GE GE752 manual Checking Internal Clearance

Page 64

GEK±91584D, Vertical Drilling Motor, Type GE752

OUTER BEARING

RACE WITH

ROLLERS

BEARING

CAGE

FEELERS

SHAFT

INNER BEARING

RACE

FRAMEHEAD

FIG. 40. CHECKING INTERNAL CLEARANCE OF

BEARING. A-120403.

17.At the commutator end, smear the seals on bear- ing cap (4) and sleeve (42) with grease.

NOTE: Prior to heating sleeve (42), apply NAL- CO RC* ªRail Conditionerº to the inside diame- ter of the sleeve and to the mating surface on the shaft. Apply the NALCO with a Scott±150 white paper towel only and allow it to dry to a thin white film on both surfaces before pro- ceeding with Step 18.

18.Heat sleeve (42) to 180￿ C (356￿ F) rise and shrink it onto the shaft tight against the spacer

19.Assemble the grease tubes to the bearing cap

(4)(UP1 and AUP1 models only). Install pipe plugs in tubes and tube fittings as indicated in Fig. 15.

NOTE: Insure that grease tubes are packed full of grease.

Armature Assembly Into Frame

Models US1, AUT

Refer to Fig. 18.

11.The clearance between the rollers and the inner race should measure between 0.0012 and 0.004 in. Try various gauge thicknesses until clearance can be determined by the feel of the gauge as the gauge is slowly pulled from between the roller and the inner race.

12.Pack 4.8 oz. of grease in the outer circumference of outer bearing cap (5).

13.Install a new gasket (54) and bearing cap (5) with bolts and lockwashers (53).

14.Smear seals on bearing cap (5) and sleeve (47) with grease.

15.Heat sleeve (47) to 110￿ C (230￿ F) rise and shrink it onto the shaft tight against the roller bearing inner race (48).

16.Seal the grease tubes which protrude through the hole in the frame with RTV±108.

1.Assemble the brushholders into the frame. Move them well back from the commutator to avoid in- terference when installing the armature. Fasten and insulate the connections and install outgoing cables.

2.Block and level the frame in a vertical position, commutator±end down, on a heavy duty stand. Be sure there is clearance for the commutator± end shaft extension when the armature is low- ered into the frame.

3.Install three guide studs in the commutator±end bearing housing bolt circle to guide the housing into the framehead fit.

4.Pack 5.25 oz. of grease in the outer circumfer- ence of bearing cap (8).

5.Lift the armature with the hoist and lifting bail at the drive end. Line up the hoist directly over the center of the cavity in the frame.

*Product of NALCO Chemical Co.

64

Image 64
Contents Contents Vertical Drilling Motor Type GE752Introduction General DescriptionGEK±91584D, Vertical Drilling Motor, Type GE752 Vertical Drilling Motor, Type GE752, GEK±91584D Model DifferencesContd Model Differences DataData Contd Carbon BrushesPole Bore Diameter measured at center of pole Motors Min Max Motor Ratings Continuous Max. HP Shunt UP Special Tools Equipment Grounding InstructionsGrounding Procedures Fig OverhaulLubrication Grease Tubes and Pipe PlugsCovers, Seals, Latches Inspection MonthlyBrushholders Fig Brushholder Sleeves Brush Spring PressureBrushes CommutatorCreepage Band Flash RingBrushholder Replacement Basic Repairs Brush ReplacementSEMI±ANNUALLY Brushholder Clearance Adjustment InstallationCommutator Resurfacing Sanding Procedure Hand Stoning ProcedureGrinder Installation Fixture GrindingCommutator GRINDER. E±18249 Grinding ±19771AAir Curing Commutator Testing Before DisassemblyBasic Overhaul Disassembly Megohmmeter TestBar±To±Bar Resistance Test Armature Removal From FrameCOMMUTATOR±END Bearing Pilot Longitudinal D732922 CHG. N. E±28621D Models See , Description Puller Tools 41D731569 CHG . E±14383C Puller TOOLS. E±18155A Models US1, AUT Longitudinal D735357, CHG. A. E±37949B Models See Table Cleaning Steam CleaningVapor Degreasing Anti±Friction Bearings/Shaft Tapers/Bearing FitsBearing Inspection ArmatureArmature Shaft Inspection CommutatorMotor Frame Armature Insulation 41D731545 CHG. F. E±18156A See Note Brushholders Lubrication of BoltsConnection Diagram 493A210 CHG . E±39092B Creepage Band Replacement Rewinding ArmatureRiser Width DiameterProcedure Commutator TighteningHydraulic Press Preferred Method Torque Wrench Acceptable MethodSpin Seasoning Commutator Assembled On Armature Commutator ResurfacingTurning To Change Motor DirectionConnection Diagram 41A330278, CHG . E±38055B Connection Diagram 41A330179, CHG. A. E±37950A Raking ±4270BResistance Measurement Test After Repair Armature High Potential TestUsed Armature Rewound ArmatureReplacement Coil InstallationProcedure for New Coil±Pole Assembly Motor Frame Field CoilCoiled Frame Assembly 41D732353 CHG. N. E±39094A Models See , Coiled Frame Assembly 41D732345 CHG. V. E±39095A BOX Ground A1 and A2 View AT E Cables with P65 Coiled Frame Assembly 41D735440, CHG. A. E±38056B Description Magnet Frame Coiled Frame Assembly 41D735343, CHG. C. E±37951C Hardened Washer 1 1/4 Brazing Coil Terminals Gas Torch BrazingTest After Repair Flood Dipping Coiled FrameCoiled Frame Without Armature Balancing Armature ReassemblyVarnish Treatment Armature Armature Bearings Drive±End Bearing Figs , 35, 36Commutator±End Bearing All Models Except US2, UP6, AUT2 and AUP5DRIVE±END Bearing ASSEMBLY. E±18166E DRIVE±END Bearing ASSEMBLY. E±39301 Models US2, UP6, AUT2 and AUP5DRIVE±END Bearing Assembly 41B537821, CHG. B. E±37952B Armature Assembly Into Frame Models UP and AUPCOMMUTATOR±END Bearing Assembly 41B532745 CHG. F. E±39090A COMMUTATOR-END Bearing Assembly 41B538068 CHG . E-39300 Checking Internal Clearance Brush Installation Hub Fitting HUB MountingHub Mounting Testing Series Machines Testing After OverhaulModels 5GE752AUP, AUT Testing Shunt Machines Models 5GE752UP and US Motor OperationVentilated 2300 cfm at 7.6 in. H2O at Commutator Chamber UnventilatedCleaning and Slushing Removing Armature Locking ArrangementLocking the Armature For Shipment ShippingSkidding ProtectionArmatures Preparation of BOXBoxing the Armature Storage Placing Into StorageRemoving from Storage Shipping BOX with Armature Less COVER. E±3784Vertical Drilling Motor, Type GE752, GEK±91584D OUTLINE, UP and AUP 41E903631 CHG. H. E±28755B Hole Grease Vent Tube Grease Tube Holes REF OUTLINE, US1, AUT 41E903745, CHG. A. E±37954B ºDº ºBº Vertical Drilling Motor, Type GE752, GEK±91584D GE Transportation Systems