Reference
Start-Up Checklist
Unit Model Number________________________________
(e.g.
Unit Serial Number________________________________
(e.g. 10111000)
Phone Number____________________________________
Pre
oCheck tightness of all factory wiring connections
oVerify control wiring wire gauge
o
oVerify supply voltage to the main disconnect
oVerify the supply gas pressure
oVerify remote controls wiring
o Check line voltage | ___________ | |
| ___________ | |
| ___________ |
o Check blower rotation |
|
|
o Check for vibration |
|
|
o Supply fan RPM | __________ | RPM |
o Motor nameplate amps | __________ | Amps |
o Actual motor amps | __________ | Amps |
o Actual CFM delivered | __________ | CFM |
Optional Accessories – refer to Blower
oBuilding Freeze Protection
_______ Actual Setting
Typical setting 5 minutes; 45ºF
oDirty Filter Gauge
_______ Actual Setting
Typical setting varies
oCheck supply gas pressure
_________ Maximum
_________ Minimum
_________ Actual
oSet optional High Gas Pressure Switch
_________ Actual Setting Typical 8.0 in. wg
oSet optional Low Gas Pressure Switch
_________ Actual Setting Typical 3.0 in. wg
oSet Burner Pressure Differential
_________ Actual Setting Typical 0.65 in. wg
oSet the maximum firing rate
_________ temp rise
oSet the minimum firing rate
_________ check
oSet the unit’s operating temperature
_________ ºF
®
DGX Industrial Space Heating 29