Sterling SSV 05/2R operating instructions

Page 27

L

SSV 05/2R

Disconnect the equipment from mains supply before starting maintenance procedures to ensure that it cannot be switched on unintentionally.

Depressurize all compressed air piping of the equipment be- fore starting maintenance work.

F

Please observe the maintenance intervals.

Before starting maintenance work, clean the equipment of oil, fuel or lubricants.

Ensure that materials and incidentals required for operation as well as spare parts are disposed of properly and in an en- vironmentally sound manner.

Use only original Sterling spare parts.

Keep record of all maintenance and repair procedures.

SM4-610

Maintenance 26

Image 27
Contents Sterling Material Processing Operating Instructions Single Conveyor Unit SSV 05/2RTechnical service SSV 05/2R Sterling Material ProcessingEdition 08/99 SSV 05/2R Parts and Service Department Table of contents SSV 05/2R Technical data Safety instructions Safety instructionsSSV 05/2R SSV 05/2R Explanations and information SSV 05/2R For your safety SSV 05/2R SSV 05/2R SSV 05/2R For the safety of the units Installation instructions SSV 05/2R General information SSV 05/2R Installing the conveyor hopper SSV 05/2R Installing the control and maintenance unit SSV 05/2R Connecting the compressed-air supply SSV 05/2R Electrical connection Functional description SSV 05/2R Method of functioning Control and maintenance unitSet-up SSV 05/2R Preparations Setting the mixing ratio of the componentsFilling level too high Filling level too lowSet-up Maintenance SSV 05/2R Maintenance intervals Disassembly SSV 05/2R Cleaning/replacing the filter cartridgeAdjusting the level probe SSV 05/2R AssemblyTest steps SSV 05/2R Trouble-shooting Problem RemedyTechnical data SSV 05/2R Dimension sheet SSV 05/2R Spare parts list SSV 05/2R Pos ID-No Designation