Heat & Glo LifeStyle RED60 2159-900 manual Overlap Fit Method

Page 69

WARNING! Risk of Fire! DO NOT apply combustible materials beyond the minimum clearances. Comply with all minimum clearances to combustibles as specified in this manual. Overlapping materials could ignite and will interfere with proper operation of doors and louvers.

WARNING! Risk of Fire! DO NOT install drywall or other combustible materials directly onto the factory- installed non-combustible board. Overlapping materials could ignite.

Decorative facing material thickness is measured from the face of the factory-installed non-combustible board. See Figure 13.5.

The mesh front can be installed such that it overlaps non- combustible materials up to 1-1/4 in. thick. See Figure 13.6.Refer to Section 1.E and 1.F of this manual for defi- nition and qualifications and definition of non-combustible and combustible materials.

Specific requirements for each method if installation are described below and on the following pages of this section.

 

7 IN.

 

13-3/4 IN.

 

NON-COMBUSTIBLE BOARD

 

0-1-1/4 IN.

1 IN.

FACTORY-INSTALLED

NON-COMBUSTIBLE

 

 

BOARD

 

STANDARD

 

DECORATIVE FRONT

 

SHOWN

 

0-1-1/4 IN. THICK DRYWALL

 

OR EQUIVALENT

 

= AIR SPACE

Figure 13.7 Overlap Fit Method

Non-Combustible Finish Materials

0 to 1-1/4 inch thickness-Overlap Fit Method

The mesh front is designed to overlap finish materials 0 inches to 1-1/4 inch thick. See Figure 13.7.

NOTICE: This 1-1/4 inch maximum not only includes the decorative finish materials (marble, tile, slate, etc) but also the thin set, lath and adhesive used to attach the decorative finish material.

The non-combustible finish material can be installed up to the 17-1/8 inch (height) by 62-3/4 inch (width) fireplace opening.

30-7/8 IN. HEIGHT

FACTORY INSTALLED

NON-COMBUSTIBLE

BOARD

SIDE FINISH NON-COMBUSTIBLE BOARD (2)

68 IN. WIDTH

FACTORY INSTALLED NON-COMBUSTIBLE BOARD

= 2 IN. MAX. SCREW LENGTH

= NO SCREWS IN THIS AREA

Figure 13.6 Non-Combustible Finish Material Diagram for 0 - 1-1/4 Inch Thick Overlap Fit Method

Non-Combustible Finish Materials

0 Inches to 4 Inches Thick-Inside Fit Method

The mesh decorative front is approved for inside fit ap- plications. Non-combustible finishing materials up to 4 inches thick can be installed around the Mesh front (left, right, top, and bottom). See Figure 13.8.

1/2 IN. THICK

WALL SHEATHING

0-4 IN.

1/2 IN.

19-1/2 IN.

20-1/2 IN.

1/2 IN.

0- 4 IN.

DRYWALL OR

EQUIVALENT (1/2 IN.)

Figure 13.8 Inside Fit Method

Heat & Glo • RED60 • 2159-900 Rev. R • 9/12

69

Image 69 Contents
What to do if you smell gas ModelsHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Hearth & Home Technologies IncWarranty Conditions Limited Lifetime WarrantyListing and Code Approvals Requirements for the Commonwealth of Massachusetts Vent Directly BELOW. Keep Clear of ALL OB- StructionsManufacturer Requirements Gas Fireplace Safety Operating Instructions User GuideYour Fireplace Clear Space Decorative Doors and Fronts Fixed Glass AssemblyControl Module Operation Before Lighting FireplaceFinal inspection by Lighting Instructions IPIFrequently Asked Questions Initial Break-in ProcedureAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Doors, Surrounds, FrontsGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting FireboxTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Selecting Appliance Location Framing and ClearancesMinimum Framing Dimensions Constructing the Appliance ChaseClearances Mantel and Wall Projections TOP View Fireplace MIN MAX Opening Unlimited= Acceptable NON-COMBUSTIBLE Mantel LEG Zone Vent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Covered Alcove ApplicationsVent Information and Diagrams Components and Service Parts List Installation Instructions and Venting In- formation PVI-DVPInstallation Precautions Installation GuidelinesFraming and Clearances Chassis Dimensions Installation of Vent PipeFraming Dimensions Vent Pipe RegulationsAccess Panel Framing Dimensions Chase Appliance Wire Harness Wiring the PVI-DVPScrews PVI-DVP ConnectionsVacuum Switch Orientation Installation InspectionOperating Instructions MaintenanceVent Diagrams Top Vent Horizontal Termination Venting with 1 elbowMinimum + H 1 Maximum V1 Minimum V1 + H1 + H2 Maximum Top Vent Horizontal Termination Venting with 2 elbowsV1 Minimum V1 + V2 + H1 + H2 Maximum Top Vent Horizontal Termination Venting with 3 elbowsElbows Minimum Total V + Total H Maximum Minimum Total V + Total H Maximum25 Vertical Vent Maximum Minimum V1 + V2 + H Maximum Top Vent Vertical Termination Venting with 2 elbowsMinimum V1 + V2 + H1 + H2 Maximum Top Vent Vertical Termination Venting with 3 elbowsDirect Vent with 4 FT. Minimum Vertical OFF TOP of Appliance 29 Power Vent Positioned After Vertical Drop Components These Instructions Must Remain with the EquipmentVenting of More than ONE Appliance in a Common Vent System is ProhibitedWiring the PVK-80 Power Vent Installation Inspection 8K1-PVI AUX300 Operating Instructions To Reassemble the Power Vent V1 Minimum V1 + H1 Maximum PVK-80 Top Vent Horizontal Termination Venting with 1 elbowPVK-80 Top Vent Horizontal Termination Venting with 2 elbows Elbows V1 + V2 Minimum Total V + Total H Maximum MAX. Elbows MAX. Total Vent RUN FT MAX. VERT. Drop FT Pipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe DVP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Top Vent Appliance PreparationFiberglass Rope RingSecuring and Leveling the Appliance Setting the Fireplace into the FramingDetail a Active Convection TechnologyAssemble Vent Sections Installing Vent Pipe DVP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingInstall Vertical Termination Cap Install Horizontal Termination CapHeat Shield Requirements for Horizontal Termination Gas Information Fuel ConversionGas Pressure Gas Connection Gas and Electrical AccessIntelliFire PlusTM Ignition System Wiring Wiring RequirementsOptional Configuration Requirements Electrical InformationWires from touching the blower Optional LED Lighting Circuit Switch Tripped Color ProducedActive Convection Blower Replacement Electrical Service and Repair Junction Box Installation Blower TAB on Mounting Plate Slot on Blower HousingFinishing Non-Combustible Materials SpecificationSplatter Guard Framing and Finishing InstructionsFinish and Sealing Joints Finishing Around Opening with Gypsum WallboardPainting IN. Thick Facing MaterialOverlap Fit Method Mesh Fronts 10 Mesh Front InstallationAppliance Setup Rock Media Placement JIG Pilot Shield Porcelain Instructions Kit ContentsRED60 Model Without Media Tools RequiredNNN NNP InstallationDescription Part Number Service PartsRED60 Model With Media InstallationBend TAB UP Back Panel Pieces Granite Instructions19-3/8 Notched Area Over Pilot Installing First Back Panel Granite PieceGlass Assembly Tabs Face Glass Assembly Placing Back Panel Piece Glass Frame TAB Retaining TAB ALL Gaps Equal Tabs Sheet Metal Refractory InstructionsSMR-60NL Item Description Comments Part NumberInstall the Mesh Air Shutter SettingAir Shutter Settings Troubleshooting Symptom Possible Cause Corrective ActionIntelliFire Plus Ignition System Pilot PVI-DVP TroubleshootingReference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP vent components DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2 DVP-HPC1 DVP-HPC2RF6M RF12M DVP-FBHT RED60 RED60 Service Parts ServiceContact Information