Initial Installation
QUALIFIED INSTALLERS ONLY
5.Using tin snips, cut the “Support Box” from the top corners down to the roof line, and fold the resulting flaps over the roof sheathing (Figure 36). Before nailing it in to the roof, run a bead of
6.Complete the cathedral ceiling installation by following the same procedures outlined in Steps 4 through 9 for Initial
Installation - Vertical Installation.
Figure 36: Cathedral Ceiling Support Box
Installation.
Corner Installations:
Do not interfere with the structural integrity of the walls.
When rear venting if a 90° bend is used the maximum horizontal vent that can be used is 6” (152mm) and if a 45° bend is used the maximum horizontal vent that can be used is 12” (305mm). For installations
with a 36” (915 mm) snorkel refer to Figure 37 and Initial Installation - Vent Configurations and Restrictor
Settings. For other corner installations refer to Figure 38 and Initial Installation - Vent Configurations and
Restrictor Settings.
|
|
|
Figure 37: Corner installation rear vented with |
| Figure 38: Corner installation top vented. |
snorkel. |
|
|
25