Hobart Welding Products OM-945 Grounding When Supplying Building Systems, Amperes x Volts = Watts

Page 44

12-3. Grounding When Supplying Building Systems

 

 

 

1

Equipment Grounding

 

1

2

 

Terminal

 

2

Grounding Cable

 

GND/PE

 

 

 

Use #10 AWG or larger insulated

 

 

 

 

 

 

copper wire.

 

 

 

3

Ground Device

 

 

 

Y Ground generator to system

 

 

 

 

earth ground if supplying

 

 

 

 

power to a premises (home,

 

 

 

 

shop, farm) wiring system.

 

 

 

Use ground device as stated

 

2

3

 

in electrical codes.

 

 

 

 

ST-800 576-B

12-4. How Much Power Does Equipment Require?

1 Resistive Load

3

2

1

3

VOLTS 115 AMPS 4.5

Hz 60

A light bulb is a resistive load and requires a constant amount of power.

2 Non-Resistive Load

Equipment with a motor is a non-re- sistive load and requires approxi- mately six times more power while starting the motor than when running (see Section 12-8).

3 Rating Data

Rating shows volts and amperes, or watts required to run equipment.

AMPERES x VOLTS = WATTS

EXAMPLE 1: If a drill uses 4.5 amperes at 115 volts, calculate its running power requirement in watts.

4.5 A x 115 V = 520 W

The load applied by the drill is 520 watts.

EXAMPLE 2: If three 200 watt flood lamps are used with the drill from Example 1, add the individual loads to calculate total load.

(200 W + 200 W + 200 W) + 520 W = 1120 W

The total load applied by the three flood lamps and drill is 1120 watts.

S-0623

OM-945 Page 40

Image 44
Contents Processes DescriptionFrom Hobart to You Table of Contents Options and Accessories Warranty Symbol Usage Arc Welding HazardsEngine Hazards Compressed Air Hazards Principal Safety Standards California Proposition 65 WarningsEMF Information Radiation can cause interferenceSignification des symboles − Consignes DE Sécurité − Lire Avant UtilisationUN Choc Électrique peut tuer LES Fumées ET LES GAZ peuvent être dangereuxLE Soudage peut provoquer un in- cendie ou une explosion DES Particules Volantes peuvent blesser les yeuxDES Pièces Chaudes peuvent provoquer des brûlures graves LE Bruit peut affecter l’ouïe’AIR Comprimé peut provoquer des blessures ’EMPLOI Excessif peutLE Surchauffement peut endom- mager le moteur électrique LES Étincelles Volantes risquent de provoquer des blessuresLE Soudage À L’ARC risque de provoquer des interférences Pour les moteurs à essencePour les moteurs diesel En ce qui concerne les stimulateurs cardiaques− Specifications Symbol DefinitionsWeld, Power, and Engine Specifications − DefinitionsDimensions, Weights, and Operating Angles Generator Power CurveFuel Consumption All Models Duty CycleMaterial Thickness Reference Chart Volt-Ampere Curves− Installation Installing Welding GeneratorVehicle frame. Always connect a ground wire MountingEngine Prestart Checks Robin-Powered Units Engine Prestart Checks Kohler-Powered UnitsFuel OilActivating The Dry Charge Battery If Applicable Connecting the BatteryDo not overfill battery cells Connect negative −Installing Exhaust Pipe Weld Output TerminalsConnecting To Weld Output Terminals Selecting Weld Cable Sizes− Operating the Welding Generator Front Panel ControlsCold Weather Engine Operation Amperage Selection Table For Stick Smaw ElectrodesInfrequently Loaded− Operating Auxiliary Equipment Standard ReceptaclesOptional Generator Power Receptacles Gfci Receptacle OptionCurrent Available in Amperes 240 Receptacle− Maintenance ROBIN-POWERED Units Routine Maintenance Robin-Powered UnitsMaintenance Label Robin-Powered Units Servicing Air Cleaner Robin−Powered Units Overload Protection Robin-Powered Units Servicing Optional Spark Arrestor Robin-Powered UnitsStop engine. Disconnect nega- tive − battery cable Stop engine and let coolFull Tools Needed Weld/Power Speed Adjustment Adjusting Engine Speed Robin-Powered UnitsIdle Speed Adjustment − Maintenance − KOHLER-POWERED Units Routine Maintenance Kohler-Powered UnitsMaintenance Label Kohler-Powered Units Servicing Air Cleaner Kohler−Powered Units Overload Protection Kohler-Powered Units Servicing Optional Spark Arrestor Kohler-Powered Units802 339-G / S-0842 Adjusting Engine Speed Kohler-Powered Units Stop engine. Reinstall wrapper− Troubleshooting TroubleshootingGenerator Power WeldingEngine Work like a Pro − Electrical Diagram Grounding Generator To Truck Or Trailer Frame − Generator Power GuidelinesSelecting Equipment Grounding When Supplying Building Systems How Much Power Does Equipment Require?Earth ground if supplying Amperes x Volts = WattsApproximate Power Requirements For Industrial Motors Approximate Power Requirements For Farm/Home EquipmentIndustrial Motors Rating Starting Watts Running Watts Farm/Home Equipment Rating Starting Watts Running WattsApproximate Power Requirements For Contractor Equipment Contractor Rating Starting Watts Running WattsPower Required To Start Motor How Much Power Can Generator Supply?Single-Phase Induction Motor Starting Requirements KVA/HP x HP x 1000 = Starting AmperageTypical Connections To Supply Standby Power Selecting Extension Cord Use Shortest Cord Possible Current Load Watts Amperes− Stick Welding Smaw Guidelines Stick Welding ProcedureWeld current starts when electrode touches work- piece Striking an Arc − Tapping Technique Electrode and Amperage Selection ChartStriking an Arc − Scratch Start Technique Positioning Electrode Holder Poor Weld Bead CharacteristicsGood Weld Bead Characteristics Conditions That Affect Weld Bead Shape Electrode Movement During WeldingTee Joint Butt JointsLap Joint Troubleshooting − Porosity Troubleshooting − Excessive SpatterWeld Test Possible Causes Corrective ActionsTroubleshooting − Excessive Penetration Troubleshooting − Incomplete FusionTroubleshooting − Lack Of Penetration Troubleshooting − Distortion Troubleshooting − Burn-ThroughTroubleshooting − Waviness Of Bead − Parts List Main Assembly Robin Engine ShownMain Assembly Panel, Front w/Components Panel, Front w/Components -1Item Generator -1Item Assistance ServiceSupport Contact your Distributor for Hobart Welding Products