GE GE752 manual Commutator, Armature Shaft Inspection, Motor Frame

Page 32

GEK±91584D, Vertical Drilling Motor, Type GE752

tion. A reading of one megohm or higher should be obtained. If necessary, perform additional cleaning and baking operations to obtain this val- ue before proceeding.

NOTE: If additional cleaning and baking opera- tions do not increase the resistance value of the insulation, it may be necessary to replace the creepage band and rewind the armature.

2.Measure and record armature resistance. See the DATA section for values.

3.If there are no armature coils grounded, perform

abar±to±bar comparison test to check for open or short±circuited armature coils.

a.Pass a regulated d±c current through the ar- mature coils.

b.Read the voltage drop between the commu- tator segments with a millivoltmeter. If the reading varies more than plus or minus 5%, a defective or short±circuited coil is indicated. If the armature fails the bar±to±bar test, the ar- mature must be rewound.

If the armature will not be rewound, proceed to inspect the following items.

Insulation

Inspect the insulation of armature coils for cracks, physical damage, burns and deterioration. If minor re- pairs are required, refer to Fig. 19 for insulation details.

Glass Band, Commutator End

Inspect the glass bands for split, frayed or loose con- dition.

Wire Band, Drive End

check for movement of the band to determine if loose. If the band is loose or has deep burns, replace it. See RE- PAIR section for instructions.

COMMUTATOR

Check the commutator for threading, pitting, groov- ing, burns, flat spots, high bars and copper drag.

Check the commutator to make sure that it is not out±of±round. See the DATA section for concentricity limits.

Resurfacing

For the resurfacing procedure for a commutator, see REPAIR, Armature section.

Refer to the DATA section for the minimum permissi- ble commutator diameter dimension and check the di- ameter of the commutator.

NOTE: If the brush surface diameter will be less than the minimum permissible diameter after resurfacing operations are performed, the com- mutator must be replaced.

Tightening

If the commutator is loose (has high bars), see the ªREPAIR, Commutator Tighteningº section for instruc- tions to tighten the commutator.

ARMATURE SHAFT INSPECTION

Armature shaft bearing fit dimensions can be checked and compared to armature shaft drawings pro- vided in Fig. 20. If the bearing fit dimensions are not within stated tolerances the shaft must be replaced or repaired. Refer to Table 2 to determine the correct shaft drawing for the machine being repaired.

MOTOR FRAME

Inspect the wire band for physical damage, loose tie clips or broken wire.

Creepage Band

Inspect the surface of the Teflon creepage band for possible flashover damage. Tap the band lightly and

1.Check the connection strap insulation for dam- age, signs or burning, cracks or discoloration.

2.Check the insulation on the coils for damage, signs of burning, cracks or discoloration.

3.Check the lead cables for damage, overheating and signs of deterioration.

32

Image 32
Contents Contents Vertical Drilling Motor Type GE752GEK±91584D, Vertical Drilling Motor, Type GE752 General DescriptionIntroduction Vertical Drilling Motor, Type GE752, GEK±91584D Model DifferencesContd Model Differences DataData Contd Carbon BrushesPole Bore Diameter measured at center of pole Motors Min Max Motor Ratings Continuous Max. HP Shunt UP Special Tools Equipment Grounding InstructionsGrounding Procedures Fig OverhaulLubrication Grease Tubes and Pipe PlugsBrushholders Fig Inspection MonthlyCovers, Seals, Latches Brushholder Sleeves Brush Spring PressureBrushes CommutatorCreepage Band Flash RingSEMI±ANNUALLY Basic Repairs Brush ReplacementBrushholder Replacement Commutator Resurfacing InstallationBrushholder Clearance Adjustment Sanding Procedure Hand Stoning ProcedureGrinder Installation Fixture GrindingCommutator GRINDER. E±18249 Grinding ±19771ABasic Overhaul Testing Before DisassemblyAir Curing Commutator Disassembly Megohmmeter TestBar±To±Bar Resistance Test Armature Removal From FrameCOMMUTATOR±END Bearing Pilot Longitudinal D732922 CHG. N. E±28621D Models See , Description Puller Tools 41D731569 CHG . E±14383C Puller TOOLS. E±18155A Models US1, AUT Longitudinal D735357, CHG. A. E±37949B Models See Table Cleaning Steam CleaningVapor Degreasing Anti±Friction Bearings/Shaft Tapers/Bearing FitsBearing Inspection ArmatureMotor Frame CommutatorArmature Shaft Inspection Armature Insulation 41D731545 CHG. F. E±18156A See Note Brushholders Lubrication of BoltsConnection Diagram 493A210 CHG . E±39092B Creepage Band Replacement Rewinding ArmatureRiser Width DiameterProcedure Commutator TighteningHydraulic Press Preferred Method Torque Wrench Acceptable MethodSpin Seasoning Commutator Assembled On Armature Commutator ResurfacingTurning To Change Motor DirectionConnection Diagram 41A330278, CHG . E±38055B Connection Diagram 41A330179, CHG. A. E±37950A Raking ±4270BResistance Measurement Test After Repair Armature High Potential TestUsed Armature Rewound ArmatureReplacement Coil InstallationProcedure for New Coil±Pole Assembly Motor Frame Field CoilCoiled Frame Assembly 41D732353 CHG. N. E±39094A Models See , Coiled Frame Assembly 41D732345 CHG. V. E±39095A BOX Ground A1 and A2 View AT E Cables with P65 Coiled Frame Assembly 41D735440, CHG. A. E±38056B Description Magnet Frame Coiled Frame Assembly 41D735343, CHG. C. E±37951C Hardened Washer 1 1/4 Brazing Coil Terminals Gas Torch BrazingCoiled Frame Without Armature Flood Dipping Coiled FrameTest After Repair Varnish Treatment Armature ReassemblyBalancing Armature Armature Bearings Drive±End Bearing Figs , 35, 36Commutator±End Bearing All Models Except US2, UP6, AUT2 and AUP5DRIVE±END Bearing ASSEMBLY. E±18166E DRIVE±END Bearing ASSEMBLY. E±39301 Models US2, UP6, AUT2 and AUP5DRIVE±END Bearing Assembly 41B537821, CHG. B. E±37952B Armature Assembly Into Frame Models UP and AUPCOMMUTATOR±END Bearing Assembly 41B532745 CHG. F. E±39090A COMMUTATOR-END Bearing Assembly 41B538068 CHG . E-39300 Checking Internal Clearance Brush Installation Hub Mounting HUB MountingHub Fitting Models 5GE752AUP, AUT Testing After OverhaulTesting Series Machines Testing Shunt Machines Models 5GE752UP and US Motor OperationVentilated 2300 cfm at 7.6 in. H2O at Commutator Chamber UnventilatedCleaning and Slushing Removing Armature Locking ArrangementLocking the Armature For Shipment ShippingSkidding ProtectionArmatures Preparation of BOXBoxing the Armature Storage Placing Into StorageRemoving from Storage Shipping BOX with Armature Less COVER. E±3784Vertical Drilling Motor, Type GE752, GEK±91584D OUTLINE, UP and AUP 41E903631 CHG. H. E±28755B Hole Grease Vent Tube Grease Tube Holes REF OUTLINE, US1, AUT 41E903745, CHG. A. E±37954B ºDº ºBº Vertical Drilling Motor, Type GE752, GEK±91584D GE Transportation Systems