8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

Note: Heat shields MUST overlap by a minimum of 1-1/2 in. (38 mm).

SLP heat shield - designed to be used on a wall 4-3/8 in. to 7-5/8 in. (111 mm to 194 mm thick).

If wall thickness is less than 4-3/8 the existing heat shields must be field trimmed. If wall thickness is greater than 7-5/8 in. a DVP- HSM-B will be required.

Heat

2-1/2 in. (64 mm)Shields top clearance at

wall shield firestops

3 in. (76 mm) top clearance

B. Wall Penetration Framing

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

SLP pipe - A wall shield firestop must be placed on each side of an interior wall. A minimum 1-1/2 in. (38 mm) overlap of attached heat shields must be maintained.

See Section 10.L. for information for regarding the in- stallation of a horizontal termination cap.

Non-Combustible Wall Penetration

If the hole being penetrated is surrounded by noncom- bustible materials such as concrete, a hole with diameter one in. greater than the pipe is acceptable.

Whenever a non-combustible wall is penetrated, the wall shield firestop is only required on one side and no heat shield is necessary.

1 in. (25 mm) clearance around vertical sections

Wall

Shield

Firestop

1 in. (25 mm) clearance bottom and sides

1/2 in. (13 mm) bottom clearance at wall shield firestops

WALL

10 in. 10 in.

Figure 6.1 Horizontal venting clearances to combustible materials

B

A*

A*

B

50-7/8 in.

49-7/8 in.

*Shows center of vent framing hole for top venting. The center of the hole is one (1) inch (25.4 mm) above the center of the horizontal vent pipe.

Figure 8.2 Wall Penetration

Heat & Glo • ST-550TM-IPI2142-900 Rev. B • 11/08

31

Image 31
Contents What to do if you smell gas ModelsHomeowner Reference Information CongratulationsUser Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Decorative Doors and Fronts Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsRemote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningVenting Porcelain Firebox Panel CleaningMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseFireplace Opening Non-Combustible MantelVent Termination Minimum Clearances Termination LocationsCovered Alcove Applications To Install the Heat Shield Install Support BracketsContinue Adding Vent Components Use of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyUse of Flex Vent Top Vent Horizontal Termination One Elbow Vent DiagramsV1 Minimum H1 Maximum V1 Minimum H1 + H2 Maximum Top Vent Horizontal Termination Two ElbowsV1 Minimum H1 + H2 Maximum V1 + V2 Min Top Vent Horizontal Termination Three ElbowsExhaust restrictor Instructions Minimum Maximum + V 2 Min Two Elbows Three ElbowsV1 Minimum Maximum V1 + V2 Min Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingPipe SLP Install the Ceiling FirestopFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Securing and Leveling the Appliance Appliance PreparationAssemble Vent Sections Installing Vent PipeSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingApply Sealant TOP & Partial Sides Install RF4-8Install Decorative Wall Components Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination 22 Venting through the wall Install Horizontal Termination CapGas Connection Gas InformationFuel Conversion Gas PressureElectrical Service and Repair Wiring RequirementsIntellifire Ignition System Wiring Optional Accessories RequirementsIntellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Option Junction Box InstallationFinishing To install the Splatter GuardSplatter Guard To Remove the Splatter Guard To Close the Lower Access Panel15 Non-Combustible Zone Mantel and Wall Projections Combustible MantelFinishing Material Facing MaterialWithout Front Shown Appliance Setup Air Shutter Setting Install Trim Kits and SurroundsSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Remove any contaminants that may have accumulated on Reference Materials Appliance Dimension DiagramVent Components Diagrams Wall Thimble-Black Snorkel Black Support Box-BlackAdapter SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP ST-550TM-IPI Service PartsStocked Service Parts ListAt Depot Intermittent Pilot Ignition Valve Assembly Contact Information