G. Install Metal Roof Flashing

Note: Skip this section if using the RF4-8.

See minimum vent heights for various pitched roofs (Figure 10.14) to determine the length of pipe to extend through the roof.

Slide the roof flashing over the pipe sections extending through the roof as shown in Figure 10.15.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

20 INCHES MIN.

VERTICAL

MIN.

 

 

WALL

 

LOWEST

 

 

 

DISCHARGE

 

 

OPENING

 

GAS DIRECT VENT

 

 

TERMINATION CAP

 

 

 

 

X

 

 

12

 

 

ROOF PITCH

 

 

IS X/ 12

 

H (MIN.) - MINIMUM HEIGHT FROM ROOF

 

TO LOWEST DISCHARGE OPENING

Roof Pitch

 

H (Min.) Ft.

Flat to 6/12........................................1.0*

Over 6/12 to 7/12............................1.25*

Over 7/12 to 8/12..............................1.5*

Over 8/12 to 9/12..............................2.0*

Over 9/12 to 10/12............................. 2.5

Over 10/12 to 11/12 ......................... 3.25

Over 11/12 to 12/12 ........................... 4.0

Over 12/12 to 14/12........................... 5.0

Over 14/12 to 16/12........................... 6.0

Over 16/12 to 18/12........................... 7.0

Over 18/12 to 20/12........................... 7.5

Over 20/12 to 21/12........................... 8.0

* 3 foot minimum in snow regions

Figure 10.14 Minimum Height From Roof To Lowest Discharge

Opening

 

 

NOTICE: Failure to properly caulk the roof flashing could cause water entry.

Caulk the gap between the roof flashing and the outside diameter of the pipe.

Caulk the perimeter of the flashing where it contacts the roof surface. See Figure 10.15.

CAULK

Figure 10.15

H. Assemble and Install Storm Collar

CAUTION! Risk of Cuts, Abrasions or Flying Debris. Wear protective gloves and safety glasses during instal- lation. Sheet metal edges are sharp.

Connect both halves of the storm collar with two screws (see Figure 10.16).

Wrap the storm collar around the exposed pipe section closest to the roof and align brackets. Insert a bolt (provided) through the brackets and tighten the nut to complete the storm collar assembly. Make sure the collar is tight against the pipe section.

Slide the assembled storm collar down the pipe section until it rests on the roof flashing (see Figure 10.17).

Caulk around the top of the storm collar (see Figure 10.23).

Figure 10.16 Assembling the Storm Collar

Figure 10.17 Assembling the Storm Collar Around the Pipe

42

Heat & Glo • 6000GLX-IPI-S/-R, 6000GLX-IPILP-S/-R2101-900 Rev. S • 12/08

Image 42
Contents What to do if you smell gas Hot glass will cause burnsCongratulations Homeowner Reference InformationTable of Contents User GuideFinishing Appliance SetupTroubleshooting Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Fan Kit optional Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Clear SpaceLighting Instructions IPI Turn off all electric power to the applianceOn position. The ON/OFF switch may Final inspection byFrequently Asked Questions After Fireplace is LitMaintenance and Service Venting Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection LogsIPI Pilot Flame Patterns Getting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Vent Table Key Vent Information and DiagramsApproved Pipe Use of ElbowsVent Diagrams Top Vent Horizontal Termination V1 Minimum H1 MaximumV1 Minimum H1 + H2 Maximum Top Vent Horizontal Termination Three Elbows Min MaxBreak Here Top Vent Vertical Termination Two ElbowsMaximum + V 2 Min Top Vent Vertical Termination Three Elbows H1 + H2 V1 + V2 Minimum H1 + H2 MaximumPage Rear Vent Horizontal Termination Two Elbows H1 Maximum V1 Minimum H1 + H2 MaximumH1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max Rear Vent Vertical Termination One Elbow H1 + H2 Maximum V1 MinimumRear Vent Vertical Termination Three Elbows V1 Minimum H1 + H2 + H3Wall Penetration Framing Vent Clearances and FramingPipe Clearances to Combustibles Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPFlat Ceiling Installation Install Attic Insulation ShieldInstalling the Optional Heat-Zone-Gas Kit Vaulted Ceiling InstallationAppliance Preparation Choosing the Top or Rear VentProceed to . C Installing the Non-combustible Board Rear Vent Securing and Leveling the ApplianceAssemble Vent Sections DVP Pipe Only Installing Vent Pipe DVP and SLP PipeAttach Vent to the Firebox Assembly Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 SLP-FSInstall Vertical Termination Cap Install Decorative Wall Components SLP onlyHeat Shield Requirements for Horizontal Termination Install Horizontal Termination Cap DVP and SLP Pipe Ansi Z223.1 and CAN/CGA-B149 installation codesRefer to of this manual Gas Pressure Gas InformationFuel Conversion Gas ConnectionOptional Accessories Requirements Wiring RequirementsIntellifire Ignition System Wiring Electrical InformationElectrical Service and Repair Intellifire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialDoors Finish Door FIT Material See Maximum ThicknessAppliance Setup Ember Placement Placement of EmbersLog Assembly LOGS-6000GLX LOGS-6000GLXLP Install the Log Assembly11 Front View 17 Front View Air Shutter Setting Install the MeshInstall Trim and/or Surround Air Shutter SettingsTroubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsLocation Inches Millimeters Vent Components Diagrams DVP vent componentsHorizontal Termination Cap DVP vent components302 mm 787 mm 13-1/4 367 mm 24-5/8 625 mm 27-1/2 127 mmRoof Flashing Multi-pak 13-3/4 11-7/8 349 mm 13-3/4 13-7/8 352 mm 349 mmDVP-TVHW DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP Elbow 165 mm165 mm 222 mm 235 mm 152 mm 168 mm 251 mmCathedral Ceiling Vertical Snorkel Support Box-BlackBlack Termination CapLog Set Assembly Service PartsService Parts List StockedAt Depot 6000GLX-IPI-R,-S 6000GLX-IPI-R,S Contact Information