Electrical Wiring

All electrical work must be installed in accordance with the National Electrical Code, ANSI/NFPA 70 or the Canadian Electrical Code, CSA C22.1 and local requirements.

When installed, the water heater must be electrically grounded in accordance with local codes or, in the absence of local codes, with the National Electrical Code, ANSI/NFPA 70 or the Canadian Electrical Code, CSA C22.1.

If any of the original wire as supplied with the water heater must be replaced, it must be replaced with 105°C rated wiring or its equivalent, except in the burner housing. In this case use 200°C rated wire must be used.

Power Supply Connections

Read the requirements for the Power Supply on page 39 before connecting power.

Correct Polarity:

The water heater’s control system is polarity sensitive and will lock out and disable heating operation if the polarity of the power supply is reversed. The control system will display the “AC Reversed” Fault message on the LCD. The 120 VAC hot wire from the power supply must connect to the black wire in the junction box and the 120 VAC neutral wire must connect to the white wire in the junction box for correct polarity.

Power supply connections must be made as follows:

1.Ensure the power supply is turned off at the breaker or disconnect switch.

2.Remove the junction box cover. See Figure 3 on page 39 for junction box location.

3.Connect the 120 VAC hot wire from the power supply to the black wire in the junction box on top of the water heater with a properly sized wire nut. Wrap electrical tape around the wire nut and wire end. See wiring diagrams Figure 62 on page 39 and Figure 63 on page 39.

4.Connect the 120 VAC neutral wire from the power supply to the white wire in the junction box. Wrap electrical tape around the wire nut and wire end. See wiring diagrams Figure 62 on page 39 and Figure 63 on page 39.

5.Connect the ground wire from the power supply to the grounding lug inside the junction box. See wiring diagrams Figure 62 on page 39 and Figure 63 on page 39.

6.Replace the junction box cover when connections are complete.

Note: Do not apply power to the water heater before installation is complete and the water heater is filled with water.

Enable/Disable Circuit

The water heaters covered in this manual are equipped with an enable/disable circuit for use with field supplied external supervisory controls such as time clocks or building Building Management Systems. The enable/disable circuit may be used to disable heating operation during periods when the building is unoccupied or there is no demand for hot water.

To use the enable/disable circuit it must first be activated by configuring the S1 dipswitch on the water heater’s CCB (central control board), see Figure 61 on page 39. Field supplied wiring is then installed between the water heater’s CCB and a set of “dry contacts” (no voltage or load) on the field supplied external control.

Note: The water heater’s enable/disable circuit is a switching

circuit only: Do not apply external voltage or connect any load

(IE: relay coil) to this circuit. This will damage the CCB circuit board and is not covered under the limited warranty.

Connecting An External Supervisory Control

The enable/disable circuit is accessed from the CCB’s J6 plug inside the CCB enclosure, see Figure 3 on page 39 to locate the CCB enclosure. From the factory there is a short (black) jumper wire installed between pins 8 and 11 of the J6 plug, see Figure 61 on page 39 to locate the J6 plug.

Install field wiring to the enable/disable circuit:

1.Turn off power at the water heater’s on/off switch and the breaker that supplies power to the appliance.

2.Locate the CCB enclosure.

3.Remove the screws from the CCB enclosure cover and carefully open the CCB enclosure. Note how strain relief for the wiring is provided between the cover and enclosure along one edge.

4.Activate the enable/disable circuit; locate the S1 dipswitch on the CCB, see Figure 61 on page 39.

Toggle S1 dipswitch #2 to the open position.

Toggle S1 dipswitch #3 to the open position.

5.Locate the black jumper wire between pin 8 and 11 on the CCB J6 plug, see Figure 61 on page 39 and Figure 62 on page 39.

6.Cut the black jumper wire in the middle.

7.Strip approximately 1/2 inch of insulation from the two ends of the black jumper wire.

8.Using wire nuts connect two field supplied control wires to the two ends of the black jumper wire. Wrap electrical tape around the wire nut connections.

9.Thread the control wires out of the CCB enclosure with the other wiring and carefully replace the CCB enclosure cover. Ensure all wiring is routed through the indented area provided for strain relief. Ensure no wiring is being pinched.

10.Reinstall the CCB enclosure cover screws and tighten.

11.Route the control wires inside the junction box on the top of the water heater, see Figure 3 on page 39 to locate the junction box. Use an available knock-out to route the wires inside the junction box.

12.Install field supplied control wiring and conduit as required by national and local codes between the water heater’s junction box and the external supervisory control. Connect the wiring from the external control to the control wires inside the junction box using wire nuts and electrical tape.

13.Connect the control wiring to a set of dry contacts on the external control. Follow the control manufacturers instructions for making connections.

14.Restore power to the water heater.

Note: Whenever the external control opens the set of dry contacts used, heating operation will be disabled. Whenever the external control closes the set of dry contacts used, heating operation will be enabled. A diagonal line and circle appears over the thermometer icon on the control system’s display when heating operation is disabled. See the Status Icons descriptions in Table 11 on page 39.

Note: Ensure the water heater is protected from freezing temperatures when heating operation is disabled. Damage to the water heater caused by freezing temperatures is not covered under the limited warranty.

39

Image 39
Contents Commercial gas water heaters Table Of Contents Safe Installation, Use and Service ANSI/NSF-5Optional Overheated water can cause water tank explosion General Safety InformationPrecautions Hydrogen Gas FlammableFire and Explosion Hazard Installing, using or servicing Water heaterQualifications Preparing For The InstallationIntroduction Abbreviations UsedBasic Operation Features And ComponentsWater Heater’s 120 VAC on/off switch Top ViewTop View Components Side Views Gas Line Connection Size Installation ConsiderationsRough In Dimensions Recovery CapacitiesIntake Air and Vent Pipe Clearances Service ClearanceLocating The Water Heater Clearance To Combustible MaterialsCirculation Pumps Extended Vent TerminationsOptional Concentric Terminations Hard WaterSupply Gas Line Installation RequirementsPower Supply Gas Pressure RequirementsThermal Expansion Mixing ValvesDishwashing Machines Closed Water SystemsValve Discharge Pipe Requirements Temperature-Pressure Relief ValveCondensate Drain Water Trap Condensate DrainCombustible Material Storage Contaminated AirAir Requirements Unconfined SpaceConfined Space Outdoor Air Through Two Horizontal Ducts Fresh Air Openings For Confined SpacesOutdoor Air Through Two Openings Outdoor Air Through One OpeningPage Inspection Commonwealth of MassachusettsVenting Installation General Venting InformationGeneral Venting Instructions Venting Requirements Venting Installation Sequence Power Vent InstallationDirect Vent Installation 3 Reducer Vertical Termination InstallationVertical Termination Direct Vent Sidewall Termination Installation Inch Concentric Termination Flat Roof Clearance Concentric Termination InstallationInch Concentric Termination KIT Inch Concentric Termination InstallationInch Concentric Termination Sidewall Installation Eight Concentric Terminations TWO Concentric TerminationsThree Concentric Terminations Four Concentric TerminationsMultiple Concentric Termination Arrangements Two Concentric TerminationsEight Concentric Terminations Power Vent Horizontal Venting ArrangementsDirect Vent Horizontal Direct Vent Vertical Vent Horizontal Intake Direct Vent Horizontal Vent Vertical IntakeDirect Vent Horizontal Concentric Power Vent Termination Clearances Sidewall Power VentDirect Vent Termination Clearances Sidewall Direct VentInstallation Instructions Water Heater InstallationCondensate Drain Installation Installation NotesSupply Gas Line Sizing Metric Units Supply Gas Line InstallationGas Line Sizing Supply Gas Line Sizing U. S. UnitsSupply Gas Regulator Installation Gas Line Leak TestingGas Line Connection Connecting An External Supervisory Control Electrical WiringPower Supply Connections Enable/Disable CircuitThermometers not Supplied Water Piping DiagramsWater Line Connections Valve Discharge PipeThermostat Control Temperature RegulationHigh Temperature Limit Control ECO High Temperature ApplicationsUser Input Buttons Control System OperationOverview Control System NavigationIcon Description Status IconsMenu Description Operating StatesState Description Control System MenusDescription/Action Display User Settings & Control System MenusUpdate Cancel Back HelpChange Back Help Heater Information Description/Action Display Display Settings Description/ActionYES Back AdvancedView Back Help ECOName UpdateService Contact Information Select Back HelpStart Up Prior to Start upInitial Start Up Supply Gas Pressure Adjustment Multiple Appliance InstallationsManifold Gas Pressure Adjustment To Turn Off Gas High Altitude InstallationsChecking The Firing Rate 1050 = 300,000 Btu/hr 87.9 kWLighting The Water Heater Lighting & Operation LabelHoneywell Troubleshooting Installation ChecklistSequence Of Operation Water is heated to VAC Gas Valve Sequence Of Operation Flow ChartClosed by control system Fault Msg is displayed Pre-Purge cycleMomentary Ignition Operational ProblemsInstallation Errors Rough Starting, Rough OperationFault And Alert Conditions Possible Causes Check/Repair Displayed Fault/Alert Message Fault And Alert MessagesNo Anode Voltage Blower Prover FailureDraining And Flushing MaintenanceMaintenance Schedule GeneralFilling The Water Heater Sediment RemovalLime Scale Removal Vent System Powered Anode RodsDrain Valve and Access Panels Temperature-Pressure Relief Valve TestCCB Central Control Board Layout DiagramsUser Interface Modul SUF 130 300 Wiring DiagramUser SUF 130 400, 500 Wiring DiagramCirculation Pump Wiring Diagrams Water Piping Diagrams Temperature & Pressure Tank Temperature ALT. Cold Water State Storage Tank Water Piping Diagrams Line Temperature Control HOT Water Outlet Pipe T&P to Open Drain Finished Floor Limited Warranty