Heat & Glo LifeStyle XLR-PLUS-N-AU Install Metal Roof Flashing, Assemble and Install Storm Collar

Page 39

F. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 10.11) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.12.

HORIZONTAL

OVERHANG

510 mm MIN.

610 mm MIN.

VERTICAL

WALL

LOWEST

DISCHARGE

OPENING

TERMINATION

CAP

X

305 mm

ROOF PITCH

IS X/ 305 mm

H (MIN.) - MINIMUM HEIGHT FROM ROOF

TO LOWEST DISCHARGE OPENING

Angle

H (Min.) mm

0°-26.6°

............................................................500*

26.6°-30.3°

............................................................500*

30.3°-33.7°

............................................................500*

33.7°-36.9°

............................................................610*

36.9°-39.8°

............................................................760

39.8°-42.5°

............................................................990

42.5°-45.0°

.........................................................1220.

45.0°-49.4°

.........................................................1520.

49.4°-53.1°

.........................................................1830.

53.1°-56.3°

.........................................................2130.

56.3°-59.0°

.........................................................2290.

59.0°-60.3°

.........................................................2440.

*910 mm minimum in snow regions

Figure 10.11 Minimum Height From Roof To Lowest Discharge Opening

NOTICE: Failure to properly caulk the roof flashing and pipe seams could cause water entry.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.12.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 10.12

G. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris.

Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.13).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.14).

Caulk around the top of the storm collar (see Figure 10.15).

Figure 10.13 Assembling the Storm Collar

Figure 10.14 Assembling the Storm Collar Around the Pipe

Heat & Glo • XLR-PLUS-N-AU, XLR-PLUS-PB-AU2264-900 Rev. M • 7/12

39

Image 39
Contents Ref No GSCS20194 AS45532008 SAI GlobalWhat to do if you smell gas Models XLR-PLUS-N-AU XLR-PLUS-PB-AU Homeowner Reference Information CongratulationsUser Guide Table of ContentsFinishing Appliance SetupTroubleshooting Component AccessLimited Lifetime Warranty Australian Warranty InformationOther Rights Perth This warranty is void ifListing and Code Approvals Gas Fireplace Safety Operating Instructions User GuideYour Fireplace Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches IPI Battery Tray/Battery InstallationLighting Instructions IPI Final inspection byAGE 110/120 VAC or 220/240 Control Module Operation Nine Hour Safety Shutdown FeatureFrequently Asked Questions Initial Break-in ProcedureAfter Fireplace is Lit Maintenance and Service Control Compartment and Firebox Top Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection FireboxTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseFront Side Finishing Detail Mantel and Wall ProjectionsMantels Combustible/Non-Combustible Mantel Leg Combustible/Non-CombustibleVent Termination Minimum Clearances Termination LocationsMIN. Clearance in. mm Vent Information and Diagrams Minimum H1 Maximum Top Vent Horizontal Termination Venting with 1 elbowMinimum H1 + H2 Maximum Top Vent Horizontal Termination Venting with 2 elbowsExhaust Restrictor Instructions Top Vent Vertical Termination No Elbows V1 Max= 13.4 m 44 ftV1 Minimum Maximum V1 + V2 Minimum Top Vent Vertical Termination Venting with 2 elbowsV1 Minimum H1 + H2 Maximum V1 + V2 Minimum Top Vent Vertical Termination Venting with 3 elbowsTop Vent Vertical Termination Venting with 4 elbows Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe SLP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationSecuring and Leveling the Appliance Installing the Optional Heat-Zone-240V Kit Assemble Vent Sections Installing Vent Pipe SLP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingInstall Vertical Termination Cap Install Decorative Wall ComponentsHeat Shield Requirements for Horizontal Termination 17 Venting through the Wall Install Horizontal Termination CapPropane Butane Gas InformationGas Connection Natural GasValve Pressure Taps Access Through the Valve AssemblyOptional Remote Control Receiver Location Wiring RequirementsIntelliFire Plus Ignition System Wiring Optional Accessories RequirementsJunction Cord Information Electrical Service and Repair BlowerKit Contents Fireplace Specific InformationIntroduction Determine Location Installation PrecautionsChanging Temperature Scale Installation of Remote Control HousingAUX300CE Module Installation Fan InstallationProgramming the RC300AU to the Control Module Function Buttons Idle When Remote is in on ModeStandby mode Display ScreenAdjusting Fan Speed About on ModeAbout OFF Mode Adjusting Flame HeightPower Outage Adjusting ThermostatAdjusting Timer Setting the Child LockSymptom Possible Cause Corrective Action Frequently Asked Questions/TroubleshootingFinishing Instructions Non-Combustible Materials SpecificationFinishing Framing and Finishing InstructionsFinishing Details Painting Finish and Sealing JointsFinishing Around Opening with Gypsum Wallboard Gas Pipe RequirementsTOP View Unlimited Overlap Fit Method Tonic or Martini Decorative Front Facing MaterialInside and Overlap Method See .C Decorative FrontsSee Figures 13.15 Dimensions of Tonic Decorative FrontAppliance Setup Air Shutter Setting Media OptionsVerify Performance of Appliance Troubleshooting Symptom Possible Cause Corrective ActionIntelliFire Plus Ignition System Ues to spark, and main Frequently Asked Questions/Troubleshooting Component Access Access Through the Valve Assembly Pilot Assembly Replacement Gas Valve ReplacementReference Materials Appliance Dimension DiagramInspect Maintenance Tasks Maintenance TasksDVP-HPC Cap Brick Extension Vent Components DiagramsSupport SLP-45 45 ElbowSLP90- 90 Elbow Ceiling FirestopSupport Box-Black SnorkelSLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP XLR-PLUS-N-AU, XLR-PLUS-PB-AU Service Parts#15 Valve Assembly XLR-PLUS-N-AU, XLR-PLUS-PB-AU Service Parts ListContact Information