Step 1

Step 2

Step 3

Step 4

Check security of antenna mounting and interconnecting assembly hardware. Be cer-

tain all electrical grounding connections (including cross-axis grounding straps) and intact and secure, not corroded or broken. Thoroughly clean any noticeable corroded portions of grounding cables, unplated portion of universal terminals and corresponding mounting surfaces with a wire brush. Replace rather than tighten any loose A-325 struc- tural hardware. The hardware distorts at initial installation and once loosened will not maintain the required high strength friction connection. All other assembly and installa- tion hardware should be tightened to its original torqued condition. When installing new structural hardware, do not use a wrench with a lever arm longer than two feet.

Examine painted aluminum and galvanized surfaces and touch-up where required.

At the conclusion of the installation procedure and prior to turning the system over to the station facility, an installation acceptance check-off sheet was prepared and duly signed off if installed by an Andrew crew. Part of this check-off included voltage readings retak- en to determine if proper voltage was available. Current readings were also taken as a reference for future comparison to serve as a troubleshooting aid in determining possi- ble equipment degradation and shortened life. Any current reading taken during the fol- lowing procedure that significantly varies by more than five percent from the preestab- lished reference values necessitates trouble shooting the particular system involved to determine the cause and required corrective action.

Approximately every three months and during a period of down time, disconnect as applicable the RF transmitter and all power supplies. The main disconnect switch in the main load center box at the antenna site must be in the ON position and the detachable hand-held controller assembly must be plugged in.

Open the outer local control/motor drive controller door at the antenna site to gain access to the conductors supplying power to the azimuth, elevation and polarization drive motors. Turn the primary power disconnect switch to the ON position.

Turn the Az/El speed switch to the FAST position. Turn the AZIMUTH EAST/WEST switch to either position and while the antenna is rotating, carefully use a clamp-on ammeter in accordance with the ammeter manufacturer’s instructions to take current readings off each of the power conductors (phases) connected to the main terminal block at the bottom of the panel. Record the current draw in the equipment log and com- pare the readings to the reference values entered in the installation/acceptance check- off. If the readings differ significantly, refer to the appropriate troubleshooting information and perform the applicable corrective action. Then take voltage readings off each of the three conductors; the readings should agree with each other - within two percent. Turn the AZIMUTH switch to OFF.

Repeat preceding step (3) with the AZIMUTH EAST/WEST switch in the alternate oper- ating position.

77

Preventive Maintenance

Image 77
Contents Meter ESA Table of Contents Introduction IntroductionProprietary Data Information Assistance Technical Customer Service CenterOverview Content How to Use This ManualGetting Started OverviewTool Size Qty Recommended ToolsGetting Started Main Reflector Assembly Getting Started Overview Foundation Preparation Installation ProceduresA-325 Tensioning Tensioning StepTripod Mount Step 300747 Step Upper Step Step Step Step Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Step ES45T-R Reflector Assembly Reflector Leveling Procedure Step ES45T-R Reflector Assembly ES45T-R Reflector Assembly Step Feed Strut Assembly ES45T-R Reflector Assembly ES45T-R-1 Back Structure ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Installation Procedures ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Installation Procedures ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step ES45T-R Reflector Assembly Step Installation Procedures ES45T-R Reflector Assembly Step Feed Support Assembly Step ES45T-T Reflector Assembly ES45T-T-1 Reflector Step ES45T-T Reflector Assembly Step Top Match Markings Reflector Segment Top Match Markings Capscrew Hardware 49693 Joining Plate ES45T-T Reflector Assembly Step ES45T-T Reflector Assembly Step Reflector Leveling Procedure Line of Sight Steel Rule Elevation Reflector X 1-1/2 ES45T-T Reflector Assembly Step Feed Strut Assembly ES45T-T Reflector Assembly ES45T-T-1 Back Structure Step ES45T-T Reflector Assembly Step Installation Procedures ES45T-T Reflector Assembly Step ES45T-T Reflector Assembly Step Installation Procedures ES45T-T Reflector Assembly Step ES45T-T Reflector Assembly Step Installation Procedures ES45T-T Reflector Assembly Step Step Feed Support/Strut Assembly Polarization Adjustment Step Medium Modular Mount Operation Overview Acquiring a Satellite StepStep Step Step Manual Actuator Assembly Removal Step Preventive Maintenance Overview General Cleaning Electrical PartsPreventive Maintenance Antenna Preventive Maintenance Drive System Voltage Current Checks Step Step Pedestal Mount Bearing Pad Adjustment Preventive Maintenance Jackscrews/Motors Gear Motor/Housing Fill Drain Requirements Antenna Lubrication Chart