Hearth and Home Technologies 6000GLX-IPILP-S, 6000GLX-IPI-R Install Vertical Termination Cap

Page 44

J. Install Vertical Termination Cap

Attach the vertical termination cap by sliding the inner collar of the cap into the inner flue of the pipe section while placing the outer collar of the cap over the outer flue of the pipe section.

Secure the cap by driving three self-tapping screws (supplied) through the pilot holes in the outer collar of the cap into the outer flue of the pipe (see Figure 10.23).

TERMINATION CAP

(1 of 3)

STORM

COLLAR

SCREWS

CAULK

Figure 10.23

K.Install Decorative Wall Components (SLP only)

A decorative wall thimble can be installed on wall through which the vent passes. The decorative wall thimble is used to cover the wall shield firestop.

Slide the decorative wall thimble over the last section of horizontal pipe before connecting the termination cap to the pipe.

Once the pipe section and the termination cap have been connected, slide the wall thimble up to the interior wall surface and attach with screws provided. See Figure 10.24.

L.Heat Shield Requirements for Horizontal Termination

WARNING! Risk of Fire! To prevent overheating and fire, heat shields must extend through the entire wall thick- ness.

DO NOT remove the heat shields attached to the wall shield firestop and the horizontal termination cap (shown in Figure 10.25).

Heat shields must overlap 1-1/2 in. (38 mm) mini- mum.

There are two sections of the heat shield. One section is factory-attached to the wall shield firestop. The other section is factory-attached to the cap. See Figure 10.25.

If the wall thickness does not allow the required 1-1/2 in. (38 mm) heat shield overlap when installed, an extended heat shield must be used.

If the wall thickness is less than 4 in./102 mm (DVP) or 4-3/8 in./ 111 mm (SLP), the heat shields on the cap and wall shield firestop must be trimmed. A minimum 1-1/2 in. (38 mm) overlap MUST be maintained.

Use an extended heat shield if the finished wall thickness is greater than 7-1/4 in. (184 mm).

The extended heat shield may need to be cut to length maintaining sufficient length for a 1-1/2 in. (38 mm) overlap between heat shields.

Attach the extended heat shield to either of the existing heat shields using the screws supplied with the extended heat shield. Refer to vent components diagrams in the back of this manual.

Rest the small leg on the extended heat shield on top of the pipe section to properly space it from the pipe section.

Important Notice: Heat shields may not be field constructed.

Figure 10.24 Wall Thimble

44

Heat & Glo • 6000GLX-IPI-S/-R, 6000GLX-IPILP-S/-R2101-900 Rev. S • 12/08

Image 44
Contents What to do if you smell gas Hot glass will cause burnsCongratulations Homeowner Reference InformationTable of Contents User GuideAppliance Setup TroubleshootingFinishing Reference MaterialsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsYour Fireplace Gas Fireplace SafetyOperating Instructions User Guide Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceTurn off all electric power to the appliance On position. The ON/OFF switch mayLighting Instructions IPI Final inspection byFrequently Asked Questions After Fireplace is LitMaintenance and Service Maintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionVenting LogsIPI Pilot Flame Patterns Getting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesCombustible Mantel Legs or Wall Projections Mantel and Wall ProjectionsCombustible Mantels Termination Locations Vent Termination Minimum ClearancesCovered Alcove Applications Vent Information and Diagrams Approved PipeVent Table Key Use of ElbowsV1 Minimum H1 + H2 Maximum Vent Diagrams Top Vent Horizontal TerminationV1 Minimum H1 Maximum Top Vent Horizontal Termination Three Elbows Min MaxBreak Here Maximum + V 2 Min Top Vent Vertical TerminationTwo Elbows Top Vent Vertical Termination Three Elbows H1 + H2 V1 + V2 Minimum H1 + H2 MaximumPage H1 Maximum V1 Minimum H2+ H3 H1+ H2+ H3 Max Rear Vent Horizontal Termination Two ElbowsH1 Maximum V1 Minimum H1 + H2 Maximum Rear Vent Vertical Termination One Elbow H1 + H2 Maximum V1 MinimumRear Vent Vertical Termination Three Elbows V1 Minimum H1 + H2 + H3Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Pipe DVP SLPInstall Attic Insulation Shield Installing the Optional Heat-Zone-Gas KitFlat Ceiling Installation Vaulted Ceiling InstallationProceed to . C Appliance PreparationChoosing the Top or Rear Vent Installing the Non-combustible Board Rear Vent Securing and Leveling the ApplianceInstalling Vent Pipe DVP and SLP Pipe Attach Vent to the Firebox AssemblyAssemble Vent Sections DVP Pipe Only Assemble Pipe SectionsAssemble Vent Sections SLP Pipe Only Assemble Slip SectionsSecure the Vent Sections Disassemble Vent SectionsInstall Decorative Ceiling Components SLP only Install Metal Roof Flashing Assemble and Install Storm CollarInstall RF4-8 SLP-FSHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components SLP only Refer to of this manual Install Horizontal Termination Cap DVP and SLP PipeAnsi Z223.1 and CAN/CGA-B149 installation codes Gas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements Intellifire Ignition System WiringOptional Accessories Requirements Electrical InformationElectrical Service and Repair Intellifire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialDoors Finish Door FIT Material See Maximum ThicknessAppliance Setup Ember Placement Placement of EmbersLog Assembly LOGS-6000GLX LOGS-6000GLXLP Install the Log Assembly11 Front View 17 Front View Install the Mesh Install Trim and/or SurroundAir Shutter Setting Air Shutter SettingsIntellifire Ignition System TroubleshootingSymptom Possible Cause Corrective Action Ues to spark, and main Location Inches Millimeters Appliance Dimension DiagramReference Materials Vent Components Diagrams DVP vent componentsHorizontal Termination Cap DVP vent components787 mm 13-1/4 367 mm 24-5/8 625 mm 27-1/2 127 mm Roof Flashing Multi-pak 13-3/4 11-7/8 349 mm302 mm 13-3/4 13-7/8 352 mm 349 mmDVP-TVHW DVP-HRC-SS DVP-HRC-ZC-SS Horizontal Termination CAP 165 mm 165 mm 222 mm 235 mm 152 mm 168 mmElbow 251 mmSnorkel Support Box-Black BlackCathedral Ceiling Vertical Termination CapLog Set Assembly Service PartsAt Depot Service Parts ListStocked 6000GLX-IPI-R,-S 6000GLX-IPI-R,S Contact Information