in the hose is at the same temperature as the heaters, keep heat off and store the hose FTS near the machine for several minutes.

2.While holding down the temperature unit button (Fahrenheit - “F” or Celsius - “C”) turn the Reactor main power ON.

3.Hold the temperature unit button until temperature is shown on the display. The fluid temperature sensor is now correctly calibrated.

Initial Startup

3.Turn both PRESSURE RELIEF/SPRAY valves (SA, SB) to SPRAY.

SB

SA

ti8442a

4.Open both fluid valves (FV).

FV

ti8449a

5.Start feed pumps. Do not start proportioner air motor or pumps.

Load Fluid with Feed Pumps

The Reactor is tested with oil at the factory. Flush out the oil with a compatible solvent before spraying; see page 13.

1.Check that Setup process is complete; see page 14.

2.Turn on component B agitator, if used.

Always provide two grounded waste containers to keep component A and component B fluids separate.

6.Hold gun fluid manifold over two grounded waste containers. Open fluid valves A and B until clean, air-free fluid comes from valves. Close valves.

TI2484a

311511G

21

Image 21
Contents Reactor A-20 Related Manuals ContentsProportioner 50 ft 15 m 10 ft 3 m SystemsPart ApprovalsElectric Shock Hazard Fire and Explosion Hazard Moving Parts Hazard Key for FIG Typical Installation, without CirculationTypical Installation, with Circulation Foam Self-Ignition Moisture Sensitivity of IsocyanatesIsocyanate Hazard Keep Components a and B SeparateComponent Identification Typical InstallationKey AP Park/Run Switch Controls and IndicatorsFlushing Pressure Relief ProcedureSetup Determine Power SourceLocate Reactor A-20 Electrical Requirements Step One Connect Electrical Cord Configure to Supply PowerTerminal Blocks Power Jumper LocationGround System Iso Pump Lubrication System SetupFluid Supply Connections Air Supply ConnectionConnect FTS and Heated Dual Whip Hose Connect Heated Hose Recirculation / Pressure Relief LinesClose Gun Fluid Manifold Valves a and B Connect Whip Hose to Gun Fluid ManifoldPressure Check Hose Fluid Temperature Sensor FTS Calibration Initial StartupLoad Fluid with Feed Pumps Digital Temperature Controllers To change or enter the set point, proceed as followsA1 A2 A3 To change back to Fahrenheit units To change to Celsius unitsOver Temperature Alarms Fluid Heater Temperature OffsetHose Heat Manual Mode Supply Wet-Cups with Throat Seal Liquid Spray Spraying SetupSpray Adjustments Shutdown Operation Daily Start-up ProcedureTi2414A Circulation Through Reactor Fluid CirculationCKN Circulation Through Gun ManifoldMaintenance Category Data Technical DataTechnical Data 311511G Graco Information Graco Standard Warranty