Hearth and Home Technologies ST-550TM-IPI owner manual Install Vertical Termination Cap

Page 40

I. Install Vertical Termination Cap

Attach the vertical termination cap by sliding the inner collar of the cap into the inner flue of the pipe section while placing the outer collar of the cap over the outer flue of the pipe section.

Secure the cap by driving three self-tapping screws (supplied) through the pilot holes in the outer collar of the cap into the outer flue of the pipe (see Figure 10.20).

TERMINATION CAP

(1 of 3)

STORM

COLLAR

SCREWS

CAULK

Figure 10.20

J. Install Decorative Wall Components

A decorative wall thimble can be installed on wall through which the vent passes. The decorative wall thimble is used to cover the wall shield firestop.

Slide the decorative wall thimble over the last section of horizontal pipe before connecting the termination cap to the pipe.

Once the pipe section and the termination cap have been connected, slide the wall thimble up to the interior wall surface and attach with screws provided. See Figure 10.21.

K.Heat Shield Requirements for Horizontal Termination

WARNING! Risk of Fire! To prevent overheating and fire, heat shields must extend through the entire wall thick- ness.

DO NOT remove the heat shields attached to the wall shield firestop and the horizontal termination cap (shown in Figure 10.21).

Heat shields must overlap 1-1/2 in. (38 mm) mini- mum.

There are two sections of the heat shield. One section is factory-attached to the wall shield firestop. The other section is factory-attached to the cap. See Figure 10.25.

If the wall thickness does not allow the required 1-1/2 in. (38 mm) heat shield overlap when installed, an extended heat shield must be used.

If the wall thickness is less than 4-3/8 in. (111 mm), the heat shields on the cap and wall shield firestop must to be trimmed. A minimum 1-1/2 in. (38 mm) overlap MUST be maintained.

Use an extended heat shield if the finished wall thickness is greater than 7-1/4 in. (184 mm).

The extended heat shield may need to be cut to length maintaining sufficient length for a 1-1/2 in. (38 mm) overlap between heat shields.

Attach the extended heat shield to either of the existing heat shields using the screws supplied with the extended heat shield. Refer to vent components diagrams in the back of this manual.

Rest the small leg on the extended heat shield on top of the pipe section to properly space it from the pipe section.

Important Notice: Heat shields may not be field constructed.

Figure 10.21 Wall Thimble

40

Heat & Glo • ST-550TM-IPI2142-900 Rev. B • 11/08

Image 40
Contents Models What to do if you smell gasCongratulations Homeowner Reference InformationTable of Contents User GuideAppliance Setup TroubleshootingFinishing Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsOperating Instructions User Guide Gas Fireplace SafetyYour Fireplace Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesClear Space Decorative Doors and FrontsLighting Instructions IPI Final inspection byFrequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote ControlPorcelain Firebox Panel Cleaning Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingBurner Ignition and Operation IPI Pilot Flame PatternsGetting Started Typical Appliance SystemTools and Supplies Needed Design and Installation ConsiderationsInspect Appliance and Components Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesNon-Combustible Mantel Fireplace OpeningTermination Locations Vent Termination Minimum ClearancesCovered Alcove Applications To Install the Heat Shield Install Support BracketsContinue Adding Vent Components Vent Information and Diagrams Approved PipeVent Table Key Use of ElbowsUse of Flex Vent Top Vent Horizontal Termination One Elbow Vent DiagramsV1 Minimum H1 Maximum Top Vent Horizontal Termination Two Elbows V1 Minimum H1 + H2 MaximumTop Vent Horizontal Termination Three Elbows V1 Minimum H1 + H2 Maximum V1 + V2 MinExhaust restrictor Instructions Minimum Maximum + V 2 Min Two Elbows Three ElbowsV1 Minimum Maximum V1 + V2 Min Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Pipe SLPFlat Ceiling Installation Install Attic Insulation ShieldVaulted Ceiling Installation Appliance Preparation Securing and Leveling the ApplianceInstalling Vent Pipe Assemble Vent SectionsAssemble Slip Sections Secure the Vent SectionsInstall Decorative Ceiling Components Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 Apply Sealant TOP & Partial SidesInstall Decorative Wall Components Install Vertical Termination CapHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap 22 Venting through the wallGas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements Intellifire Ignition System WiringOptional Accessories Requirements Electrical Service and RepairIntellifire Ignition Wiring Diagram with Remote Receiver Junction Box Installation Wall Switch Installation for Fan OptionFinishing To install the Splatter GuardSplatter Guard To Close the Lower Access Panel To Remove the Splatter GuardMantel and Wall Projections Combustible Mantel 15 Non-Combustible ZoneFacing Material Finishing MaterialWithout Front Shown Appliance Setup Install Trim Kits and Surrounds Air Shutter SettingSymptom Possible Cause Corrective Action TroubleshootingIntellifire Ignition System Remove any contaminants that may have accumulated on Appliance Dimension Diagram Reference MaterialsVent Components Diagrams Wall Thimble-Black Snorkel Black Support Box-BlackAdapter SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP Service Parts ST-550TM-IPIStocked Service Parts ListAt Depot Intermittent Pilot Ignition Valve Assembly Contact Information