3. INSTALLATION
3.1Mounting Requirements
IMPORTANT: To obtain the best return signal from the product level it is recommended to mount the MT2000 cou- pler directly into the top of the vessel if the vessel material is metal, or into a metal plate if the vessel is
CAUTIONS:
1.The housing cover can only be removed when the unit is installed in a
2.Tanks constructed of concrete additionally require probe mountings be: a. 1 ft. / 0.3 m from wall with up to 20 ft. / 6.1 meter measuring length. b. 2 ft. / 0.61 m from wall over 20 ft. / 6.1 meter measuring length.
CORRECT | INCORRECT |
FigureFigure3.13‑1
7 |