GE EPM 6000 instruction manual Configuring the Communication Port Setting

Page 66

CHAPTER 4: USING THE METER

ZPush the DOWN Button to scroll through the configuration mode parameters.

ZPress ENTER when Cnct is the active parameter (i.e. it is in the “A” screen and flashing).

This will display the Cnct (connection) screen. The possible connection configurations are 3-element Wye (3 EL WYE), 2.5-element Wye (2.5EL WYE), and 2 CT Delta (2 Ct deL), as shown below.

3-Element Wye

2.5-Element Wye

2 CT Delta

ZPress ENTER to scroll through the other CFG parameters.

ZPress DOWN or RIGHT to display the password screen (see Reset Mode and Password Entry on page 4–6 for details).

ZPress MENU to return to the main configuration menu.

4.3.7Configuring the Communication Port Setting

Use the following procedure to program the communication port (POrt) settings.

ZPush the DOWN Button to scroll through the configuration mode parameters.

ZPress ENTER when POrt is the active parameter (i.e. it is in the “A” screen and flashing).

The following parameters can be configured through the POrt menu

The meter address (Adr, a 3-digit number).

The baud rate (bAUd). Select from “9600”, “19.2”, “38.4”, and “57.6” for 9600, 19200, 38400, and 57600 kbps, respectively.

The communications protocol (Prot).

4–14

EPM 6000 MULTI-FUNCTION POWER METERING SYSTEM – USER GUIDE

Image 66
Contents Chapter Page Table of Contents Using the Meter Miscellaneous TOC-4 Introduction DescriptionHighlights EPM 6000 Highlights Current Inputs FeaturesUniversal Voltage Inputs Utility Peak DemandMeasured Values EPM 6000 Measured ValuesOrdering Order CodesEPM 6000 Order Codes Specifications Inputs/OutputsMetering Environmental CommunicationsMechanical Parameters Type Testing ApprovalsThree-Phase Power Measurement Three-Phase System Configurations Wye ConnectionCommon Phase Voltages on Wye Services VcnThree-Phase Delta Winding Relationship Delta ConnectionBlondells Theorem and Three-Phase Measurement Three-Phase, Four-Wire Delta PhasorsPhase B Phase C Node n Phase a Electrical Background Power, Energy, and Demand PowerEnergy Power Use Over Time Power and Energy Relationship Over Time DemandEnergy Use and Demand Intervals Reactive Energy and Power Factor Real, Reactive, and Apparent PowerPower Factor Apparent powerHarmonic Distortion Harmonics of a Non-Sinusoidal WaveformInductive and Capacitive Impedance Voltage and Current MonitoringWaveform Capture Power Quality Typical Power Quality ProblemsElectrical Background Mechanical Installation DimensionsAnsi Installation Steps Ansi and DIN Mounting Panel CutoutsDIN Installation Steps Ansi Mounting ProcedureDIN Mounting Procedure Electrical Installation Installation ConsiderationsCT Leads Terminated to Meter CT Leads Pass-Through No Meter TerminationVoltage and Power Supply Connections Quick Connect Crimp CT TerminationsGround Connections Voltage ConnectionWiring Diagrams 2 Wye, 4-Wire with no PTs and 3 CTs, 3 Element 4-Wire Wye with no PTs and 3 CTs, 3 Element3 Wye, 4-Wire with no PTs and 3 CTs, 2.5 Element 10 4-Wire Wye with no PTs and 3 CTs, 2.5 Element4 Wye, 4-Wire with 3 PTs and 3 CTs, 3 Element 11 4-Wire Wye with 3 PTs and 3 CTs, 3 Element5 Wye, 4-Wire with 2 PTs and 3 CTs, 2.5 Element 12 4-Wire Wye with 2 PTs and 3 CTs, 2.5 ElementDelta, 3-Wire with no PTs and 2 CTs 13 3-Wire Delta with no PTs and 2 CTsDelta, 3-Wire with 2 PTs and 2 CTs 14 3-Wire Delta with 2 PTs and 2 CTsCurrent-Only Measurement Three-Phase Current-Only Measurement Dual-Phase Current-Only Measurement Single-Phase Communications Setup IrDA COM1 Port3 RS485 COM2 Port 16 RS485 Communications Installation Front Panel Interface Faceplate ElementsUsing the Meter Faceplate ButtonsPercentage of Load Bar % of Load Bar SegmentsWatt-Hour Accuracy Testing Verification EPM 6000 Accuracy Test ConstantsConfiguring the Meter via the Front Panel OverviewStart Up Reset Mode and Password Entry Main MenuUsing the Meter Using the Meter Changing Settings in Configuration Mode Configuring the Scroll FeatureProgramming the Configuration Mode Screens Configuring the CT Setting Configuring the PT Setting Value for amps is a product of the Ct-nand the Ct-SvaluesConfiguring the Connection Setting Configuring the Communication Port Setting Address Using the Meter Operating Mode Operating Mode Parameter ReadingsUsing the Meter Modbus Communications Memory Map DescriptionMemory Map HEX Range Units or Comments THD Block7 Description 1 Format Range 7532 PT denominator Modbus Memory Map Notes Secondary Readings SectionCommunications Modbus Memory Map Data Formats DNP Point Mapping DNP Point MapsDNP Point Mapping Sheet 1 DNP Point Mapping Sheet 2 DNP Point Map Notes DNP Implementation Data Link LayerTransport Layer Application Layer Following function codes are implemented on the EPMDNP Objects and Variations Binary Output Status Object 10, VariationControl Relay Output Object 12, Variation 4 32-Bit Binary Counter Without Flag Object 20, Variation 5 16-Bit Analog Input Without Flag Object 30, VariationClass 0 Data Object 60, Variation Internal Indications Object 80, VariationCommunications Navigation Maps IntroductionMain Menu Screens Main Menu NavigationOperating Mode Screens Operating Mode NavigationReset Mode Screens Reset Mode NavigationConfiguration Mode Screens Revision History Release DatesChanges to the Manual Major Updates for 1601-0215-A2 Warranty GE Multilin WarrantyIndex Irda Power Supply Wiring