period one

Absorption Refrigeration Cycle

notes

dilute

intermediate

concentrated

solution

solution

solution

 

 

Figure 9

These two fluids, the refrigerant and the absorbent, are mixed inside the chiller in various concentrations. The term dilute solution refers to a mixture that has a relatively high refrigerant content and low absorbent content. A concentrated solution has a relatively low refrigerant content and high absorbent content. An intermediate solution is a mixture of dilute and concentrated solutions.

steam or

condenser

hot water

cooling

generator

 

 

water

 

 

evaporator

chilled water

heat exchanger

absorber

Figure 10

Components of the Absorption Cycle

The four basic components of the absorption refrigeration cycle are the generator and condenser on the high-pressure side, and the evaporator and absorber on the low-pressure side. The pressure on the high-pressure side of the system is approximately ten times greater than that on the low-pressure side.

8

TRG-TRC011-EN

Image 13
Contents Air Conditioning Clinic Absorption Water Chillers Absorption Water Chillers Preface Contents TRG-TRC004-EN Introduction TRG-TRC011-EN Period one Absorption Refrigeration CyclePeriod one Reject heat Heat energy Absorption System Fluids High affinity for water refrigerant Components of the Absorption Cycle Conditions Steam or Hot waterrefrigerant vapor Generator Condenser Refrigerant then flows into the evaporator pan Absorber spray pump Solution Heat Exchanger Dilute Generator pump Equilibrium Chart Heat Solution temperature Period two Absorption Chiller TypesSingle-Effect Chiller Absorber Evaporator spray pump Spray pump Generator pump Double-Effect Chiller Vapor Low Temperature condenser Cooling Generator Water Evaporator Absorber Low-temperature generator pump Generator pump Absorption Chiller Types Direct-Fired Chiller Evaporator High-temperature high-temperature Generatorgenerator pump Chiller/Heater Absorption Chiller Types Changeover Absorption Chiller Types Period three Capacity ControlPeriod three Energy valve Generator Crystallization 10C 37.8C Capacity Control Capacity Control Capacity Control Heat exchanger bypass Evaporator pan Purge System Isolation valve Period four Maintenance ConsiderationsPeriod four Maintenance Considerations Test run with alternate fuel, if dual-fuel burner Maintenance Considerations Maintenance Considerations Corrosion inhibitor and performance additive recommendations Period five Application ConsiderationsCooling-Water Temperature Limitations Combination Chiller Plants 58F Special Considerations for Direct-Fired Chillers Application Considerations Equipment Rating Standards Period six ReviewPeriod six Review Review Review Questions for Period QuizQuiz TRG-TRC011-EN Answers Glossary Glossary Glossary Trane Company