Machine-Side Loaders

Quick Start Guide

Turning on the loader:

Locate the power switch on the left side of the control box and move to the ‘ON’ position.

Setting the loader convey time:

It is only possible to set the convey time when the unit is not conveying material

1.Disconnect the flapper valve switch from the control box, by unscrewing the plastic retainer ring, and pulling the plug straight down.

2.Adjust the conveying time by pressing the up arrow button (the center LED on the display lights up). Convey time can be adjusted from 1 to 99 seconds, incrementally.

3.Make note of the conveying level and adjust time accordingly .

Please Note: The material level inside the loader should never exceed the material inlet.

Setting the line clearing time or purge time:

It is only possible to set the purge time when the unit is not conveying material

1.Press and hold the “change-over” key, (bottom LED on the display lights up)

2.While holding the change-over key, adjust the purge time by pressing the up arrow. Purge time can be adjusted from 0 to 99 seconds.

If no line clearing valve has been installed, be sure to set purging time to 0.

Make note of the purge time and adjust for optimum efficiency

Connecting the proportioning valve:

Control and power of the proportioning valve is supplied through a 4-wire control connection.

Brown

Pos. Power

X7, L

Blue

Neg. power

X7, N

Black

Line signal

X7, ZKW

Green/Yellow

–Ground

X3

3.Remove the control box face, and locate the removable plug in the bottom of the box.

4.Remove the plug and feed the wire of the proportioning valve through the empty hole.

5.Tighten the lock nut inside, position the wire length for optimum use and tighten the lock nut on the outside.

6.Strip the wires so that 1/4” of wire is showing, for connection to terminal blocks.

7.Remove the loader control face.

Upon removal of the loader control face you will see two printed circuit boards. One board on the reverse of the control face, and the other mounted inside the control box. The ground wire will connect to the terminal block X3 on the back of the control face. The other three wires connect to terminal block X7 inside the control box, in order from left to right Brown, Blue, then Black. Please refer to the schematic in the back of the manual.

Connecting Material Lines:

Component 1 – connected to the intake port furthest from the air cylinder (regrind)

Component 2 – connected to the intake port closest to the air cylinder (virgin)

Setting the ratio:

When the loader motor is not running, pressing the up arrow key will change the percentage of component 1. This can be set from 0% to 99%

Set the cycle switching:

Press and hold the percentage key. Then by pressing the up arrow, you will be selecting the cycle time period in increments of 5 seconds.

Therefore, if the convey time is 60 seconds and you select a cycle time period of 10 seconds the valve will switch a total of 6 times.

Quick Start Guide

Image 76
Contents Operating Instructions Machine-Side Hopper Loader SSE Series Machine-Side Hopper Loaders Iii Machine-Side Hopper Loaders Parts and Service Department Table of Contents Accessories 11-1 Electrical manual 12-1 General instructions Machine-Side Hopper Loaders Legal basis Explanations and informationFields of applications Page Safety instructions For your safety GeneralAssembly Maintenance OperationFor the operating safety of the equipment Page Transport, assembly and storage Transport and packing AssemblyStorage Assembly instructions Unpacking Liter modelInstalling the dump valve sensor Dump valve and sensorAttaching the pickup wand Mounting MountingMounting on the processing machine Mounting onto a machine hopperMounting onto mixing hoppers with lateral inlet Mounting onto DT 30 dosing stationElectrical connection Compressed air connectionInstallation of the optional proportioning valve X7, ZKWConnecting Material Lines Functional description Sequence of operation ControllerOperation Switching on the unit Checking the flexible hoseSetting the conveying time Setting the purge time optional Switching off the unit Initial operationPage Troubleshooting Alarms Maintenance Machine-Side Hopper Loaders Maintenance intervals Servicing the loader Changing the sealing ring of the outlet flapAdjusting the dump valve sensor Cleaning the unit Order numbers Filter cloth Wire cloth Installation Replacing carbon brushes at the motorMachine-Side Hopper Loaders Taking out of service, dismantling, disposal Disposal InstructionsTechnical data Specifications Liter model Brushless motor Loader Capacity Dimension Sheet Liter model Liter brushless model Spare parts list Parts breakdown, brush-type motor Parts lists, 2-liter model 10.2.1 V, 50 Hz10.2.2 V, 60 Hz 10.2.3 V, 50 Hz with active cleaning 10.2.4 V, 60 Hz with active cleaningParts list, 5-liter model 10.3.1 V, 50 Hz V6637210.3.2 V, 60 Hz V66378US Pos. Order no. Designation10.3.3 V, 50 Hz with active cleaning 10.3.4 V, 60 Hz with active cleaningParts breakdown and list, 5-liter model with brushless motor 10.5 V, 50 Hz Accessories Page Electrical manual Page Page Page Page Page Page Page Page Page Setting the loader convey time Quick Start Guide