Bradford-White Corp EF operation manual Concentric Vent Side Wall Attachment

Page 33

NOTICE

Position termination where vent vapors will not damage plants/shrubs or air conditioning equipment.

Position termination where vent vapors will not be adversely affected by wind condition.

Position termination where it will not be damaged or be subjected to foreign objects.

Position termination where vapors will not be objectionable.

3.Cut the recommended 5 inch (12.7 cm) diameter hole.

4.Partially assemble vent kit.

a.Cement Y concentric fitting to larger diameter kit pipe. (See Figure 20).

b.Cement rain cap to smaller diameter kit pipe. (See Figure 21).

5.Install concentric Y fitting and pipe assembly through the structure’s hole and field-supplied roof boot/flashing. Do not allow insulation or other materials to accumulate inside pipe assembly when installing through the hole.

6.Install rain cap and small diameter pipe assembly in concentric Y fitting and large pipe assembly. Ensure small diameter pipe is cemented and bottomed in concentric Y fitting.

7.Secure assembly to structure as shown in Figure 23A. Ensure clearances as shown in Figure 23A.

Figure 23A. Concentric Vent Side Wall Attachment

8.Cement water heater combustion-air and vent pipes to concentric Y fitting termination assembly. See Figure 23A & 23B for proper pipe attachment.

9.Operate water heater through one cycle to ensure combustion-air and vent pipes are properly connected and sealed to concentric vent termination connections.

33

Image 33
Contents What to do if YOU Smell GAS With Troubleshooting GuideTable of Contents Page Do not Operate the Appliance Until the Leakage is Corrected If YOU Smell GASDimensions Inches Section II SpecificationsSection III General Information FeaturesTemperature and Pressure Relief Valve Condensate Elbow With Trap Dishwashing Machine RequirementsSection IV Installation Instructions Minimum Clearance To Combustible Material UnpackingRemove Crate Recommended Minimum Clearances For Service AccessAIR Requirements LocationMechanical Exhausting of Room AIR Unconfined SpaceChemical Vapor Corrosion Typical Installation IllustrationTypical Two Water Heater Connection Section V Water Connections Instructions for ConnectionsScalding Alternate Space Heating Water Connections Approximate TIME/TEMPERATURE Relationships in ScaldsSection VI Venting Approved Venting Materials Venting Direct Vent InstallationCanadian US Installations2 Installations1 Clearance above Direct Vent Terminal Clearances Page Typical Horizontal Direct Vent System Typical Vertical Direct Vent System Installation Determining required vent length Power Vent InstallationPage Typical Horizontal Power Vent System Typical Vertical Power Vent System Installation Power Vent Maximum Vent Length Multiple INTAKE/EXHAUST Terminal Separation Distances Dimensional Layout of Concentric Vent Kit Concentric Vent Terminal Installation ProcedureRain Cap to Small Vent Pipe Ass’y Concentric Vent Side Wall Attachment Vent Pipe Preparation ModelsSection VII GAS Connections Initial PreparationSelection of Materials GAS Pressure Regulation GAS Meter Size Natural Gases onlySection Viii Electrical Connections Wiring Diagram and SchematicGeneral Instructions Section IX Operating InstructionsTo Fill the Water Heater Sequence of OperationLighting Instructions Temperature AdjustmentSight Glass Location Burner Flame CheckMaintenance Schedule Section X MaintenanceGeneral Flushing Water HeaterDraining Water Heater Filling Water HeaterSediment and Lime Scale Removal To inspect or replace an anode Anode Inspection and ReplacementVent and AIR Intake System Drain Valve and Tank Access PanelCombustion System Inspection Section XI Troubleshooting GuideEF Series Water Heater Section XII Parts ListCombustion Surround Assy Ignition Control Assy