Hearth and Home Technologies ST-550TM-IPI owner manual Install Horizontal Termination Cap

Page 41

L. Install Horizontal Termination Cap

WARNING! Risk of Fire! The telescoping flue section of the termination cap MUST be used when connecting vent.

1-1/2 (38 mm) minimum overlap of flue telescoping section is required.

Failure to maintain overlap may cause overheating and fire.

Vent termination must not be recessed in the wall. Siding may be brought to the edge of the cap base.

Flash and seal as appropriate for siding material at outside edges of cap.

When installing a horizontal termination cap, follow the cap location guidelines as prescribed by current ANSI Z223.1 and CAN/CGA-B149installation codes and refer to Section 6 of this manual.

CAUTION! Risk of Burns! Local codes may require in- stallation of a cap shield to prevent anything or anyone from touching the hot cap.

NOTICE: For certain exposures which require superior resistance to wind-driven rain penetration, a flashing kit and HRC caps are available. When penetrating a brick wall, a brick extension kit is available for framing the brick.

Note: When using termination caps with factory-supplied heat shield attached, no additional wall shield firestop is required on the exterior side of a combustible wall.

HEAT SHIELD OR

HEAT SHIELD

EXTENDED

1-1/2 IN. (38 MM) MIN.

HEAT SHIELD

OVERLAP

WALL SHIELD

 

FIRESTOP

 

SLIP SECTION

 

CAN BE EXTENDED

 

INNER VENT

SHEATHING

OUTER VENT

 

INTERIOR

EXTERIOR

Figure 10.22 Venting through the wall

 

Heat & Glo • ST-550TM-IPI2142-900 Rev. B • 11/08

41

Image 41
Contents What to do if you smell gas ModelsHomeowner Reference Information CongratulationsUser Guide Table of ContentsTroubleshooting Appliance SetupFinishing Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Remote Controls, Wall Controls and Wall Switches Fixed Glass AssemblyClear Space Decorative Doors and FrontsFinal inspection by Lighting Instructions IPIAfter Fireplace is Lit Frequently Asked QuestionsMaintenance Tasks-Homeowner Maintenance and ServiceGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Porcelain Firebox Panel CleaningGasket Seal and Glass Assembly Inspection VentingIPI Pilot Flame Patterns Burner Ignition and OperationTypical Appliance System Getting StartedInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Selecting Appliance Location Framing and ClearancesClearances Constructing the Appliance ChaseFireplace Opening Non-Combustible MantelVent Termination Minimum Clearances Termination LocationsCovered Alcove Applications Continue Adding Vent Components Install Support BracketsTo Install the Heat Shield Approved Pipe Vent Information and DiagramsVent Table Key Use of ElbowsUse of Flex Vent V1 Minimum H1 Maximum Vent DiagramsTop Vent Horizontal Termination One Elbow V1 Minimum H1 + H2 Maximum Top Vent Horizontal Termination Two ElbowsV1 Minimum H1 + H2 Maximum V1 + V2 Min Top Vent Horizontal Termination Three ElbowsExhaust restrictor Instructions V1 Minimum Maximum V1 + V2 Min Two Elbows Three ElbowsMinimum Maximum + V 2 Min Pipe Clearances to Combustibles Vent Clearances and FramingWall Penetration Framing Combustible Wall PenetrationPipe SLP Install the Ceiling FirestopVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Securing and Leveling the Appliance Appliance PreparationAssemble Vent Sections Installing Vent PipeSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Decorative Ceiling ComponentsAssemble and Install Storm Collar Install Metal Roof FlashingApply Sealant TOP & Partial Sides Install RF4-8Heat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components 22 Venting through the wall Install Horizontal Termination CapFuel Conversion Gas InformationGas Pressure Gas ConnectionIntellifire Ignition System Wiring Wiring RequirementsOptional Accessories Requirements Electrical Service and RepairIntellifire Ignition Wiring Diagram with Remote Receiver Wall Switch Installation for Fan Option Junction Box InstallationSplatter Guard To install the Splatter GuardFinishing To Remove the Splatter Guard To Close the Lower Access Panel15 Non-Combustible Zone Mantel and Wall Projections Combustible MantelFinishing Material Facing MaterialWithout Front Shown Appliance Setup Air Shutter Setting Install Trim Kits and SurroundsIntellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Remove any contaminants that may have accumulated on Reference Materials Appliance Dimension DiagramVent Components Diagrams Adapter Snorkel Black Support Box-BlackWall Thimble-Black SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP ST-550TM-IPI Service PartsAt Depot Service Parts ListStocked Intermittent Pilot Ignition Valve Assembly Contact Information