Installation (for qualified installers only)

Corner Installations - Top Vent Configuration

A typical 45° installation uses the framing dimensions shown in the illustration below (NOTE: all clearances still apply)

Minimum 1/2" Clearance

15-1/2"

48" Min.

© Travis Industries

4080214

100-01182_003

Image 16
Contents HH Fireplace Overview Listing DetailsIAS Icbo Approval Massachusetts ApprovalTable of Contents Safety Precautions Safety WarningsSafety Precautions Heating Specifications Installation OptionsDimensions Installation Overview Recommended Installation ProcedurePacking List Additional Items RequiredMassachusetts Requirements Requirements for the Commonwealth of MassachusettsTop Vent or Rear Vent Configuration Converting Fireplace to Top Vent ConfigurationConverting the Fireplace to Top Vent Do not Over Tighten ScrewsClearances Fireplace Placement RequirementsRaised Fireplaces Minimum Framing Dimensions Rear Vent Configuration Minimum 49 Fireplace Enclosure HeightMinimum Framing Dimensions Top Vent Configuration TOP View Nailing BracketsCorner Installations Rear Vent Configuration Corner Installations Top Vent Configuration Gas Line Requirements FuelGas Line Connection Gas Inlet PressureGas Line Location Left Side Gas Inlet preferredElectrical Connection required Wiring Diagram Millivolt System Wall Switch or Thermostat InstallationWall Switch Installation Vent Clearances Vent RequirementsAltitude Considerations Vent Installation Approved VentExhaust Restrictor Adjustment Approved Vent ConfigurationsRestrictor Position Intake Restrictor Adjustment Diffuser Plate Adjustment Diffuser Side ViewExhaust Restrictor Removal 0feet 5feet 22 max Feet 10feet 15feet Rear Vent Configuration with Vertical Termination Top Vent Configuration with Horizontal Termination Feet 21 max 5feet 10feet 15feetTop Vent Configuration with Vertical Termination Termination Requirements Hearth Requirements Floor Mounted FireplacesDrywall Installation Facing RequirementsOptional Faceplates Sizing Chart Facing OverviewFront View Raised Fireplace with no Hearth Front View Thick Facing with Fireplace Xtrordinair FPX Arched Faces Thick Facing Installation Side Floor-Mounted Fireplace with HearthMantel Requirements Side View Installation Example Build-In with Horizontal Termination Starting the Pilot Flame Steps for Finalizing the InstallationPilot Flame Inspection Finalizing the Installation for qualified installers only Air Shutter AdjustmentGlass Frame Removal and Installation Re-Attaching the Glass FrameFinalizing the Installation for qualified installers only Fireback and Grate Installation Rear Log Installation Log Set InstallationRight Log Installation Left Log Installation Right Twig Installation Verify Rear LOG PositionFront Twigs Installation Center Twig InstallationEmber Installation LP Conversion Instructions Follow the directions below to replace the orifices Slotted Screwdriver Or T-20 Torx Grill Installation Upper Grill InstallationOption # 1 Remote Thermostat Remote Control Receiver Installation 2 OptionsOption # 2 Remote Thermostat New Wire Hook-Up Extra Room Power Heat Duct skuSpecial Instructions for 864 HH Maximum Duct Installation OverviewLength = Duct Installation Instructions LengthFloor Mounting Attach the grill and wall adapter, if necessary Wiring Diagram -864TRV Follow the directions below to wire the blower boxOperating Instructions OFFAccent Light Installation sku Optional Equipment for qualified installers only Optional Wall-Mounted Rheostat Accent Light OperationOptional Equipment for qualified installers only 68Index Index