G. Install Metal Roof Flashing

See minimum vent heights for various pitched roofs (Figure 10.14) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.15.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12.......................... 3.25

Over 11/12 to 12/12............................ 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.14 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing and pipe seams may permit entry of water.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.15.

Caulk the overlap seam of any exposed pipe sections that are located above the roof line.

CAULK

Figure 10.15

H. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.16).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.17).

Caulk around the top of the storm collar (see Figure 10.18).

Figure 10.16 Assembling the Storm Collar

Figure 10.17 Assembling the Storm Collar Around the Pipe

Heat & Glo • 6000C, 6000C-IPI, 8000C, 8000C-IPI2164-900 Rev. T • 9/12

49

Image 49
Contents HOT Surfaces What to do if you smell gasHot glass will cause burns Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Hearth & Home Technologies IncWarranty Conditions Limited Lifetime WarrantyBTU Specifications Tempered Glass SpecificationsHigh Altitude Installations Listing and Code ApprovalsCombustible Materials Specification Non-Combustible Materials SpecificationElectrical Codes C22.1Requirements for the Commonwealth of Massachusetts Operating Instructions User Guide Gas Fireplace SafetyYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyFan Kit optional Clear SpaceModule Reset IPI Battery Tray/Battery InstallationNine Hour Safety Shutdown Feature Control Module OperationFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveLighting Instructions Standing Pilot For Your Safety Read Before Lighting Lighting InstructionsIssue Solutions Frequently Asked QuestionsAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting LogsBase Refractory Refractory, Grate and Valve Assembly RemovalNotch Location Burner Identification/VerificationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Any such action may cause a fire hazardSelecting Appliance Location Framing and Clearances6000 8000Clearances Constructing the Appliance Chase6000 8000Combustible Mantels Mantel and Wall ProjectionsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination Locations= 9 inches U.S.A Covered Alcove ApplicationsApproved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsOne Elbow Vent Diagrams Top Vent Horizontal TerminationVent pipe, if desired 6000C-IPI 8000C-IPI V1 Minimum H1 MaximumThree Elbows Top Vent Horizontal Termination Two Elbows6000C-IPI V1 Minimum H1 + H2 Maximum 8000C-IPI V1 Minimum H1 + H2 MaximumBreak Maximum + V 2 Min Top Vent Vertical TerminationH1 + H2 V1 + V2 Minimum H1 + H2 Maximum Top Vent Vertical Termination Three ElbowsPage H1 Maximum V1 Minimum H1 + H2 Maximum Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max V1 Minimum H1 Maximum Rear Vent Vertical Termination One ElbowMinimum + H Maximum V1 Minimum H1 + H2 + H3 Maximum 10 ft Rear Vent Vertical Termination Three ElbowsCoaxial to Colinear Venting Prior to installing the gas applianceClearances to Combustibles Termination Cap Flue DamperConnecting the LINK-DV30B to the DV-46DVA-GCL adapter Connecting the DV-46DVA-GCL Adapter to Appliance Top VentRear Vent Pipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe DVP SLP Install the Ceiling FirestopInstalling the Optional Heat-ZoneGas Kit Install Attic Insulation ShieldFlat Ceiling Installation Vaulted Ceiling InstallationTop Vent Appliance PreparationCut the metal retaining band and fold the sides out Rear VentSecuring and Leveling the Appliance Installing the Non-combustible BoardHeader Attach Vent to the Firebox Assembly Installing Vent Pipe DVP and SLP PipeAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Assemble and Install Storm Collar Install Metal Roof FlashingRoof Pitch Min. Ft Install Decorative Wall Components SLP only Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination DVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeFuel Conversion Gas InformationGas Pressure Gas ConnectionIntelliFire Plus Ignition System Wiring Wiring RequirementsStanding Pilot Ignition System Wiring Optional Accessories RequirementsTo Junction Wall Switch Installation for Fan Optional Electrical Service and Repair Junction Box InstallationFacing Material FinishingFinishing Material Inch Thick or Less DoorsDoor FIT Finish Material See Thickness Finishing Material Thickness 0-4 inches maximum Finishing Material Thickness 1-4 inches maximumModels Finishing Strips Removed Removal of Finishing StripsElevated Hearth Systems Appliance Setup 6000C, 6000C-IPI Install the Log Assembly Log Assembly LOGS-6CBottom view Logs # 2 LOG Contacts Grate Tines 8000C-IPILP, 8000CBV-IPI Install the Log Assembly Log Assembly LOGS-8CHorizontal Grate BAR Air Shutter Setting Install Trim and/or SurroundAir Shutter Settings 6000 8000Symptom Possible Causes Corrective Action TroubleshootingStanding Pilot Ignition System Symptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Shorts in the wiringReference Materials Appliance Dimension DiagramLocation Inches Millimeters GAS Line Access R Left Side TOP View Front View Right View DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPBEK DVP-BEK2 RF6M RF12MDVP-TRAPFL COOL-ADDMDVP-FBHT DVP-TVHWPower Vent Inline Optional Wire HarnessPVI-SLP SLP-LPCLINK-DV30B DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAPDV-46DVA-GCL DVP-2SL AdapterSLP90 SLP45SLP Pipe DVP-SLP24DVP-2SL SLP-TRAPSLP-WT-BK SLK-SNKD SLP-CCS-BKSLP-DCF-BK SLP-TVHWAt Depot Service PartsGas Fireplace DV Beginning Manufacturing Date Aug8000C, 8000C-IPI 8000C-IPI 6000C-IPI6000C Stocked8000C IPI Conversion Kits Standing Pilot Conversion KitsContact Information