10 Installing Vent Pipe (DVP and SLP Pipe)

A. Assemble Vent Sections (DVP Pipe Only)

Attach Vent to the Firebox Assembly

Note: The end of the pipe sections with the lanced tabs will face toward the appliance.

Attach the first pipe section to the starting collar:

Lanced pipe end to the starting collar

Inner pipe over inner collar

Push the pipe section until all lanced tabs snap in place

Lightly tug on pipe to confirm it has locked.

Commercial, Multi-family (Multi-level exceeding two sto- ries), or High-Rise Applications

All outer pipe joints must be sealed with silicone with a minimum of 300ºF continuous exposure rating, including the slip section that connects directly to the horizontal termi- nation cap.

Figure 10.1 High Temperature Silicone Sealant

Apply a bead of silicone sealant inside the female outer pipe joint prior to joining sections. See Figure 10.1

Only outer pipes need to be sealed. All unit collar, pipe, slip section, elbow and cap outer flues shall be sealed in this manner, unless otherwise stated.

WARNING! Risk of Fire or Explosion! DO NOT break silicone seals on slip sections. Use care when remov- ing termination cap from slip pipe. If slip section seals are broken during removal of the termination cap, vent may leak.

A

B

Figure 10.2

Lances

Figure 10.3

Assemble Pipe Sections

Per Figure 10.2:

Start the inner pipe on the lanced end of section A into the flared end of section B.

Start the outer pipe of section A over the outer pipe of section B.

Once both vents sections are started, push firmly until all lanced tabs lock into place.

Lightly tug on the pipe to confirm the tabs have locked.

It is acceptable to use screws no longer than 1/2 in. (13

mm)to hold outer pipe sections together. If predrilling holes, DO NOT penetrate inner pipe.

For 90º and 45º elbows that are changing the vent direction from horizontal to vertical, one screw minimum should be put in the outer flue at the horizontal elbow joint to prevent the elbow from rotating. Use screws no longer than 1/2 in. (13 mm). If predrilling screw holes, DO NOT penetrate inner pipe.

Note: Make sure that the seams are not aligned to prevent unintentional disconnection.

CORRECT

Figure 10.4 Seams

INCORRECT

Heat & Glo • 6000C, 6000C-IPI, 8000C, 8000C-IPI2164-900 Rev. T • 9/12

45

Image 45
Contents What to do if you smell gas HOT SurfacesHot glass will cause burns Homeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Hearth & Home Technologies IncWarranty Conditions Limited Lifetime WarrantyBTU Specifications Tempered Glass SpecificationsHigh Altitude Installations Listing and Code ApprovalsCombustible Materials Specification Non-Combustible Materials SpecificationElectrical Codes C22.1Requirements for the Commonwealth of Massachusetts Gas Fireplace Safety Operating Instructions User GuideYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyFan Kit optional Clear SpaceModule Reset IPI Battery Tray/Battery InstallationNine Hour Safety Shutdown Feature Control Module OperationFinal inspection by Lighting Instructions IPIWhat to do if YOU Smell GAS GAS ValveLighting Instructions Standing Pilot For Your Safety Read Before Lighting Lighting InstructionsFrequently Asked Questions Issue SolutionsAfter Fireplace is Lit Maintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlGasket Seal and Glass Assembly Inspection Maintenance Tasks-Qualified Service TechnicianVenting LogsBase Refractory Refractory, Grate and Valve Assembly RemovalNotch Location Burner Identification/VerificationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Any such action may cause a fire hazardSelecting Appliance Location Framing and Clearances6000 8000Clearances Constructing the Appliance Chase6000 8000Mantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination Locations= 9 inches U.S.A Covered Alcove ApplicationsApproved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsOne Elbow Vent Diagrams Top Vent Horizontal TerminationVent pipe, if desired 6000C-IPI 8000C-IPI V1 Minimum H1 MaximumThree Elbows Top Vent Horizontal Termination Two Elbows6000C-IPI V1 Minimum H1 + H2 Maximum 8000C-IPI V1 Minimum H1 + H2 MaximumBreak Maximum + V 2 Min Top Vent Vertical TerminationH1 + H2 V1 + V2 Minimum H1 + H2 Maximum Top Vent Vertical Termination Three ElbowsPage Rear Vent Horizontal Termination Two Elbows H1 Maximum V1 Minimum H1 + H2 MaximumH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max Rear Vent Vertical Termination One Elbow V1 Minimum H1 MaximumMinimum + H Maximum V1 Minimum H1 + H2 + H3 Maximum 10 ft Rear Vent Vertical Termination Three ElbowsCoaxial to Colinear Venting Prior to installing the gas applianceClearances to Combustibles Termination Cap Flue DamperConnecting the DV-46DVA-GCL Adapter to Appliance Top Vent Connecting the LINK-DV30B to the DV-46DVA-GCL adapterRear Vent Pipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe DVP SLP Install the Ceiling FirestopInstalling the Optional Heat-ZoneGas Kit Install Attic Insulation ShieldFlat Ceiling Installation Vaulted Ceiling InstallationTop Vent Appliance PreparationCut the metal retaining band and fold the sides out Rear VentInstalling the Non-combustible Board Securing and Leveling the ApplianceHeader Attach Vent to the Firebox Assembly Installing Vent Pipe DVP and SLP PipeAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Slip Sections Assemble Vent Sections SLP Pipe OnlyDisassemble Vent Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarRoof Pitch Min. Ft Install Vertical Termination Cap Install Decorative Wall Components SLP onlyHeat Shield Requirements for Horizontal Termination DVP-HPC1 DVP-HPC2 Install Horizontal Termination Cap DVP and SLP PipeFuel Conversion Gas InformationGas Pressure Gas ConnectionIntelliFire Plus Ignition System Wiring Wiring RequirementsStanding Pilot Ignition System Wiring Optional Accessories RequirementsTo Junction Wall Switch Installation for Fan Optional Electrical Service and Repair Junction Box InstallationFacing Material FinishingDoors Finishing Material Inch Thick or LessDoor FIT Finish Material See Thickness Finishing Material Thickness 1-4 inches maximum Finishing Material Thickness 0-4 inches maximumModels Finishing Strips Removed Removal of Finishing StripsElevated Hearth Systems Appliance Setup Install the Log Assembly Log Assembly LOGS-6C 6000C, 6000C-IPIBottom view Logs # 2 LOG Contacts Grate Tines 8000C-IPILP, 8000CBV-IPI Install the Log Assembly Log Assembly LOGS-8CHorizontal Grate BAR Air Shutter Setting Install Trim and/or SurroundAir Shutter Settings 6000 8000Troubleshooting Symptom Possible Causes Corrective ActionStanding Pilot Ignition System Symptom Possible Cause Corrective Action TroubleshootingIntelliFire Plus Ignition System Shorts in the wiringAppliance Dimension Diagram Reference MaterialsLocation Inches Millimeters GAS Line Access R Left Side TOP View Front View Right View DVP-AS2 Vent Components DiagramsHorizontal Termination Cap DVP-TRAPBEK DVP-BEK2 RF6M RF12MDVP-TRAPFL COOL-ADDMDVP-FBHT DVP-TVHWPower Vent Inline Optional Wire HarnessPVI-SLP SLP-LPCLINK-DV30B DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAPDV-46DVA-GCL DVP-2SL AdapterSLP90 SLP45SLP Pipe DVP-SLP24SLP-TRAP DVP-2SLSLP-WT-BK SLK-SNKD SLP-CCS-BKSLP-DCF-BK SLP-TVHWAt Depot Service PartsGas Fireplace DV Beginning Manufacturing Date Aug8000C, 8000C-IPI 8000C-IPI 6000C-IPIStocked 6000C8000C IPI Conversion Kits Standing Pilot Conversion KitsContact Information