D. Install Attic Insulation Shield

WARNING! Fire Risk. DO NOT allow loose materials or insulation to touch vent. Hearth & Home Technologies Inc. requires the use of an attic shield.

The National Fuel Gas Code ANSI Z223.1 and NFPA 54 requires an attic shield constructed of 26 gauge minimum metal that extends at least 2 in. (51 mm) above insulation.

Attic shields must meet specified clearance and be se- cured in place.

Flat Ceiling Installation

• Remove one shield from box.

NOTICE: Cut previously installed batt insulation to make room for the attic insulation shield.

Wrap shield around pipe if pipe is already installed in area to be insulated.

Match the three holes in each side and fasten with three screws to form a tube.

Bend three tabs on the bottom of the shield outward to allow attachment to the ceiling firestop.

Bend the remaining bottom tabs inward 90° to maintain the air space between the pipe and the shield. Set the shield on the ceiling firestop and attach to the firestop.

Bend all tabs inward 90° around the top of the shield. These tabs must be used to prevent blown insulation from getting between the shield and vent pipe, and to maintain air space clearance.

Vaulted Ceiling Installation

• Remove one shield from box.

NOTICE: Cut previously installed batt insulation to make room for the attic insulation shield.

Cut the attic insulation shield (if application is for vaulted ceiling) to fit your ceiling pitch. Snip cut edge to recreate 1 in. bend tabs all the way around the bottom.

Wrap shield around pipe if pipe is already installed in area to be insulated.

Match the three holes in each side and fasten with three screws to form a tube.

Bend three tabs on the bottom of the shield outward to allow attachment to the ceiling firestop.

Bend the remaining bottom tabs inward 90° to maintain the air space between the pipe and the shield. Set the shield on the ceiling firestop and attach to the firestop.

Bend all tabs inward 90° around the top of the shield. These tabs must be used to prevent blown insulation from getting between the shield and vent pipe, and to maintain air space clearance.

BEND ALL TABS INWARD 90° TO MAINTAIN CLEARANCE AND PREVENT INSULATION FROM FALLING INSIDE

INSERT 3

SCREWS

Figure 8.5 Attic Insulation Shield

BEND 3 TABS

OUTWARD TO FASTEN TO CEILING FIRESTOP-BEND REMAINING TABS INWARD 90 DEGREES TO MAINTAIN CLEARANCE

Heat & Glo • ST-550TM-IPI2142-900 Rev. B • 11/08

33

Image 33
Contents What to do if you smell gas ModelsHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyClear Space Decorative Doors and FrontsFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsMaintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Porcelain Firebox Panel CleaningGasket Seal and Glass Assembly Inspection VentingIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseFireplace Opening Non-Combustible MantelVent Termination Minimum Clearances Termination LocationsCovered Alcove Applications Install Support Brackets To Install the Heat ShieldContinue Adding Vent Components Approved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsUse of Flex Vent Vent Diagrams Top Vent Horizontal Termination One ElbowV1 Minimum H1 Maximum V1 Minimum H1 + H2 Maximum Top Vent Horizontal Termination Two ElbowsV1 Minimum H1 + H2 Maximum V1 + V2 Min Top Vent Horizontal Termination Three ElbowsExhaust restrictor Instructions Two Elbows Three Elbows Minimum Maximum + V 2 MinV1 Minimum Maximum V1 + V2 Min Pipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe SLP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Securing and Leveling the Appliance Appliance PreparationAssemble Vent Sections Installing Vent PipeSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingApply Sealant TOP & Partial Sides Install RF4-8Install Vertical Termination Cap Install Decorative Wall ComponentsHeat Shield Requirements for Horizontal Termination 22 Venting through the wall Install Horizontal Termination CapFuel Conversion Gas InformationGas Pressure Gas ConnectionIntellifire Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical Service and RepairIntellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Option Junction Box InstallationTo install the Splatter Guard FinishingSplatter Guard To Remove the Splatter Guard To Close the Lower Access Panel15 Non-Combustible Zone Mantel and Wall Projections Combustible MantelFinishing Material Facing MaterialWithout Front Shown Appliance Setup Air Shutter Setting Install Trim Kits and SurroundsTroubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Remove any contaminants that may have accumulated on Reference Materials Appliance Dimension DiagramVent Components Diagrams Snorkel Black Support Box-Black Wall Thimble-BlackAdapter SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP ST-550TM-IPI Service PartsService Parts List StockedAt Depot Intermittent Pilot Ignition Valve Assembly Contact Information