B. Clearances

WARNING! Risk of Fire! You must comply with all minimum air space clearances to combustibles as specified in Fig- ure 6.2. DO NOT pack required air spaces with insulation or other materials.

Storm Collar

Roof Flashing

(attic)

(insulation)

2 in. (51 mm) min.

Shaded areas

represent

2 in. (51 mm) min. air space clearance required around pipe

Attic

Insulation

Shield

(ceiling)

Offset/Return (secured

with hanger straps)

(ceiling)

Ceiling Firestop

Must have 2 in. (51 mm)

minimum clearance

 

 

to header

 

Chimney air kit

 

attached here (not shown)

 

0 in. to level

 

of standoffs

 

1/2 in. (13 mm) to back &

 

side of appliance

0in.

to floor

Figure 6.2 Clearances to Combustible Materials

Note: Chimney air kit is not shown, but is required in Canada.

Heatilator • CL36D, CR36D • 12538 • Rev V • 05/09

19

Image 19
Contents Hot screen/mesh and glass doors will cause burns Wood Burning FireplaceFire Risk Grate Listing Label Information/LocationNumber Installer Guide Table of ContentsUser Guide Limited Warranty Heatilator CL36D, CR36D 12538 Rev V 05/09 Combustible Materials Listing and Code ApprovalsAppliance Certification Non-Combustible MaterialsYour Fireplace Operating InstructionsHot glass will cause burns Firescreen Seasoned WoodStarting a Fire GrateOptional Components Glass DoorsOutside Air optional Vented Gas Log Sets & Gas Log LightersHardwood vs Softwood Wood FuelChimney Inspection/Cleaning Maintenance and ServiceDisposal of Ashes Frequency As desired Glass CleaningCheck Firebox Refractory Inspect GrateStart Fire Problems Possible Cause Solution Troubleshooting GuideTypical Fireplace System Getting StartedDraft Design and Installation ConsiderationsNegative Pressure Frequently open doors Central heat outlets or returns Locating Fireplace & ChimneyFireplace System Requirements Tools and Supplies NeededInspect Fireplace and Components Select Fireplace Location Framing & ClearancesClearances to Combustible Materials ClearancesMantel Leg or Wall Projections Sidewalls/SurroundsRequired Frame the FireplacePlace Protective Metal Hearth Strips Installation of FireplaceThings to Consider Position the FireplaceYES Outside Air Installation Install Outside Air KitChimney Assembly Height of Chimney Components Chimney RequirementsExample Using Offsets/ReturnsInstall Ceiling Firestops Install Chimney Air KitAssemble Chimney Sections Mm overlap Install Attic Insulation ShieldInstall Flashing Complete InstallationCut out Hole in Roof Flat Roofs Chimney Termination RequirementsConstruct the Chase Chase InstallationsInstall Chase Top Install Fireplace & ChimneyInstall Termination Cap ST375 Square Termination Cap Radiation Shield ShroudsField Constructed Shrouds Mailbox Style Shroud radiation shield required Hearth Extension Finishing= 1/k x inches of thickness In. Micore or equivilent insulation Finishing MaterialMantel Combustible Mantel50 deg 16 3/4 in. Minimum 14-1/2 39 deg 18 in. Min Gas Code, Ansi Z223.1 AccessoriesGas Log/Lighter Provision Wood Burning InsertsReference Materials Fireplace DimensionsCatalog # Chimney Components14-1/2 10-7/8 276 mm CL36D Service PartsParts Contact Information