Hearth and Home Technologies CNXT4236IH Vent Diagrams, Top Vent Horizontal Termination, One Elbow

Page 23

E. Vent Diagrams

To replace the first starter elbow with two 45° elbows, refer to Figure 7.4. All other 90° elbows can be replaced with two 45° elbows.

General Rules:

SUBTRACT 3 ft. from the total H measurement for each 90° elbow installed horizontally.

SUBTRACT 1-1/2 ft. from the total H measurement for each 45° elbow installed horizontally.

A maximum of three 90° elbows (or six 45° elbows) may be used in any vent configuration. Some elbows may be installed horizontally. See Figure 7.9.

Elbows may be placed back to back anywhere in the system as long as the first 90° elbow is a starter elbow except as shown in Figure 7.4.

When penetrating a combustible wall, a wall shield firestop must be installed.

When penetrating a combustible ceiling, a ceiling firestop must be installed.

Horizontal runs of vent do not require vertical rise; horizontal runs may be level.

1. Top Vent - Horizontal Termination

One Elbow

V1

H1

V1 min.

V1 max.

H1 max.

ft

m

ft

m

ft

m

0

0.00

-

-

1.5

0.46

0.5

0.15

-

-

6

1.83

 

 

 

 

 

 

1

0.30

-

-

11

3.35

1.5

0.46

-

-

18

5.49

2

0.61

-

-

25

7.62

 

 

 

 

 

 

 

DVP

25

7.62

25

7.62

 

SLP

23

7.01

23

7.01

You may install a DVP elbow directly on top of the

CNXT4236 and on top of the CNXT4842.

Figure 7.3

Note: The CNXT series appliances can adapt to SLP series vent pipe when venting off the top of the appliance. You must use a DVP-SLP24 adapter which can only be attached to the appliance starting collar.

When looking at horizontal termination diagrams, the adapter is not counted as part of the minimum vertical (V1 min.) requirements.

Whether horizontal or vertical termination, the adapter is counted as part of the maximum vertical limitations.

All venting rules for the vent run must still be followed.

HORIZONTAL EXAMPLE

V1 = 1 ft.

H1 = 11 ft. max.

DVP

V1 = 1 ft.

H1 = 11 ft.

max

DVP-SLP24

SLP

VERTICAL EXAMPLE

 

 

 

 

DVP-SLP24

12 ft (3.66 m) min.

12 ft (3.66 m) min.

Adapter

60 ft (18.29 m) max.

60 ft (18.29 m) max.

 

DVP

SLP

Heatilator • Caliber CNXT Series • 4047-132 Rev U • 11/08

23

Image 23
Contents What to do if you smell gas Installation and OperationModels Direct Vent Gas ApplianceHomeowner Reference Information CongratulationsUser Guide Table of ContentsInstaller Guide Reference Materials Appliance SetupTroubleshooting FinishingCONDITIONS, Exclusions & Limitation of Liability Warranty Hearth & Home Technologies Limited WarrantyWarranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Your Fireplace Gas Fireplace SafetyOperating Instructions Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalLighting Instructions IPI After Fireplace is Lit Frequently Asked QuestionsMaintenance Tasks-Homeowner Maintenance and ServiceMaintenance Tasks-Qualified Service Technician Typical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsModel # Framing and ClearancesSelecting Appliance Location Rough Opening Model Width Height Depth Constructing the Appliance ChaseClearances Mantel Legs or Wall Projections Mantel and Wall ProjectionsMantels Vent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Use of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyOne Elbow Vent DiagramsTop Vent Horizontal Termination Min Max +H 2 max +H 2+H 3 max Two 45 Elbows replacing One 90 ElbowTwo Elbows Three Elbows Installed VerticallyNo Elbow Top Vent Vertical Termination12 ft 3.66 m min 60 ft 18.29 m max One 45 Elbow Rear Vent Horizontal TerminationTwo Elbows Rear Vent Vertical Termination Min Ft 1.83 m max 12 ft 3.66 m min 60 ft 18.29 m max 17 Flat Baffle Installing Vertical Termination BaffleReplace the glass refer to .H Start the appliance Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingInstalling Ceiling Firestop Install the Ceiling FirestopVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Convert from Top Vent to Rear Vent Appliance PreparationOuter Collar, Remove Four Screws 11 Place Outer Collar on Rear of Appliance 16 Cover Plate-Replace 20 Proper Positioning, Leveling And Securing Of An Securing and Leveling the ApplianceAssemble Pipe Sections DVP Only Installing Vent PipeAttach Pipe to the Firebox Assembly Assemble Pipe Sections DVP OnlyAdding Venting Components Assemble Vent Sections SLP OnlySecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling Components SLP onlyCaulk Install Metal Roof Flashing17 Assembling the Storm Collar Assemble and Install Storm CollarSLP-FS Install RF4-8Heat Shield Requirements for Horizontal Termination Installing Vertical Termination CapInstalling Decorative Wall Components SLP only Interior Install Horizontal Termination CapGas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntellifire Ignition System Wiring Electrical Service and Repair Junction Box InstallationDetermine Location WSK-MLT Multifunction Wall SwitchPrecautions Intellifire IPI Wiring Diagram Wiring the Wall SwitchHook up the Temperature Sensor Switch for Fan Install the Flame SolenoidInstall the Cover Plate Install the Remote Cover PlateWSK-MLT Operating Instructions Setting Flame Height/Manifold PressureWall Switch Button Operation Service Parts List Facing Material FinishingAppliance Setup Place the Rockwool Log AssemblyRemoving Fixed Glass Assembly Install Trim and/or SurroundsInstall Hood Air Shutter SettingIntellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Will not ignite. If the pilot Reference Materials Appliance Dimension DiagramDVP Vent Components Vent Components DiagramsBEK DVP-BEK2 DVP-TVHW Horizontal Termination Cap DVP-TRAPDVP-HRC-SS Effective Adapter SL-2DVPParts ServiceStocked Service PartsIPI Valve Assembly CNXT4842 Series Log/Grate Assembly Valve Assembly Model Description Optional ComponentsContact Information