Graco 3A1163A Connect EasyKey to Fluid Station Control, EasyKey Connections and AC Power Switch

Page 22

Electrical

 

 

AC Power

Fiber Optic Strain

Audible Alarm

Switch

Relief Port

 

 

Main Power

Access Port

Ground Screw

I/S Power

Graco Web

Discrete I/O Cable

 

 

 

Interface

Connector Ports

 

 

 

 

TI12638a

TI12657a

FIG. 10. EasyKey Connections and AC Power Switch

Connect EasyKey to Fluid Station Control

There are two 50 ft (15.2 m) cables to route between the EasyKey and Fluid Station Control: the Fluid Station Power Cable and the Fiber Optic Cable.

1.Connect the appropriate Fluid Station Power Cable end to the EasyKey connector VDC . See FIG. 10.

2.Connect the other cable end to the Fluid Station

Control connector VDC (J10). See FIG. 11.

3.The Fiber Optic Cable is shipped from the factory

attached to the EasyKey connector . See FIG. 10.

NOTE: If you need to detach the Fiber Optic Cable from the EasyKey, note how the cable is routed inside the enclosure. Ensure that the door can swing open and close without catching or pulling wires.

4.Route the opposite Fiber Optic Cable end through

the Fluid Station strain relief connector . Do not route the cable with tight bends or kinks.

NOTE: The fiber optic cable has a minimum bend radius of 1.6 in. (40 mm).

5.Connect the blue and black cable connectors to the matching connectors on the fluid station circuit board. See FIG. 11. Insert the cable connectors until they bottom out (approximately ¼ in. [6 mm]), then tighten the threaded connector.

NOTICE

To avoid cracking the circuit board, do not over-tighten or cause excessive stress on the circuit board con- nector.

6. Tighten the strain relief connector .

22

3A1163A

Image 22
Contents ProControl 1KS II 2 GContents Related Manuals Equipment ApprovalsModels System Configuration and Part NumbersLabel Location on EasyKey Feature AccessoryFire and Explosion Hazard Skin Injection Hazard Toxic Fluid or Fumes Hazard Important Two-Component Material Information Component Identification and Definition Component Description Fluid Manifold FM Control Box Power Supply Cable PS Flow ControlAssembly FC Pneumatically Operated Dose Valve for component aLocation Requirements Intrinsically Safe Installation RequirementsLocation Optional CablesNON-HAZARDOUS Hazardous Classified Location Location only Requirements onGeneral Information See Dimensions and Mounting Hole Layouts,Wall Mounting ProControl 1KS System Layout Drawing Wall Mounting Requirements See the System Pneumatic Schematic onAir Supply Air ConnectionsFluid Supply Fluid ConnectionsColor Change Board and Solenoid Valves Color Change Valve Stack TI11668aRegulator Fluid Air Fluid Out FC Cable Flow Control RegulatorRequirements Connect Main Power ElectricalEasyKey Connections and AC Power Switch Connect EasyKey to Fluid Station ControlFluid Station Board Connections Connect Color Change Module Color Change Board Switch Settings Two Color Change BoardsOne Color Change Board J11 IG . Color Change Board Switches S3-S6 Switch S3-S6Positions Wiring Diagram Grounding Check ResistanceEasyKey Display Control Box RobotSchematic Diagrams System Pneumatic SchematicSystem Electrical Schematic Non-Hazardous AreaHazardous Area Dimensions and Mounting Hole Layouts Wall Panel Mounting bracket onlyEasyKey Flow Control Module Air Supply ControlDimensions and Mounting Hole Layouts Technical Data Maximum fluid working pressure Maximum working air pressureGraco Standard Warranty Graco Information