COMMISSIONING

INSTALLATION INSTRUCTIONS

COMMISSIONING

1.COMMISSIONING

1.1Close all windows and doors to the room, check all controls, and allow fire to burn on maximum for 5 minutes. Test for spillage of flue products using a smoke match. For standard VFC fires, pass the lighted smoke match along the top front edge just inside the opening or canopy. For the RD VFC only, hold the lighted smoke match centrally inside the flue opening. See Diagram 1 for Radiant fires and 2 for Convector fires.

1

AR0187

2

AR0179

1.2If the fire spills, run for a further 10 minutes and re-check. If there is still spillage, disconnect the fire and seek expert advice.

1.3If there are extractor fans in the room or adjacent rooms, the spillage test must be repeated with the extractors running on maximum.

1.4For RD VFC: If spillage is detected and no air vent is fitted in the room, re-check for spillage with a window slightly open. If this cures the spillage, it will be necessary to fit a vent.

IF SPILLAGE PERSISTS, DISCONNECT THE APPLIANCE AND SEEK EXPERT ADVICE.

For future reference record the installation details on the commissioning sheet on page 3 of these Instructions.

18

Image 18
Contents With upgradeable control valve For use in GB, IE Great Britain and EireInstructions for Use Installation and Servicing VFC Radiant & Convector Fire RangeCONTENTS user instructions instaLlation InstructionsServicing Instructions APPLIANCE COMMISSIONING CHECKLIST DEALER AND INSTALLER INFORMATIONIMPORTaNT NOTICE 2.LIGHTING THE FIRE USER INSTRUCTIONS1.general 3.TURNING THE FIRE OFF5.UPGRADING YOUR FIRE 6.CLEANING THE FIREUSER INSTRUCTIONS 7.ARRANGEMENT OF FUEL BED COMPONENTSUSER INSTRUCTIONS 16” AND REDUCED DRAUGHT COAL LAYOUT18” COAL LAYOUT AR1121 USER INSTRUCTIONS22” COAL LAYOUT AR11228. OXYGEN DEPLETION SENSOR 13. INSTALLATION DETAILSUSER INSTRUCTIONS 9. THE FLAME FAILURE DEVICEVFC RADIANT TECHNICAL SPECIFICATIONtHESE INSTRUCTIONS COVER THE FOLLOWING MODELS VFC CONVECTORINSTALLATION INSTRUCTIONS SITE REQUIREMENTSINSTALLATION INSTRUCTIONS SITE REQUIREMENTS1A VFC Radiant 1B VFC Convector 1.CONTROL UPGRADE INSTALLATIONINSTALLATION INSTRUCTIONS 2.SAFETY PRECAUTIONSINSTALLATION INSTRUCTIONS INSTALLATION5.INSTALLATION - CONVECTOR FIRES ADVICE ON HANDLING AND DISPOSAL OF FIRE CERAMICS INSTALLATION INSTRUCTIONSINSTALLATION 6.ARRANGEMENT OF FUELBED COMPONENTS16” AND REDUCED DRAUGHT COAL LAYOUT INSTALLATION INSTRUCTIONSINSTALLATION NOTE CERAMIC PARTS ARE FRAGILE6.9Curved fronts Holyrood- Place 6 large coals onto the front coal moulding ensuring that they rest against the front. Place 2 small coals onto the front coal, 1 at each end. See Diagram INSTALLATION INSTRUCTIONSINSTALLATION 18” COAL LAYOUTINSTALLATION INSTRUCTIONS INSTALLATION7.LIGHTING COMMISSIONING INSTALLATION INSTRUCTIONS1.COMMISSIONING SERVICING INSTRUCTIONS SERVICING REQUIREMENTSIGNITION FUNCTIONAL CHECK PILOT WILL NOT LIGHT FAULT FINDINGSee “NO SPARK” chart IGNITION FUNCTIONAL CHECK NO SPARK2.IGNITION LEAD REPLACING PARTSSERVICING INSTRUCTIONS 3.PIEZO5. ODS PILOT UNIT REPLACING PARTSSERVICING INSTRUCTIONS 6.GAS VALVE7.MAG UNIT INSTALLATION INSTRUCTIONSREPLACING PARTS 8.MAIN INJECTORSPARES PARTS LIST MANUAL FIRESNatural Gas Parts SERVICE RECORDS