Vertical installations up to 40’ (12 m) in height. Up to a 20’ (6 m) horizontal vent run can be installed within the vent system using a maximum of three (3) 90° elbows. (Fig. 33)

A 2’ (610 mm) vertical section must be installed before any offset. A maximum of 20’ (6.1 m) horizon- tal and three (3) 90° elbows may be installed with a minimum of 12’ (3.66 m) vertical section above the flue collar of the unit. (Fig. 33)

Max. 8' (2.4m)

4

1 + 2 + 3 + 4 = 270°

3

12

Max. Height

40' (12m)

Min. Height

12' (3.7m)

Max. 20' (6m)

Minimum 2’ (610mm) Before Any Elbow

FP1245a

FP1464

Pipe Straps Every 3’ (914mm)

FP1463

Fig. 34 Typical offset application.

Vertical Through-the-Roof Installation

1.

Locate your fireplace.

2.

Plumb to center of the (8”) flue collar from ceiling

 

above and mark position.

3.

Cut opening equal to 14¹⁄” x 14¹⁄” (368 x 368 mm).

Fig. 33 Support straps for horizontal runs.

Up to two (2) 30° or 45° elbows may be used within the horizontal run. For each 30° or 45° elbow used on the horizontal level the maximum horizontal length must be reduced by 18” (457 mm).

Example: Maximum horizontal length

0 x 30° or 45° elbows = 10’ (3 m)

1x 30° or 45° elbows = 8’6” (2.6 m)

2 x 30° or 45° elbows = 7’ (2.1 m)

A minimum of a 12’ (3.7 m) vertical rise.

Two sets of 30° or 45° elbows offsets within these vertical installations. From 0 to a maximum of 8’ (2.4 m) of vent pipe can be used between elbows. (Fig. 34)

SKCS8 must be used to support offsets. (Fig. 37) This application will require that you first determine the roof pitch and use the appropriate starter kit. (Refer to Venting Components List)

The minimum height of the vent above the highest point of penetration through the roof is 2’ (610 mm). (Fig. 38)

4.

Proceed to plumb for additional openings through

 

the roof. In all cases, the opening must provide a

 

minimum of 1¹⁄” (38 mm) clearance to the vent pipe,

 

i.e., the hole must be at least 14¹⁄” x 14¹⁄” (368 x

 

368 mm).

5.

Place fireplace into position.

6.

Place firestop(s) SKFS2A or Attic Insulation Shield

 

AIS-SK into position and secure. (Figs. 35, 36)

7.

Install roof support (Fig. 35) and roof flashing making

 

sure upper flange of flashing is below the shingles.

8.

Install appropriate pipe sections until the venting is

 

above the flashing.

NOTE: Tape the inner and outer flue collars of the fireplace using UL approved metal adhesive tape to ensure the joints are sealed.

9.Seal around the pipe.

10.Add additional vent lengths for proper height. (Fig. 38)

24

20011957

Image 24
Contents INSTALLER/CONSUMER Safety Information What to do if YOU Smell GASTable of Contents Installation & Operating Instructions Certified ToAnsi Z21.50b-2005 / CSA 2.22b-2005 Vented Gas Fireplace Please Review the Following CarefullyLocating Your Fireplace Standard FramingClearance to Combustibles MantelsHearth Framing and FinishingFinal Finishing Gas SpecificationsGas Line Installation Gas Inlet and Manifold PressuresHigh Elevations Electrical Junction BoxControl System Installation Control SystemSpecial Feature for Cold Climates Chateau Direct Vent Gas FireplaceRemote Control Transmitter Operating Instructions Key SettingsIntroduction LCD Liquid Crystal DisplayManual Function Thermostat FunctionContinuous Pilot Feature CP Childproof FeatureSetting LOCK-OUT CP Thermostatic Updating Feature Operational NotesGeneral Venting Location of Vent TerminationCanadian Installations1 US Installations2 General Venting Information Termination LocationCanadian Installations USA InstallationsGeneral Information Assembling Vent Pipes SK8 Venting Pipes Horizontal Termination Vertical TerminationSidewall Applications Sidewall Installation StepAlways install horizontal venting on a level plane Zero clearance sleeve is only required for combustible wallsSidewall Installation with Stationary Glass Facing Outside Horizontal length requirementInstallation Procedure Installing the 38S2VDK DoorFlue Restrictor Plate Installation Restrictor Plate InstallationFlue Restrictor Plate Guide Typical ApplicationsFlue restrictor plate use in straight up installation Vertical Through-the-Roof Installation + 2 + 3 + 4 =Min Chimney Components Component Description Model NumberGlass Frame Assembly Removal Glass CleaningCeramic Refractory Installation Clean the glass after the first two weeks of operationLog, Lava Rock and Ember Placement DVT38Sw log identificationLog Pilot Plumbing F50 Overlay is very fragile Log Right Flame Characteristics Trim Installation Lighting & Operating Instructions Lighting InstructionsTurning Off the Gas to the Appliance Troubleshooting American Flame Gas Control SystemOperation Troubleshooting American Flame Gas Control System American Flame Gas Control System Error Codes What to CheckConversion Precautions Conversion ProcedureFuel Conversion Instructions Remove pilot orifice Pilot Flame Adjustment DVT38S2 Injector Orifice Size MatrixValve Minimum Rate Screw Conversion to LPMaintenance Cleaning the Control SystemBurner and Burner Compartment DVT38S2 Units GFYW5Q0 DVT38S2 DVT38S2Fuel Conversion Kits Accessories Back-up Battery KitChateau Direct Vent Gas Fireplace Limited Lifetime Warranty Product Covered by this WarrantyEfficiency Ratings Model EnerGuide Ratings Fireplace Efficiency %