Andrew manual ES45T-R Reflector Assembly Step

Page 41

ES45T-R Reflector Assembly

Step 11

Step 12

Step 13

Remove small portion of foam padding from reflector packing crate and install under bottom portion of reflector assembly to prevent reflector damage during hoisting proce- dure. Position man at bottom of reflector/backstructure to guide assembly during hoist- ing procedure.

Hoist reflector/backstructure assembly to vertical position until upper joints of main trian- gle assembly contact pipe and straddle two locator bars on support and elevation assembly (P/N 49635) as shown in Figure 49.

Figure 49

Install two U-bolts at each pivot bracket of main triangle assembly.

Use 1/2 inch (13 mm) lockwashers and nuts.

Securely tighten U-bolts allowing for some reflector movement

41

Installation Procedures

Image 41
Contents Meter ESA Table of Contents Introduction IntroductionProprietary Data Information Assistance Technical Customer Service CenterOverview Content How to Use This ManualGetting Started OverviewTool Size Qty Recommended ToolsGetting Started Main Reflector Assembly Getting Started Overview Foundation Preparation Installation ProceduresA-325 Tensioning Tensioning StepTripod Mount Step 300747 Step Upper Step Step Step Step Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Step ES45T-R Reflector Assembly Reflector Leveling Procedure Step ES45T-R Reflector Assembly ES45T-R Reflector Assembly Step Feed Strut Assembly ES45T-R Reflector Assembly ES45T-R-1 Back Structure ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Installation Procedures ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Installation Procedures ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Installation Procedures ES45T-R Reflector Assembly Step Feed Support Assembly Step ES45T-T Reflector Assembly ES45T-T-1 Reflector Step ES45T-T Reflector Assembly Step Top Match Markings Reflector Segment Top Match Markings Capscrew Hardware 49693 Joining Plate ES45T-T Reflector Assembly Step ES45T-T Reflector Assembly Step Reflector Leveling Procedure Line of Sight Steel Rule Elevation Reflector X 1-1/2 ES45T-T Reflector Assembly Step Feed Strut Assembly ES45T-T Reflector Assembly ES45T-T-1 Back Structure Step ES45T-T Reflector Assembly Step Installation Procedures ES45T-T Reflector Assembly Step ES45T-T Reflector Assembly Step Installation Procedures ES45T-T Reflector Assembly Step ES45T-T Reflector Assembly Step Installation Procedures ES45T-T Reflector Assembly Step Step Feed Support/Strut Assembly Polarization Adjustment Step Medium Modular Mount Operation Overview Acquiring a Satellite StepStep Step Step Manual Actuator Assembly Removal Step Preventive Maintenance Overview General Cleaning Electrical PartsPreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Pedestal Mount Bearing Pad Adjustment Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Antenna Lubrication Chart