B. Assemble Slip Sections

Slide the inner flue of the slip section into the inner flue of the pipe section and the outer flue of the slip section over the outer flue of the pipe section. See Figure 10.3.

Slide together to the desired length.

Pilot hole

Figure 10.3 Slip Section Pilot Holes

Maintain a 1-1/2 in. (38 mm) overlap between the slip section and the pipe section.

Secure the pipe and slip section with two screws no longer than 1/2 in. (13 mm), using the pilot holes in the slip section. See Figure 10.4.

Figure 10.4 Screws into Slip Section

Continue adding pipe as necessary following instructions in “Assembling Pipe Sections.”

NOTICE: If slip section is too long, the inner and outer flues of the slip section can be cut to the desired length.

NOTICE: When installing a vent system with an HRC termination cap, all pipe system joints shall be sealed using a high temperature silicone sealant (300ºF minimum continuous exposure rating).

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections.

Only outer pipes are sealed, sealing the inner flue is not required.

All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed.

C. Secure The Vent Sections

Vertical runs of pipe must be supported every 8 ft. (2.44 m).

Horizontal sections must be supported every 5 feet (1.52 m).

Vent supports or plumbers strap (spaced 120º apart) may be used to support. See figures 10.5 and 10.6.

Wall shield firestops may be used to provide horizontal support.

Ceiling firestops have tabs that may be used to provide vertical support.

WARNING! Risk of Fire, Explosion or Asphyxiation! Improper support may allow vent to sag and separate. Use vent run supports and connect vent sections per in- stallation instructions. DO NOT allow vent to sag below connection point to appliance.

Figure 10.5 Securing Vertical Pipe Sections

Figure 10.6 Securing Horizontal Pipe Sections

Heat & Glo • RED60 • 2159-900 Rev. R • 9/12

55

Image 55 Contents
What to do if you smell gas ModelsHomeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty Limited Lifetime Warranty Hearth & Home Technologies IncWarranty Conditions Limited Lifetime WarrantyListing and Code Approvals Vent Directly BELOW. Keep Clear of ALL OB- Structions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Operating Instructions User Guide Gas Fireplace SafetyYour Fireplace Clear Space Before Lighting Fireplace Fixed Glass AssemblyDecorative Doors and Fronts Control Module OperationFinal inspection by Lighting Instructions IPIInitial Break-in Procedure Frequently Asked QuestionsAfter Fireplace is Lit Doors, Surrounds, Fronts Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningFirebox Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesConstructing the Appliance Chase Minimum Framing DimensionsClearances TOP View Fireplace MIN MAX Opening Unlimited Mantel and Wall Projections= Acceptable NON-COMBUSTIBLE Mantel LEG Zone Vent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Covered Alcove ApplicationsVent Information and Diagrams Installation Guidelines Installation Instructions and Venting In- formation PVI-DVPComponents and Service Parts List Installation PrecautionsVent Pipe Regulations Installation of Vent PipeFraming and Clearances Chassis Dimensions Framing DimensionsAccess Panel Framing Dimensions Chase Appliance PVI-DVP Connections Wiring the PVI-DVPWire Harness ScrewsVacuum Switch Orientation Installation InspectionOperating Instructions MaintenanceTop Vent Horizontal Termination Venting with 1 elbow Vent DiagramsMinimum + H 1 Maximum V1 Minimum V1 + H1 + H2 Maximum Top Vent Horizontal Termination Venting with 2 elbowsMinimum Total V + Total H Maximum Top Vent Horizontal Termination Venting with 3 elbowsV1 Minimum V1 + V2 + H1 + H2 Maximum Elbows Minimum Total V + Total H Maximum25 Vertical Vent Maximum Minimum V1 + V2 + H Maximum Top Vent Vertical Termination Venting with 2 elbowsMinimum V1 + V2 + H1 + H2 Maximum Top Vent Vertical Termination Venting with 3 elbowsDirect Vent with 4 FT. Minimum Vertical OFF TOP of Appliance 29 Power Vent Positioned After Vertical Drop Common Vent System is Prohibited These Instructions Must Remain with the EquipmentComponents Venting of More than ONE Appliance in aWiring the PVK-80 Power Vent Installation Inspection 8K1-PVI AUX300 Operating Instructions To Reassemble the Power Vent V1 Minimum V1 + H1 Maximum PVK-80 Top Vent Horizontal Termination Venting with 1 elbowPVK-80 Top Vent Horizontal Termination Venting with 2 elbows Elbows V1 + V2 Minimum Total V + Total H Maximum MAX. Elbows MAX. Total Vent RUN FT MAX. VERT. Drop FT Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe DVP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Rope Ring Appliance Preparation Top Vent FiberglassSecuring and Leveling the Appliance Setting the Fireplace into the FramingDetail a Active Convection TechnologyAssemble Vent Sections Installing Vent Pipe DVP PipeSecure The Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingInstall Horizontal Termination Cap Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Fuel Conversion Gas InformationGas Pressure Gas Connection Gas and Electrical AccessElectrical Information Wiring RequirementsIntelliFire PlusTM Ignition System Wiring Optional Configuration RequirementsWires from touching the blower Optional LED Lighting Circuit Switch Tripped Color ProducedActive Convection Blower Replacement Electrical Service and Repair Junction Box InstallationBlower TAB on Mounting Plate Slot on Blower HousingFraming and Finishing Instructions Non-Combustible Materials SpecificationFinishing Splatter GuardFinishing Around Opening with Gypsum Wallboard Finish and Sealing JointsPainting IN. Thick Facing MaterialOverlap Fit Method Mesh Fronts 10 Mesh Front InstallationAppliance Setup Rock Media Placement JIG Pilot Shield Tools Required Kit ContentsPorcelain Instructions RED60 Model Without MediaNNN NNP InstallationDescription Part Number Service PartsRED60 Model With Media InstallationBend TAB UP Back Panel Pieces Granite Instructions19-3/8 Notched Area Over Pilot Installing First Back Panel Granite PieceGlass Assembly Tabs Face Glass Assembly Placing Back Panel Piece Glass Frame TAB Retaining TAB ALL Gaps Equal Tabs Sheet Metal Refractory InstructionsSMR-60NL Item Description Comments Part NumberAir Shutter Setting Install the MeshAir Shutter Settings Symptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Pilot PVI-DVP TroubleshootingReference Materials Appliance Dimension DiagramDVP-AS2 Vent Components DiagramsDVP vent components DVP-TRAP1 DVP-TRAP2 DVP-TRAPK1 DVP-TRAPK2 DVP-HPC1 DVP-HPC2RF6M RF12M DVP-FBHT RED60 RED60 Service Parts ServiceContact Information