Hearth and Home Technologies CNXT4842ILH Vent Clearances and Framing, Wall Penetration Framing

Page 34

8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

DVP heat shield - designed to be used on a wall 4 in. to 7-1/4 in. (102 mm to 184

mm)thick.

If wall thickness is less than 4 in. the existing heat shields must be field trimmed. If wall thickness is greater than 7-1/4 in. an extended heat shield will be required.

SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to 194 mm thick).

If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed. If wall thickness is greater than 7-5/8 in. an extended heat shield will be required.

(DVP Pipe Shown)

B. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

SLP pipe - A wall shield firestop must be placed on each side of an interior wall. A minimum 1 1/2 in. (38 mm) overlap of attached heat shields must be maintained.

DVP pipe - A wall shield firestop is required on one side only on interior walls. If your local inspector requires a wall shield firestop on both sides, then both wall shield firestops must have a heat shield attached to them.

See Section 10.N. for information for regarding the installation of a horizontal termination cap.

3 in. (76 mm) top clearance

1 in. (25 mm) clearance around vertical sections

Heat

Shield

Wall

Shield

Firestop

3 in. (76 mm) top clearance *

Heat

Shield

1 in. (25 mm) clearance bottom & sides

Non-Combustible Wall Penetration

If the hole being penetrated is surrounded by noncombus- tible materials such as concrete, a hole with diameter one in. greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield firestop is only required on one side and no heat shield is necessary.

WALL

Heat

Shield

Wall

Shield

Firestop

3 in. (76 mm) top clearance *

Heat

Shield

1 in. (25 mm) clearance bottom & sides

 

10 in.

Vent framing hole.

 

 

12 in.

 

DO NOT PACK WITH

 

INSULATION OR OTHER

MATERIAL.

The center of the framing hole is

1 in. (25mm) above the center of the horizontal vent pipe.

WALL

* When using SLP pipe, minimum clearances from the vent pipe to combustible materi-

als at inside wall firestops are:Top: 2-1/2 in. (64 mm) Bottom: 1/2 in. (13 mm) Sides: 1 in. (25 mm)

Figure 8.1 Horizontal Venting Clearances To Combustible Materi- als

A*

B*

Framing should be constructed of 2 X 4 lumber or heavier.

*Measured to center of pipe.

 

 

A

B

Model

Top Vent

Rear Vent

CNXT4236

inches

42 1/4

27 1/4

 

 

 

mm

1073

692

 

CNXT4842

inches

48 1/4

27 1/4

 

 

 

mm

1226

692

 

Figure 8.2 Wall Penetration

34

Heatilator • Caliber CNXT Series • 4047-132 Rev U • 11/08

Image 34
Contents Direct Vent Gas Appliance Installation and OperationModels What to do if you smell gasCongratulations Homeowner Reference InformationInstaller Guide Table of ContentsUser Guide Finishing Appliance SetupTroubleshooting Reference MaterialsWarranty Hearth & Home Technologies Limited Warranty CONDITIONS, Exclusions & Limitation of LiabilityWarranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Operating Instructions Gas Fireplace SafetyYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceLighting Instructions IPI Frequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-HomeownerMaintenance Tasks-Qualified Service Technician Getting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Any such action may cause a fire hazardSelecting Appliance Location Framing and ClearancesModel # Clearances Constructing the Appliance ChaseRough Opening Model Width Height Depth Mantels Mantel and Wall ProjectionsMantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesMinimum Clearances for Termination Vent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsTop Vent Horizontal Termination Vent DiagramsOne Elbow Two Elbows Two 45 Elbows replacing One 90 ElbowMin Max +H 2 max +H 2+H 3 max Installed Vertically Three ElbowsTop Vent Vertical Termination No Elbow12 ft 3.66 m min 60 ft 18.29 m max Rear Vent Horizontal Termination One 45 ElbowTwo Elbows Rear Vent Vertical Termination Min Ft 1.83 m max 12 ft 3.66 m min 60 ft 18.29 m max Installing Vertical Termination Baffle 17 Flat BaffleReplace the glass refer to .H Start the appliance Wall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Installing Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Convert from Top Vent to Rear VentOuter Collar, Remove Four Screws 11 Place Outer Collar on Rear of Appliance 16 Cover Plate-Replace Securing and Leveling the Appliance 20 Proper Positioning, Leveling And Securing Of AnAssemble Pipe Sections DVP Only Installing Vent PipeAttach Pipe to the Firebox Assembly Assemble Pipe Sections DVP OnlyAssemble Vent Sections SLP Only Adding Venting ComponentsAssemble Slip Sections Secure the Vent SectionsInstall Decorative Ceiling Components SLP only Disassemble Vent SectionsInstall Metal Roof Flashing CaulkAssemble and Install Storm Collar 17 Assembling the Storm CollarInstall RF4-8 SLP-FSInstalling Decorative Wall Components SLP only Installing Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap InteriorGas Pressure Gas InformationFuel Conversion Gas ConnectionElectrical Service and Repair Junction Box Installation Wiring RequirementsIntellifire Ignition System Wiring Electrical InformationPrecautions WSK-MLT Multifunction Wall SwitchDetermine Location Wiring the Wall Switch Intellifire IPI Wiring DiagramInstall the Flame Solenoid Hook up the Temperature Sensor Switch for FanInstall the Remote Cover Plate Install the Cover PlateWall Switch Button Operation Setting Flame Height/Manifold PressureWSK-MLT Operating Instructions Service Parts List Finishing Facing MaterialAppliance Setup Log Assembly Place the RockwoolAir Shutter Setting Install Trim and/or SurroundsInstall Hood Removing Fixed Glass AssemblySymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Will not ignite. If the pilot Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP Vent ComponentsBEK DVP-BEK2 DVP-TVHW DVP-TRAP Horizontal Termination CapDVP-HRC-SS Effective SL-2DVP AdapterService PartsService Parts StockedIPI Valve Assembly CNXT4842 Series Log/Grate Assembly Valve Assembly Optional Components Model DescriptionContact Information