Figure 3: Recommended Water Piping for

Zone Valve Zoned Heating Systems

WARNING

Safety relief valve discharge piping must be piped near floor to eliminate potential of severe burns. Do not pipe in any area where freezing could occur. Do not install any shut-off valves.

D.Install circulator with flanges, gaskets and bolts provided. Five foot long circulator harness allows circulator to be mounted on supply or return. Connect harness to circulator and secure any excess conduit.

E.For heating only system piping, see Figure 3. Consult also I=B=R Installation Guides.

F.For space heating and domestic water heating with Alliance SL™ water heater (intermittent circulation only); install Alliance SL™ water heater as a separate heating zone. Refer to Alliance SL™

Installation, Operating and Service Instructions for additional information.

G.If this boiler is used in connection with refrigeration systems, the boiler must be installed so that the chilled medium is piped in parallel with the heating boiler using appropriate valves to prevent the chilled medium from entering the boiler, see Figure 4. Also consult I=B=R Installation and Piping Guides.

If this Boiler is connected to heating coils located in air handling units where they may be exposed to refrigerated air, the boiler piping must be equipped

Figure 4: Recommended Piping for Combination Heating & Cooling (Refrigeration) Systems

with flow control valves to prevent gravity circulation of boiler water during the operation of the cooling system.

H.Use a boiler bypass if the boiler is to be operated in a system which has a large volume or excessive radiation where low boiler water temperatures may be encountered (i.e. converted gravity circulation system, etc.).

Install a pipe tee at the boiler return along

with a second tee in the supply piping as shown in Figure 3. The bypass should be the same size as the supply and return lines with valves located in the bypass and supply outlet as illustrated in Figure 3 in order to regulate water flow to maintain higher boiler water temperatures.

Set the by-pass and boiler supply valves to a half throttle position to start. Operate boiler until the system water temperature is at a normal operating range.

Adjust the valves to provide 180° to 200°F supply water temperature. Opening the boiler supply valve will raise the system temperature, while opening the by-pass valve will lower the system supply temperature.

I.A hot water boiler installed above radiation level must be provided with a low water cutoff device as part of the installation.

If a low water cut-off is required, it must be mounted in the system piping above the boiler.

The minimum safe water level of a hot water boiler is just above the highest water containing cavity of the boiler; that is, a hot water boiler must be full of water to operate safely.

Refer to Section VI for low water cut-off piping and wiring instructions.

J.If it is required to perform a long term pressure test of the hydronic system, the boiler should first be isolated to avoid a pressure loss due to the escape of air trapped in the boiler.



Image 7
Contents Price $3.00 Series 2 model BTable of Contents Weight Clearances Do not drop boiler. Do not bump boiler jacket against floorMinimum Clearances Specific Gravity Correction Factors for Natural Gas Equivalent Length of FittingsBoiler Piping Page Page Do not use one vent damper to control two heating appliances Page Wiring Diagrams and Heat Anticipator Settings Page Safety Shutdown Sequence of Operation Page Sequence of Operation Normal Operation Wiring Schematic, Zone Valves II. Operating Instructions Top View of VR Gas Valves Yellow LED Flame Codes Instructions to PUT the Boiler in OperationGreen LED Status Codes Lighting Instructions Check Pilot Burner Flame Check GAS Input Rate to BoilerCombustion Chamber BURN-OFF Check Ignition System Safety SHUT-OFF DeviceIII. Trouble Shooting IV. Service Pilot Burner Location Burner 40mm BurnerAvoid Breathing Fiber Particulates and Dust Section Assembly Gravity Circulation Only Repair PartsCanopy Group Section Assembly and Canopy GroupThis page Left Intentionally Blank Base Assembly USS Manifold and Main Burners Inch Main Burners Manifold and Main Burners 1 Inch Main Burners Only MM Main Burners Only Manifold and Main Burners 40mm Main Burners4B MM Main Burner, Electronic Ignition Only 4D MM Main Burner, Natural Gas, 5001-9000 Ft. USA Only MM Main Burners Only 4C MM Main Burner Manifold4D MM Main Burner, Natural Gas, 2001-5000 Ft. USA Only 4D MM Main Burner, LP Gas, 2001-5000 Ft. USA OnlyBurner Only 40mm Burner Only Pilot Burner, Honeywell Q327A1147 Pilot Burner, Honeywell Q348A1002 Jacket Assembly Jacket Assembly, CompletePage Jacket Vestibule Panel Water Trim Limit Control Transformer Continuous and Gravity Circulation Only Transformer/Relay Assembly Intermittent Circulation OnlyFlame Rollout Switch Blocked Vent SwitchVent Damper Draft Hood CartonVent Reducer Service Record Service Record Service Record Lwco Location Wiring of Typical LwcoLimited Warranty