Woods Equipment S106Q-3, S106-3, S105Q-3, S105-3 manual Crossbar

Page 22

Removing Gearbox from Cutter

Remove safety shielding. Remove top cover and siphon gear lube from gearbox. Remove drive lines. Remove crossbar (see Crossbar Removal). Remove gearbox from cutter.

Gearbox Assembly - Cutter Head

Press cups into main housing until they seat against machined shoulders. Press bearings onto shafts until they seat against machined surface next to gear.

Install vertical shaft into gearbox housing, and horizon- tal shaft into horizontal housing, then press bearings on with sleeve until all free play is removed (similar to adjusting front wheel bearings on an automobile). Check by spinning housing. It should turn freely.

If bearings are too tight, hold housing and rap gear shaft with a lead hammer. Do not leave bearings adjusted too tight. Proper adjustment is essential to good bearing lift.

Install the vertical and horizontal shaft seals.

After seating the seal on the vertical shaft, depending on when the gearbox was manufactured there are two options:

1.Place a 1-5/8 ID x 2-31/32 OD washer over the shaft and into the neck of the gearbox housing. You will need to tap this washer in place until the gearbox is installed on the cutter.

2.Press a 1-5/8 ID x 2-3/4 OD washer and a washer retainer firmly against the seal.

Bearing adjustment on the vertical shaft is set with the sleeve and maintained with proper crossbar shimming.

Bearing adjustment on the horizontal shaft is set with the sleeve and maintained by tightening a large hex nut against the sleeve, installing a dowel plug in the nut and tightening a set screw against the dowel. Prior to installing the nut, clean the threads on the nut and the shaft and apply two drops of Loctite on the threads.

Horizontal Housing Installation

With the housing assembled, place the square O-ring on the housing and install to gearbox, tighten the four bolts evenly. Turn the gears against each other to determine how they rotate. They should turn freely. If there is a spot where they turn hard, install a gasket between the horizontal housing and gearbox.

Gearbox Assembly - Input

Press cups into main housing until they seat against machined shoulders. Press bearings onto shafts until they seat against machined surface next to gear.

Install input shaft into gearbox housing, then press bearing on with sleeve until all free play is removed

(similar to adjusting front wheel bearings on an auto- mobile). Check by spinning housing. It should turn freely.

If bearings are too tight, hold housing and rap gear shaft with a lead hammer. Do not leave bearings adjusted too tight. Proper adjustment is essential to good bearing life.

Install input shaft seal.

Bearing adjustment on the input shaft is set with the sleeve and maintained by tightening a large hex nut against the sleeve, installing a dowel plug in the nut, and tightening the set screw against the dowel. Prior to installing the nut, clean the threads on the nut and the shaft and apply two drops of Loctite on the threads.

Output Shaft Installation

Place the square O-ring on the housing and install to gearbox, tightening the four bolts evenly. Turn the gears against each other to determine how they rotate. They should turn freely without bearing end play. If there is a spot where they turn hard, install a gasket between housing and gearbox. If there is bearing end play, remove gasket.

Install seals on both ends of shaft.

CROSSBAR

Removal

For crossbar removal, it is necessary to gain access to bottom side of cutter. Raise cutter and securely block up. You may use either puller screw (6) or a small hydraulic jack to remove crossbar. See Figure 6.

Loosen bolts on crossbar clamp. Remove bolt retaining washer by prying washer up and breaking weld. Remove washer and bolt. Remove blades from cross- bar (see page 18). Assemble clevises (1) to each end of crossbar, utilizing blade pins, spacers, keyhole plates and blade pin clips.

Position tube assembly (5) with threaded nut toward crossbar. Install pad assembly (4) in nut on square tube assembly.

Bolt square tube assembly to the clevises using 5/8" x 4-1/2" bolts (2). Insert puller screw assembly (6) into square tube assembly (5) and tighten against pad assembly (4) an gear shaft as shown. For best results, strike head of puller screw with a sledge hammer while tightening screw with a wrench. If crossbar has been installed with Loctite, it may be necessary to apply heat (greater than 500°F) to crossbar to break Loctite bond.

22 Dealer Service

29977 (Rev. 1/23/2009)

 

 

Image 22
Contents Ditch Bank Rotary Cutter Introduction To the DealerTable of Contents Specifications General InformationFree Mower Safety Video SafetyTraining Package for Rotary Mowers/Cutters-English Training Package for Rotary Mowers/Cutters-English/SpanishTraining Safety RulesInstallation PreparationTransportation OperationMaintenance StorageSafety & Instructional Decals Replace Immediately If DamagedSafety Decals from previous Be Careful General Tractor Requirements OperationOperation Tractor Front END StabilityOptional Tailwheel Adjustment Cutting Height Attitude AdjustmentSide Skid Adjustment Attaching Cutter to TractorCutter Head Hydraulic Lift General MowingBlade Selection Tractor and Cutter OperationBrush and Ditch Bank Mowing TransportOwner Service Owner ServiceLubrication Blade Servicing Blade InstallationSlip Clutch Adjustment Blade RemovalAfter Each Use CleaningChain Shielding Repair Periodically or Before Extended StorageTrouble Shooting Trouble ShootingGearbox Maintenance Dealer ServiceDealer Service Seal InstallationCrossbar Installation ShimmingDealer Service Joint Disassembly Universal Joint RepairJoint Assembly Open-Center or Closed-Center SPRING-LOADED Wheel Yoke AdjustmentSPOOL, 3-WAY Valve OperationPRE-DELIVERY Check List Dealer Check ListDealer Check Lists Delivery CheckDrive Shaft Installation AssemblyAssembly DP1Mounting A-Frame on Center Frame Lift Cylinder InstallationLift Link Installation Attaching Cutter Head to Center FrameSide Shield Installation Side Drive Installation FigureCutter Head Gearbox Shield Installation Check Chain Installation Tire and Skid Assembly InstallationChain Shielding Installation Counterweight Installation OptionalTailwheel Optional Control Valve Installation OptionalStump Jumper Optional Assembly Parts Index PartsCenter Section Assembly Hardware Cutter Head Section Assembly Early S106-3 Tubular Side Drive Assembly Cutter Head Gearbox Assembly Input Gearbox Assembly Front Half of 2-JOINT Drive 35R Standard DriveSlip Clutch Assembly Integral U-JOINT Shielding Used on Earlier Machines Joint Shielding Plastic Used on Later Machines2 Bore & 8 Stroke Hydraulic Cylinder Part QTY DescriptionPiston SPOOL, 3-WAY Valve Optional Pneumatic Tailwheel Assembly Pneumatic Tire Assembly for Tailwheel HUB Assembly for Pneumatic TailwheelTailwheel Assembly Gauge Wheel & Tailwheel HUB & Axle Assembly Tailwheel & Gauge Wheel AssemblyStandard 1 Shaft Heavy-Duty 1-1/4 Shaft Crossbar Puller Assembly Stump Jumper OptionalAppendix Bolt Torque ChartSAE Series Torque Chart Metric SeriesBolt Size Chart AbbreviationsIndex IndexWarranty South Illinois Route Post Office Box Oregon, Illinois