| 3. Label and remove the wires from the switch. With test |
REPLACEMENT | instrument check across the terminals of the switch. With the |
(Continued) | switch in the on position, the circuit should be closed. With the |
| switch in the off position, the circuit should be open. If the |
| switch is defective, replace by continuing with this |
| procedure. Figure |
Figure
4.With wires removed from the switch, push in on tabs on the switch and remove switch from front of switch box cover. Figure
5.Push new switch into panel and reconnect wires.
Figure
REPLACEMENT main burner. The valve has two
TO AVOID PERSONAL INJURY OR PROPERTY
DAMAGE, BEFORE STARTING THIS
PROCEDURE, MOVE THE MAIN POWER SWITCH
TO THE OFF POSITION. DISCONNECT THE MAIN
CIRCUIT BREAKERS AT THE CIRCUIT BREAKER
BOX OR UNPLUG SERVICE CORD FROM WALL
RECEPTACLE. TURN OFF THE MAIN GAS
SUPPLY TO THE FRYER AND DISCONNECT AND
CAP THE MAIN SUPPLY LINE TO FRYER, OR
POSSIBLE EXPLOSION COULD RESULT.