State Industries SUF-130- 300/400/500 instruction manual Water Piping Diagrams

Page 71

Water Piping Diagrams

Before installation of water piping review the following:

1.See Mixing Valves on page 71.

2.See Dishwashing Machines on page 71.

3.See Temperature-Pressure Relief Valve on page 71.

TWO WATER HEATERS, SINGLE TEMPERATURE WITH BUILDING RECIRCULATION

4.See Closed Systems and Thermal Expansion on page 71

5.See Water Line Connections on page 71.

6.If a pump is being installed between a water heater and storage tank or on a building recirculation loop wire according to Figure 64 on page 71.

7.If a pump is being installed in a recirculation loop between the water heater and a commercial dishwasher wire according to Figure 64 or Figure 65 on page 71.

LEGEND

WARNING: THIS DRAWING SHOWS SUGGESTED PIPING CONFIGURATION AND OTHER DEVICES; CHECK WITH LOCAL CODES AND ORDINANCES FOR ADDITIONAL REQUIREMENTS.

HOT WATER

OUTLET

TEMPERATURE & PRESSURE RELIEF VALVE

PRESSURE RELIEF VALVE

CIRCULATING PUMP

TANK OR LINE TEMPERATURE CONTROL

DRAIN

FULL PORT BALL VALVE

CHECK VALVE

TEMPERATURE GAGE

WATER FLOW SWITCH

71

PIPE T&P TO

OPEN DRAIN

FINISHED

FLOOR

PIPE T&P TO OPEN DRAIN

LINE TEMPERATURE

CONTROL

HOT WATER

RETURN

COLD WATER

SUPPLY

EXPANSION

TANK

Image 71
Contents Commercial gas water heaters Table Of Contents Optional Safe Installation, Use and ServiceANSI/NSF-5 Overheated water can cause water tank explosion General Safety InformationPrecautions Hydrogen Gas FlammableFire and Explosion Hazard Installing, using or servicing Water heaterQualifications Preparing For The InstallationIntroduction Abbreviations UsedBasic Operation Features And ComponentsTop View Components Water Heater’s 120 VAC on/off switchTop View Side Views Gas Line Connection Size Installation ConsiderationsRough In Dimensions Recovery CapacitiesIntake Air and Vent Pipe Clearances Service ClearanceLocating The Water Heater Clearance To Combustible MaterialsCirculation Pumps Extended Vent TerminationsOptional Concentric Terminations Hard WaterSupply Gas Line Installation RequirementsPower Supply Gas Pressure RequirementsThermal Expansion Mixing ValvesDishwashing Machines Closed Water SystemsValve Discharge Pipe Requirements Temperature-Pressure Relief ValveCondensate Drain Water Trap Condensate DrainCombustible Material Storage Contaminated AirConfined Space Air RequirementsUnconfined Space Outdoor Air Through Two Horizontal Ducts Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through One OpeningPage Inspection Commonwealth of MassachusettsGeneral Venting Instructions Venting InstallationGeneral Venting Information Venting Requirements Direct Vent Installation Venting Installation SequencePower Vent Installation 3 Reducer Vertical Termination InstallationVertical Termination Direct Vent Sidewall Termination Installation Inch Concentric Termination Flat Roof Clearance Concentric Termination InstallationInch Concentric Termination KIT Inch Concentric Termination InstallationInch Concentric Termination Sidewall Installation Eight Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Four Concentric TerminationsEight Concentric Terminations Multiple Concentric Termination ArrangementsTwo Concentric Terminations Direct Vent Horizontal Power Vent HorizontalVenting Arrangements Direct Vent Horizontal Concentric Direct Vent Vertical Vent Horizontal IntakeDirect Vent Horizontal Vent Vertical Intake Power Vent Termination Clearances Sidewall Power VentDirect Vent Termination Clearances Sidewall Direct VentInstallation Instructions Water Heater InstallationCondensate Drain Installation Installation NotesSupply Gas Line Sizing Metric Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing U. S. UnitsGas Line Connection Supply Gas Regulator InstallationGas Line Leak Testing Connecting An External Supervisory Control Electrical WiringPower Supply Connections Enable/Disable CircuitThermometers not Supplied Water Piping DiagramsWater Line Connections Valve Discharge PipeThermostat Control Temperature RegulationHigh Temperature Limit Control ECO High Temperature ApplicationsUser Input Buttons Control System OperationOverview Control System NavigationIcon Description Status IconsMenu Description Operating StatesState Description Control System MenusDescription/Action Display User Settings & Control System MenusUpdate Cancel Back HelpChange Back Help Heater Information Description/Action Display Display Settings Description/ActionYES Back AdvancedView Back Help ECOName UpdateService Contact Information Select Back HelpInitial Start Up Start UpPrior to Start up Manifold Gas Pressure Adjustment Supply Gas Pressure AdjustmentMultiple Appliance Installations To Turn Off Gas High Altitude InstallationsChecking The Firing Rate 1050 = 300,000 Btu/hr 87.9 kWHoneywell Lighting The Water HeaterLighting & Operation Label Sequence Of Operation TroubleshootingInstallation Checklist Water is heated to VAC Gas Valve Sequence Of Operation Flow ChartClosed by control system Fault Msg is displayed Pre-Purge cycleMomentary Ignition Operational ProblemsInstallation Errors Rough Starting, Rough OperationFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesNo Anode Voltage Blower Prover FailureDraining And Flushing MaintenanceMaintenance Schedule GeneralLime Scale Removal Filling The Water HeaterSediment Removal Vent System Powered Anode RodsDrain Valve and Access Panels Temperature-Pressure Relief Valve TestCCB Central Control Board Layout DiagramsUser Interface Modul SUF 130 300 Wiring DiagramUser SUF 130 400, 500 Wiring DiagramCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty