1.1.4Installing hull unit on retraction tank

After welding the retraction tank and allowing sufficient time for cooling, install the hull unit as follows.

1.Clean the hull unit flange, the O-ring and O-ring groove. Coat them with a slight amount of grease. Place the O-ring in position on the tank flange.

2.Orient the hull unit so that the bow mark (inscribed) on its flange points toward the ship’s bow. Note that heading adjustment in the display unit is required if the bow mark does not face the ship’s bow.

3.Confirm that the O-ring is in position. Place the hull unit on the tank.

4.Coat every bolt, washer and nut with a slight amount of grease to ease removal. Fasten the hull unit to the retraction tank with flat washers, spring washers and hex bolts.

5.Reinforce the hull unit against vibration by extending stays to the ship’s hull from the two eye bolts at the top of the hull unit, referring to the figure at the top of page 1-7.

1-5

Image 13
Contents Check List Iii00080916714 Safety Instructions Projected Raising Lowering Mm stroke Max kt Standard type System ConfigurationControl Unit Black box typeStandard supply Equipment ListsSEM-21Q OptionsLocation of hull unit Mounting the Hull UnitMaintenance space, example sonar compartment Shortening the retraction tank Retraction tank Reinforcement rib 250-300 mm Remarks for installation of retraction tankInstalling hull unit on retraction tank Installation of hull unit Bow Stay Hull Unit Installing stays anti-vibration measureProcessor unit Mounting the Display UnitMonitor unit Mounting procedureMonitor unit Attaching the CRT filter Control unitFixing without KB fixing plate KB fixing plate Mounting the Transceiver Unit Mounting the Power Supply UnitGrounding the Equipment Procedure Page Mounting the Cable for Extension Kit option Attachment Kit option Using the optional attachment kit How to use the crimping tool How to Use the Crimping Tool, Pin ExtractorHow to use the pin extractor Local supply Location of ConnectorsTransceiver unit side Fabrication of monitor cable 10S2074 10 m/10S2075 30 m Monitor UnitPositioning guide pins Control cable Assembling D-SUB connector CN-A302How to connect cables to the monitor unit 1 10S1258-1 cable Processor UnitPower cable Monitor cable 10S2074 or 10S2075 Optional equipment Schematic view of cablesGyro Processor EXT-KPunit Transceiver Unit Fabrication of connector 00-8016-038-313761HV CN-B101Hull control cable 10S2078 Fabrication of power cable type DPYCY-4 TB-B101Connection Cable for Extension Kit Power Supply UnitJunction box Cable clamp CKS clamp Raise/Lower Control Box Power cable fabrication Adjustment and Check Test Menu OFF Heading adjustment Heading AdjustmentSystem menu OWN Ship Mark menu Configuring Own Ship MarkTD Position Other System Menu Items Interface Setting menuSpeed & Course EXT Data Setting menuWind Others menuLanguage Adjustment of signal level echo sounder connected Cone Board Setting in the Processor UnitAdjusting the volume of audio alarm 1 CIF2/NMEA2 connector interface selection DIP Switch SettingSelecting the Net Sonde information Selecting echosounder signalTesting TX/RX independently at hull unit This page is intentionally left blank Connecting the External Interface CS-120A VH4P PP GND Ciftxdh Ciftxdc Cifrxdh Cifrxdc Shield Check List Data Sheet Data Sheet Dispaly Unit FSV-2400 User menu Color response curve sheet H 工事材料表 006-921-240-00 10CO-X-9402 006-921-250-00 10CO-X-9403 10CO-X-9412 Page 10CO-X-9406 10CO-X-9410 Furuno Electric CO .,LTD C1318-M10-C 付属品表 Page Page Page 000-144-382-00 000-155-839-10 000-157-497-10 Page Page Page Page Page Page Jan Jan Hatai Hatai Page Page Page Color Scanning Sonar Title FSV-24/24S Miyosi 制御部