Grizzly G0648 owner manual Ducting Arm Installation, Test Run, To install the ducting arm

Page 17

Ducting Arm

Installation

To install the ducting arm:

1.Remove the six button head cap screws and flat washers that surround the 6" intake port on top of the machine.

2.On the intake port where the button head screws were, position and install the down- draft table adapter box with the six hex bolts and washers.

Note: Position the port so it points in the direction where you will connect ducting to reduce the need for elbows and tees. Having a duct that is longer than 15 feet, using alternating sizes of connections, or using too many elbows or tees will dramatically reduce the available CFM at your downdraft table. When connecting duct to this fume extractor, make sure that you use only fireproof duct and fittings. Refer to the Accessories sec- tion on Page 23 for fireproof duct options.

3.With the help of an assistant or hoist, install the base of the ducting arm on the top of the adapter box, and secure it in place with the six previously removed button head cap screws and washers (Figure 6).

Adapter Box

Ducting Arm

Figure 6. Ducting installation.

G0648 Welding Fume Extractor

Test Run

Once the ducting has been attached, test run your machine to make sure it runs properly.

If, during the test run, if you cannot easily locate the source of an unusual noise or vibration, stop using the machine immediately, then review the Troubleshooting on Page 34.

If you still cannot remedy a problem, contact our Tech Support at (570) 546-9663 for assistance.

To test run the machine:

1.Refer to the Maintenance section on Page 25, and make sure that all filters are properly positioned.

2.Connect the machine to the power source. The EXHAUSTING TIME and FILTER ROLLING TIME digital displays (Figure 7) will now be lit. The values shown on the displays are the initial factory settings.

Emergency

Stop Button

Figure 7. Control panel.

3.Push in the emergency stop button shown in Figure 7, then rotate it so it pops out.

-15-

Image 17
Contents Model G0648 Welding Fume Extractor Ss ,EAD from Leadbased PAINTS Table of Contents Contact Info IntroductionForeword Functional Overview Identification Vibrating Filter & Hepa Filter HousingMachine Data Sheet Other Specifications  !,7!93 53%3 %!2.2 02/4%#4/ %. /0%2!4.! -!#.%29  !,7!93 53% !.3 !002/6%$$ 3!&%49 ,!33%33 7%. /0%2!4 53%3 2%#/--%.$%$- !##%33/2%3  53%3!!2/5.$%$ %84%.3/..#/2$ 2!4%$4&/2/4%-!#.%!-0%2!%2 -!.9 -!#.%3 #!. %*%#4 7/2+0%#%3 4/7!2$ /0%2!4/2  !,7!93 ,/#+ -/,% !3%3 & 53%$ % %&/2% /0%2!4. -!#.%29#Additional Safety Instructions for Welding Fume Extractors Meeting Welding Fume Extraction Codes Standards Circuit Requirements 220V 3-Phase OperationSetup Safety SetupItems Needed for Setup UnpackingBox 2 Figure Qty InventoryCrate 1 Figure Qty Hardware Recognition Chart Floor Load Site ConsiderationsTo install the ducting arm Ducting Arm InstallationTest Run To test run the machineCompletely open both blast gates on the ducting arm Figure To use the machine Operation Safety General OperationOperations Page Control Panel Operation Setting Time Left Button ControlsSetting Time Right Button Controls To change the rolling-filter timing Changing Rolling Filter TimingModel G0648 Rolling Filter Consumption Chart T20474-First Layer Stainless Screen AccessoriesT20475-Second Layer Paper Filter Roll T20529-Third Layer FilterH7217-Rigid Flex Hose H5297 6 Welding Fume Collection KitSteel 6 Elbows G7366 6 G7368 6 G7367 6 G7369 6 90G7370 6H3157-Deluxe Welding Gloves Model T20505 welding respiratorCleaning MaintenanceSchedule LubricationTo perform this procedure Slag-Screen CleaningLong-Term Storage Tools Needed QtyRemoving recovery axle Rolling-Filter ReplacementPage Vibrating Filter Manual Cleaning Page Page To clean the Hepa filter Hepa Filter Manual CleaningPage Symptom Possible Cause Possible Solution ServiceTroubleshooting Operation Electrical Safety Instructions Wiring220 VAC Wiring OverviewMain ELE BOX Main Electrical Box WiringMain Electrical Box Components Input relay, fuse bus, phase Controller Transformer PigtailControl Panel WiringMAIN ELE Cntrl Digital Control Panel Electrical ComponentsMOT Cabinet WiringVibrating Cabinet Electrical ComponentsMain Parts Breakdown PartsDescription Parts ListMotor 2HP 220V 3PH Blast Gates and Ducting Arm Breakdown Parts List Main Electrical Box Label Placement G0648 Welding Fume Extractor 22!.49 #!2$ 99.$5342!, .# 0//88 %,,.!- 7!  Warranty and Returns #ALL 4ODAYD&ORO! &2%%