Maytag W10097000A-SP, W10096984A, MGDX600XW Dryer gas pipe, Burner input requirements

Page 9

Option 1 (Recommended Method)

Flexible stainless steel gas connector:

■■ If local codes permit, use a new flexible stainless steel gas connector (Design Certified by the American Gas Association or CSA International) to connect your dryer to the rigid gas supply line. Use an elbow and a 3/8" flare x 3/8" NPT adapter fitting between the stainless steel gas connector and the dryer gas pipe, as needed to prevent kinking.

Option 2 (Alternate Method)

Approved aluminum or copper tubing:

■■ Lengths over 20 ft. (6.1 m) can use 3/8" approved tubing (if codes and gas supplier permit).

■■ If you are using Natural Gas, do not use copper tubing.

■■ 3/8" flare x 3/8" NPT adapter fitting between dryer pipe and 3/8" approved tubing.

■■ Lengths over 20 ft. (6.1 m) should use larger tubing and a different size adapter fitting.

■■ If your dryer has been converted to use LP gas, 3/8" LP compatible copper tubing can be used. If the total length of the supply line is more than 20 ft. (6.1 m), use larger pipe.

NOTE: Pipe joint compounds that resist the action of LP gas must be used. Do not use TEFLON®† tape.

Dryer gas pipe

■■ The gas pipe that comes out through the rear of your dryer has a 3/8" male pipe thread.

29" Wide Model

1¼"

(32 mm)

A9¼" (235 mm)

A.3/8" NPT dryer pipe

27" Wide Model

*5 3/4"

 

 

 

 

 

A

 

 

 

 

 

 

 

 

 

 

(159 mm)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1 1/2"

(38 mm)

A. 3/8" NPT dryer pipe

Burner input requirements

Elevations up to 10,000 ft. (3,048 m):

■■ The design of this dryer is certified by CSA International for use at altitudes up to 10,000 ft. (3,048 m), above sea level at the B.T.U. rating indicated on the model/serial number plate. Burner input adjustments are not required when the dryer is operated up to this elevation.

Elevations above 10,000 ft. (3,048 m):

■■ When installed above 10,000 ft. (3,048 m) a 4% reduction of the burner B.T.U. rating shown on the model/serial number plate is required for each 1,000 ft. (305 m) increase in elevation.

Gas supply pressure testing

■■ The dryer must be disconnected from the gas supply piping system during pressure testing at pressures greater than 1/2 psi.

Electrical Requirements

WARNING

Electrical Shock Hazard

Plug into a grounded 3 prong outlet. Do not remove ground prong.

Do not use an adapter.

Do not use an extension cord.

Failure to follow these instructions can result in death, fire, or electrical shock.

■■ 120 Volt, 60 Hz., AC only, 15- or 20-amp fused electrical supply is required. A time-delay fuse or circuit breaker is recommended. It is also recommended that a separate circuit serving only this dryer be provided.

GROUNDING INSTRUCTIONS

For a grounded, cord-connected dryer:

This dryer must be grounded. In the event of malfunction or breakdown, grounding will reduce the risk of electric shock by providing a path of least resistance for electric current.

This dryer is equipped with a cord having an equipment- grounding conductor and a grounding plug. The plug must be plugged into an appropriate outlet that is properly installed and grounded in accordance with all local codes and ordinances.

WARNING: Improper connection of the equipment- grounding conductor can result in a risk of electric shock. Check with a qualified electrician or service representative or personnel if you are in doubt as to whether the dryer is properly grounded. Do not modify the plug provided with the dryer: if it will not fit the outlet, have a proper outlet installed by a qualified electrician.

SAVE THESE INSTRUCTIONS

†®TEFLON is a registered trademark of E.I. Du Pont De Nemours and Company.

9

Image 9
Contents Gaz É.-U. et Canada et Électrique Canada uniquement Table of Contents Table des matièresYour safety and the safety of others are very important Dryer SafetyWhat to do if YOU Smell GAS Tools needed for all installations Installation RequirementsTools needed for gas installations Tools and PartsParts supplied Location RequirementsParts needed You will needWide Models Dryer Dimensions Installation clearancesInstallation Spacing Installation spacing for recessed area or closetElectrical Requirements Install Leveling LegsPrepare dryer for leveling legs It is your responsibilityGAS Dryer Power Hookup Gas Supply RequirementsScrew in leveling legs Burner input requirements Dryer gas pipeVenting Requirements VentingOptional exhaust installations Recommended exhaust installationsAlternate installations for close clearances Plan Vent SystemVent System Chart Install Vent SystemVent System Chart Wide Long Vent Models Only Install exhaust hoodConnect Vent Make Gas ConnectionTighten and adjust leveling legs Complete Installation ChecklistLevel Dryer Reverse Door Swing OptionalRemove bottom screws Place towel on dryerLift door off top screws Remove and transfer hinge hole plugsRemove screws from door Remove screws from hingesRotate outer door Super Wide Side-Swing DoorAttach door hinges Flip door over Remove door strikeWide Model Side-Swing Door Remove door strike plug Remove bottom screwsRemove screws from door Attach door hinges Flip door overRemove and transfer plugs Troubleshooting Sécurité de la sécheuse QUE Faire Dans LE CAS D’UNE Odeur DE GAZ Exigences D’INSTALLATION Outils nécessaires pour toutes les installationsOutillage et pièces Outils nécessaires aux installations au gaz Exigences d’emplacementPièces fournies Pièces nécessairesEspacement pour une installation Espacements d’installation’est à l’utilisateur qu’incombe la responsabilité de Spécifications électriquesRaccordement D’UNE Sécheuse À GAZ Installation des pieds de nivellementSpécifications de l’alimentation en gaz Préparer la sécheuse pour les pieds de nivellementExigences concernant le raccordement au gaz Canalisation de gazCanalisation d’arrivée de gaz de la sécheuse Caractéristiques d’alimentation du brûleurÉpreuve sous pression de lalimentation en gaz Altitudes supérieures à 10 000 pieds 3 048 mClapets de décharge Exigences concernant levacuationConduit métallique rigide Brides de serrageInstallations dévacuation facultatives Installations dévacuation recommandéesInstallations alternées pour dégagements étroits Planification du système d’évacuationTableau des systèmes d’évacuation Dispositions spéciales pour les maisons mobilesDéterminer l’itinéraire d’acheminement du conduit Raccordement au gaz Installation du circuit d’évacuationRégler l’aplomb de la sécheuse Déplacer la sécheuse à son emplacement finalRaccorder le conduit d’évacuation La bouche d’évacuationInversion du sens de l’ouverture de la Porte facultatif Achever l’installation liste de VérificationPlacer une serviette sur la sécheuse Modèle large avec porte à grande ouverture latérale deSoulever la porte pour la dégager des vis supérieures Contrôler l’alignement de la gâche de la porte Ôter les vis inférieuresPorte à très grande ouverture latérale de Ôter les vis des charnières Faire pivoter la porte externe Ôter les vis du panneau de porteRetourner la porte Retirer la gâche de porte Modèle large avec porte à ouverture latérale de Retirer le bouchon d’obturation de la gâche de porteFixer les charnières de porte Ôter les vis des charnières Retourner la porteDépannage Page W10096984A W10097000A-SP