Power Supply Connection

Connect the 16.5 Volt AC power supply to the control of the LABS cryostorage system; then plug the power supply into a surge protected 110/120 VAC outlet.

KRYOS Control Field Installation

1.Unplug power from old unit.

2.Close liquid nitrogen supply at valve.

3.Remove 4 Phillips head screws from rear of interface display box.

4.Remove controller face from interface display box.

5.Finish face removal by disconnecting plug and ground wire.

6.Remove 2 Phillips head screws from the old control located underneath the tabletop.

7.Withdraw old controller from underneath table top, noting how the controller body has been resting on outer upper head.

8.Unplug all connectors and wires and set panel aside.

9.Disconnect supply hose from solenoid valve.

10.Remove old solenoid.

11.Remove spiral wire wrap.

12.Mark old sensor locations with electrical tape

13.Measure and make note of the “Start Fill”, “Stop Fill” and temperature sensors from the bottom of the appropriate sensor tube. You will need this information to set up the new controller.

14.Remove old sensor wires.

15.Calibrate new KRYOS control to new temperature sensor.

16.Reverse procedure to install KRYOS control.

10

Image 10
Contents Labs TW-357 REV E Installation Table of ContentsKeep Equipment Area Well Ventilated Safety Precautions for Liquid NitrogenExtreme Cold Cover Eyes and Exposed Skin Liquid Nitrogen SystemDispose of Waste Liquid Nitrogen Safely Freight Damage PrecautionsElectrical General Information Text Format NotationLabs Cryostorage Specifications Kryos Specifications Liquid Nitrogen Supply Connection InstallationUnpacking and Inspection Repackaging for ShipmentPower Supply Connection Kryos Control Field InstallationOperation Initial FillControl Components Sensor AssemblyInterface Panel Remote Alarm Lid SwitchBattery Backup Solenoid ValveLiquid Phase Storage Operating ParametersAdding an Inventory Control System Thermocouple PositioningRacks are not Square Orientation is Important Inventory Control System Layouts Labs Cryostorage SystemLABS-80K LABS-40K Fenwal 4R59953 Blood Bag Rack Arrangements Fenwal 4R5462 9955 Blood Bag Rack Arrangements Introduction PowerControl Operation Normal Fill CycleMain Display Screen Menu SystemHigh Temperature 4.1 Valve Open Test Temperature System Temperature Thermocouple SelectCalibrate Temperature Help ScreensAlarms and Error Conditions Sensor TypeTest Alarms System AlarmsLogging Error Logs Dump LogsErase Logs Temperature LogsSystem Logs SecurityTemperature Control Settings Lid Switch SetupControl By Temperature Control TemperatureUser Access Logs Serial Communications and RS-232 SettingsTime and Date Set Valve Monitoring Control RangeFreeze-Guard Options Valve Open DurationDisplay Brightness Control On Battery Backup VersionSolenoid Valve About this ControlBattery Life Interface SoftwareStrainer Cleaning Instructions MaintenanceDefrosting Your LAB-Series CryoStorage System Cleaning Your Taylor-Wharton CryoStorage System Making Adjustments to the Labs Kryos Sensor Assembly Offset Value Default Start Fill / Stop Fill Default Auto DefogKryos Kryos V9.0 & Kryos V9.0B Level Readings Units of measureRemoving/Installing the Solenoid Valve Ohms to 18 K ohmsSensor Plug Schematic Pin View SchematicsLabs Plumbing Assembly Plumbing AssemblyController Will Not Turn on TroubleshootingSymptoms Indicates High Liquid LevelIndicates Low LN2 Supply Temperature reading 10 to 20 degrees warmIndicates Open Sensor Fill Solenoid Cycles On and Off Lid Open AlarmQCF Quick Chill Feature Will Not Operate Fill Solenoid Makes Humming NoisePush Buttons Will Not Respond Defog Feature Will Not OperatePower Failure Alarm Liquid Level Readout is IncorrectFactory Settings Replacement Parts Level Controller Electrical/Mechanical Parts80K/40K/20KTaylor-Wharton Technical Services. Phone 800-898-2657 Fax Harsco Corporation