2.With snap rings removed, support drive in vise, hold yoke in hand and tap on yoke to drive cup up out of yoke. See Figure 16.

Figure 16

3.Clamp cup in vise as shown in Figure 17 and tap on yoke to completely remove cup from yoke. Repeat step 2 & step 3 for opposite cup.

Figure 17

4.Place universal cross in vise as shown in Figure 18 and tap on yoke to remove cup. Repeat step 3 for final removal. Drive remaining cup out with a drift and hammer.

Figure 18

U-Joint Assembly

Figure 19

1.Place seals securely on bearing cups. Insert cup into yoke from outside and press in with hand pressure as far as possible. Insert journal cross into bearing cup with grease fitting away from shaft. Be careful not to disturb needle bearings. Insert another bearing cup directly across from first cup and press in as far as possible with hand pressure.

2.Trap cups in vise and apply pressure. Be sure journal cross is started into bearings and continue pressure with vise, squeezing in as far as possible. Tapping the yoke will help.

3.Seat cups by placing a drift or socket (slightly smaller than the cup) on cup and rap with a

26 Dealer Service

29977 (Rev. 1/23/2009)

 

 

Image 26
Contents Ditch Bank Rotary Cutter Introduction To the DealerTable of Contents Specifications General InformationFree Mower Safety Video SafetyTraining Package for Rotary Mowers/Cutters-English Training Package for Rotary Mowers/Cutters-English/SpanishTraining Safety RulesInstallation PreparationTransportation OperationMaintenance StorageSafety & Instructional Decals Replace Immediately If DamagedSafety Decals from previous Be Careful General Tractor Requirements OperationOperation Tractor Front END StabilityOptional Tailwheel Adjustment Cutting Height Attitude AdjustmentSide Skid Adjustment Attaching Cutter to TractorCutter Head Hydraulic Lift General MowingBlade Selection Tractor and Cutter OperationBrush and Ditch Bank Mowing TransportLubrication Owner ServiceOwner Service Blade Servicing Blade InstallationSlip Clutch Adjustment Blade RemovalAfter Each Use CleaningChain Shielding Repair Periodically or Before Extended StorageTrouble Shooting Trouble ShootingGearbox Maintenance Dealer ServiceDealer Service Seal InstallationCrossbar Installation ShimmingDealer Service Joint Disassembly Universal Joint RepairJoint Assembly Open-Center or Closed-Center SPRING-LOADED Wheel Yoke AdjustmentSPOOL, 3-WAY Valve OperationPRE-DELIVERY Check List Dealer Check ListDealer Check Lists Delivery CheckDrive Shaft Installation AssemblyAssembly DP1Mounting A-Frame on Center Frame Lift Cylinder InstallationLift Link Installation Attaching Cutter Head to Center FrameCutter Head Gearbox Shield Installation Side Drive Installation FigureSide Shield Installation Check Chain Installation Tire and Skid Assembly InstallationChain Shielding Installation Counterweight Installation OptionalStump Jumper Optional Control Valve Installation OptionalTailwheel Optional Assembly Parts Index PartsCenter Section Assembly Hardware Cutter Head Section Assembly Early S106-3 Tubular Side Drive Assembly Cutter Head Gearbox Assembly Input Gearbox Assembly Front Half of 2-JOINT Drive 35R Standard DriveSlip Clutch Assembly Integral U-JOINT Shielding Used on Earlier Machines Joint Shielding Plastic Used on Later Machines2 Bore & 8 Stroke Hydraulic Cylinder Part QTY DescriptionPiston SPOOL, 3-WAY Valve Optional Pneumatic Tailwheel Assembly Pneumatic Tire Assembly for Tailwheel HUB Assembly for Pneumatic TailwheelTailwheel Assembly Standard 1 Shaft Heavy-Duty 1-1/4 Shaft Tailwheel & Gauge Wheel AssemblyGauge Wheel & Tailwheel HUB & Axle Assembly Crossbar Puller Assembly Stump Jumper OptionalAppendix Bolt Torque ChartSAE Series Torque Chart Metric SeriesBolt Size Chart AbbreviationsIndex IndexWarranty South Illinois Route Post Office Box Oregon, Illinois