PB Heat 211A manual Preinstallation, Accessibility Clearances, Combustible Construction Clearances

Page 4

PREINSTALLATION

1. PREINSTALLATION

NOTICE

The equipment shall be installed with those installation requirements of the authority having jurisdiction or, in the absence of such requirements, to the current edition of the National Fuel Gas Code, ANSI Z223.1/NFPA 54 and/or CAN/CGA B149 Installation Codes.

Where required by the authority having jurisdiction, the installation must conform to American Society of Mechanical Engineers Safety Code for Controls and Safety Devices for Automatically Fired Boilers, ASME CSD-1.

Read these instructions carefully before beginning the installation.

Study the control folder and consult drawings.

A shipping list is enclosed with each boiler, listing the items packed at the factory. Check the list as you unpack parts. If any parts are missing or damaged, report the problem to the delivering carrier immediately.

Figure 1.1: Clearance Requirements

A.ACCESSIBILITY CLEARANCES

1.The following recommendations allow for reasonable access to the boiler. Local codes or special conditions may require greater clearances.

a.For servicing the boiler: provide 48" (1219 mm) between the control manifold and adjacent wall or other appliance.

b.For access to draft hood or passage to access the boiler control manifold(s): provide 48" (1219 mm) between the side of the boiler and adjacent wall or other appliance.

c.See Figure 1.1. Clearances with an “S” are minimum clearances for service accessibility.

B.COMBUSTIBLE CONSTRUCTION CLEARANCES

1.This boiler is design certified for the following clearances to combustible construction.

• 24" (610 mm) between the front, top, sides and rear of the jacket.

6" (152 mm) from steam and hot water pipes

6" (152 mm) from vent connector

See Figure 1.1. Clearances with a “C” indicate minimum clearances from combustible construction.

C.AIR FOR COMBUSTION AND VENTILATION

1.Adequate combustion air and ventilation air must be provided for this appliance in accordance with the section of the National Fuel Gas Code entitled, “Air for Combustion and Ventilation” or applicable provisions of the local building code. Subsections 2 through 8 as follows are based on the National Fuel Gas Code requirements.

2

Image 4
Contents Series 211A Table of Contents Using this Manual Follow the Piping GuidelinesControls Special Attention BoxesPreinstallation Accessibility ClearancesCombustible Construction Clearances AIR for Combustion and VentilationRequired Volume fan = 15 ft Required Volume other =21 ft Btu/hr 22 cm 2 per 2000 W of total rated Input for all appliances in the space. SeeChimney or Vent WhereMechanical Combustion Air Supply Combustion Air DuctsVent Sizing Exterior VentsCombined vent breeching Installation Survey Boiler SettingWater Quality and MAKE-UP Boiler Foundation Layout Assemble the Base Base AssemblyCrate Items Install the Pilot Burners For 211A-04 through 211A-08 OnlyBase Front and Back Panel Crates Model Overall LengthTypical Gas Manifold and Pilot Line Assembly Pilots Total Natural Gas Only Propane Gas Only Model NumberBurners Preparation Place the Boiler SectionsPlacing the Sections Assembling Sections on Base Hydrostatic Test the Boiler Align Sections VerticallyInstall the Flue Collector Do not tighten yetBoiler Position Supply Piping Pipe the BoilerReturn Piping Pipe the Boiler Multiple Boiler Installations Boiler Header End RisersEqualizers Model SizePiping Multiple Boilers, Typical, Gravity Return Systems Install the Jacket & Draft Hood Apply Cleanout Cover PlatesPrepare the Parts Apply Jacket END AssembliesApply Jacket TOP Panels Apply Lower END PanelsApply Plates and Labels Top Panel GG-6024 Carton Contents Sub-Assembly Part Number Quantity Jacket Assembly Sequence Carton Numbers and Locations 13C Install GAS Train Install Vent and Bleed PipingConnect GAS Piping Connect Pilot GAS TubingInstall GAS Supply Piping Test GAS Supply PipingPipe Length 4 Pipe 2 Pipe Specific Gravity Multiply Capacity byInstall Controls and Trim Install Safety Valves Install LOW Water CUT-OFFSInstall Blowdown Valves Install Pressure ControlsPressure Control Piping Fittings Included with Boiler Standard Float Type COntrol, Model 67PE2 Optional Float Type Pump Control/Low Water Cut-Off, Model Application of 51 Feeders Wire the Boiler Connect Supply WiringInstall Control Wiring Prepare Remaining ControlsTypical Wiring Standard Controls Low Voltage Gas Valves Typical Wiring Standard Controls 120-Volt Gas Valves Starting the Boiler Check Boiler Controls Clean the BoilerMeter reading. Rate, Btu/Hr = F x H x To Light the Boiler To Shut Down the Boiler Lighting Instructions TypicalPilot Flame Failure Operation & Maintenance Placing Boiler in Operation Pilot and Burner FlamesMonthly Maintenance Annual MaintenanceWeekly Maintenance Daily MaintenanceTroubleshooting Service Tips Problem Possible Cause Suggested RemedyCorrect Piping Boiler Ratings & Dimensions Boiler Rating InformationBoiler Ratings & Dimensions Chart continues on Series 211A Steam Boiler DimensionsSeries 211A Steam Boiler Dimensions Repair Parts Series 211A Description Part Selection Information Stock CodeBase Front Panel Cover Plate 26 660 mm Wide Base Panel Boiler Assembly Base Assembly Page Series 211A