Burnham Series 2B manual IV. Service

Page 26

IV. Service

1.Inspection should be conducted annually. Service as frequently as specified in paragraphs below. While service or maintenance is being done, Electrical Power and all Gas Supply to the Boiler must be "off".

CAUTION

Label all wires prior to disconnection when servicing controls. Wiring errors can cause improper and dangerous operation. Verify proper operation after servicing.

ATTENTION. Au moment de l’entretien des commandes, étiquetez tous les fils avant de les débrancher. Les erreurs de câblage peuvent nuire au bon fonctionnement et être dangereuses.

S’assurer que l’appareil fonctionne adéquatement une fois l’entretien terminé.

2.Vent System. Vent system (see Figure 8 for typical installation) should be checked annually for:

A.Obstructions.

B.Accumulations of soot.

C.Deterioration of vent pipe or vent accessories due to condensation or other reasons.

D.Proper support - no sags, particularly in horizontal runs.

E.Tightness of joints.

F.Proper vent damper operation - see Section II Operating Instructions, paragraph 9.

G.Remove all accumulations of soot with wire brush and vacuum, see Figure 29. Remove all obstructions. Replace all deteriorated parts and support properly. Seal all joints.

3.Cleaning Boiler Flues, see Figure 29.

Flue passageways in the boiler sections should be checked annually for any blockage or accumulation of soot. To obtain access to flueways:

A.Remove vent pipe, damper (if boiler is so equipped), blocked vent switch, and draft hood.

B.Remove sheet metal screws securing Jacket Top Panel, lift panel and rotate about relief valve piping until top of boiler is exposed.

C.Remove bolts securing Canopy to Boiler Sections.

Remove Canopy - flueways are now exposed.

D.Models with flue gas baffles only: Remove baffles by lifting out of flueways.

Using flashlight, examine all flue passageways. If passageways are free of soot and obstruction, replace canopy (and flue gas baffles, if applicable), and seal.

Reinstall Jacket Top Panel, draft hood, blocked vent switch, damper (if boiler is so equipped), and vent pipe.

If the flue passageways need cleaning, remove burners as described in paragraph 4 below. Using long handle wire or bristle flue brush and vacuum, brush flueways thoroughly from top of boiler as illustrated in Figure 29. Replace canopy and seal with boiler putty. Reinstall Jacket Top Panel, draft hood, blocked vent switch, damper (if boiler is so equipped), and vent pipe.

NOTICE

4.Burners and firebox should be cleaned annually, and if necessary adjusted once a year BY a qualified service agency.

A. To remove burners for cleaning, changing orifice plugs, or repairs.

1.Remove the jacket front panel.

2.Disconnect pilot tubing at the gas valve. See Figure 17.

3.Disconnect thermocouple (standing pilot) or pilot lead wires (electronic ignition) at the gas valve.

4.40mm burners only. Remove injection shield assembly, where used. See Figure 30.

5.Remove wires to flame roll-out switch.

6.Remove the burner access panel.

7.Mark the location of the pilot main burner on the manifold if the marking on manifold is missing or obliterated.

Figure 29: Cleaning of Vent System

and Boiler Flues

26

Image 26
Contents Series 2 model B Price $3.00Table of Contents Weight Do not drop boiler. Do not bump boiler jacket against floor ClearancesMinimum Clearances Boiler Piping Equivalent Length of FittingsSpecific Gravity Correction Factors for Natural Gas Page Page Do not use one vent damper to control two heating appliances Page Wiring Diagrams and Heat Anticipator Settings Page Safety Shutdown Sequence of Operation Page Sequence of Operation Normal Operation Wiring Schematic, Zone Valves II. Operating Instructions Top View of VR Gas Valves Instructions to PUT the Boiler in Operation Yellow LED Flame CodesGreen LED Status Codes Lighting Instructions Check GAS Input Rate to Boiler Check Pilot Burner FlameCheck Ignition System Safety SHUT-OFF Device Combustion Chamber BURN-OFFIII. Trouble Shooting IV. Service Burner 40mm Burner Pilot Burner LocationAvoid Breathing Fiber Particulates and Dust Repair Parts Section Assembly Gravity Circulation OnlySection Assembly and Canopy Group Canopy GroupThis page Left Intentionally Blank Base Assembly USS Manifold and Main Burners Inch Main Burners Manifold and Main Burners 1 Inch Main Burners Only 4B MM Main Burner, Electronic Ignition Only Manifold and Main Burners 40mm Main BurnersMM Main Burners Only 4D MM Main Burner, LP Gas, 2001-5000 Ft. USA Only MM Main Burners Only 4C MM Main Burner Manifold4D MM Main Burner, Natural Gas, 2001-5000 Ft. USA Only 4D MM Main Burner, Natural Gas, 5001-9000 Ft. USA OnlyBurner Only 40mm Burner Only Pilot Burner, Honeywell Q327A1147 Pilot Burner, Honeywell Q348A1002 Jacket Assembly, Complete Jacket AssemblyPage Jacket Vestibule Panel Water Trim Limit Control Blocked Vent Switch Transformer/Relay Assembly Intermittent Circulation OnlyFlame Rollout Switch Transformer Continuous and Gravity Circulation OnlyVent Reducer Draft Hood CartonVent Damper Service Record Service Record Service Record Wiring of Typical Lwco Lwco LocationLimited Warranty