Step 3.

For installations using a round support box/wall thimble (check pipe manufacturer's instructions), mark the wall for a 10 in. x 10 in. (254mm x 254mm) square hole. The center of the square hole should line up with the center line of the horizontal pipe, as shown in Figure 5.5. Cut and frame the hole in the exterior wall where the vent will be terminated. If the wall being penetrated is constructed of noncombustible material, i.e. masonry block or concrete, a 7 in. (178mm) diameter hole is acceptable.

NOTE:

(1) Installation requires a minimum of 6 in. (152mm)

horizontal run of vent with a 1/4 in. (6mm) rise run towards

the termination. Each 1 ft. (305mm) of horizontal venting

must include a 1/4 in. (6mm) rise. Never allow the vent

to run downward. This could cause high temperatures

and may present the possibility of a house or structure

fire.

(2) The location of the horizontal vent termination on an

exterior wall must meet all local and national building

codes, and must not be easily blocked or obstructed,

see Figure 4.4 on page 9.

Rear Vent

CENTER

LINE

WALL

THIMBLE

Top Vent

CENTER

LINE

CENTER OF

HOLE

CENTER

LINE

CENTER OF

HOLE

CENTER

WALL LINE

THIMBLE

(3) For installations requiring a vertical rise on the exterior

of the building, the HHT RHVK snorkel kit (Part #844-

8921) is available with a 14 in. (356mm) and a 36 in.

(914mm) tall snorkel termination cap. Follow the

same installation procedures as used for standard

horizontal terminations. If the snorkel termination must

be installed below grade (i.e. basement application),

proper drainage must be provided to prevent water from

entering the snorkel termination. Do not backfill around

snorkel termination.

Step 4.

Position the horizontal termination cap in the center of the 10 in. x 10 in. (254mm x 254mm) square hole and run a bead of non-hardening mastic around its outside edges, so as to make a seal between it and the wall, attach termination cap to the exterior wall with the four wood screws provided. The arrow on the vent cap should be pointing up (Figure 5.6).

WOOD

SCREW

45° Elbow in Corner Installation

Wall Thimble

14 in. (356mm) Pipe Length

Max. Wall Depth 10 in. (254mm)

1 in. (25mm) clearance from appliance corner

45°to combustible wall Elbow

1 in. (25mm) clearance from appliance corner to combustible wall

When installing the Sapphire in a rear vent configuration with no vertical rise: a Snorkel Kit must be used, and a derating orifice must be installed. The appropriate orifice is supplied with the Rear Vent Kit.

Figure 5.5

PART HHW2 PART 841-0670 (Preferred)

WALL THIMBLE

Figure 5.6

NOTES:

(1)The four wood screws provided should be replaced with appropriate fasteners for stucco, brick, concrete, or other types of sidings.

(2)Termination cap HHW2 (Part #841-0670) is highly recommended on a building with vinyl siding, as the vinyl siding standoff is built in. The pilot hole will be 2 in. (51mm) closer to the bottom of the square than the top. Using a framing square, draw a 14 in. x 14 in. (356mm x 356mm) square around the pilot hole in the siding. See Figure 5.7 on the next page.

January 3, 2007

Quadra-Fire · Topaz · 7009-113E

Page 13

Image 13
Contents Do not Discard this Manual What to do if you smell gasDo Discardnot Manufactured Date Table of Contents 1Listing and Code Approvals BELOW. Keep Clear of ALL Obstructions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Getting Started Design & Installation ConsiderationsInspect Appliance & Components Tools and Supplies NeededSelecting Appliance Location Appliance Location and ClearancesClearances Design Purposes onlyVent Termination Minimum Clearances 4Termination LocationsAlcove Applications Venting Components Vent InformationUse of Elbows Measuring StandardsExceptions for Horizontal Installations How to Use the Vent GraphVenting Guidelines Vertical Distance from Appliance to 90 ElbowType B Rear Installations for Use with Rear Vent Kit Up & Out Installations for Top Vent ConfigurationsHorizontal Termination Type aRear Vent 203mm Direct Vent Pipe Vertical TerminationStep Wood Screws Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Existing Masonry Chimney Type a Up & Out Installations for Top Vent ConfigurationsCap Retro Connector Fuel Conversions Gas InformationConverting to LP Gas Propane Natural GAS Valve Regulator ReplacementPressure Gas PressuresCheck for GAS Leaks Gas ConnectionConnecting to the Appliance Recommendation for WireStanding Pilot Ignition System Wiring Wire Size Max. LengthON/OFF Remove Shipping Materials Appliance SetupTop to Rear Vent Conversion Leg Leveling System AccessoriesBrick Installation Front Installation Fronts shipped attached to faceFor Both Quartet and Solitaire Fronts Qty Description Positioning the LogsMineral Wool Blower Installation Glass Door Assembly Replacement31 Blower Wiring Diagram Shutter Adjustment Damper AdjustmentFor TOP or Rear Vent Installations Make adjustmentBefore Lighting Appliance Operating InstructionsControls Lighting Appliance For Your Safety Read Before LightingInitial Break-in Procedure Frequently Asked QuestionsAfter Appliance is Lit Symptom Possible Cause Corrective Action TroubleshootingBe Placed in this Opening After servicing Maintaining and Servicing Your ApplianceNecessary. USE Caution When CLEANING/HANDLING Ceramic Burner Maintenance Tasks InspectReference Materials Appliance Dimension DiagramVent Components Diagram Miscellaneous Vent Components ListItem # Description TopazBRNR-TOPAZ RD. Service Parts List cont’dRV-TPZ-CLG RV-TPZ-CCRRV-TPZ-CSB RV-TPZ-CWLCast Parts Individual Pieces RE. Accessories Warranty Policy This page Intentionally Left Blank Quadra-Fire · Topaz · 7009-113E January 3 This page Intentionally Left Blank Contact Information TopazDealer Telephone